Date filters select awards with transaction activity in the period. Amounts below are lifetime award obligations. IDV values remain separate.
MAXIMUM CONTRACT AMOUNT - K WORKDepartment of Defense$3.6M obligationsEnds Jun 25, 2026
MAXIMUM CONTRACT AMOUNT - K WORKDepartment of Defense$2.2M obligationsEnds Sep 30, 2026
PROJECT: HA-00011-6J. REPLACE AIR DUCTS IN B821. LOCATION CAMP CARROLL.Department of Defense$15.1K obligationsEnds Sep 14, 2026
[MATOC] REPAIR LEAKING ROOF, WALL AND FLOOR AT B354, CAMP CARROLL [PROJECT# HS-00064-5J]Department of Defense$383.2K obligationsEnds Oct 25, 2026
REPAIR FAILING EXTERIOR OF B2650, PIER#8 (WORK PLAN)Department of Defense$561.9K obligationsEnds Dec 19, 2026
REPAIR FAILED OR FAILING FIRE DEFICIENCIES IN B#800, 810, 820, CAMP WALKERDepartment of Defense$160.1K obligationsEnds Sep 19, 2026
REFINISH BASKETBALL COURT FLOOR AT B261, KELLY FITNESS CENTER, CAMP WALKERDepartment of Defense$48.7K obligationsEnds May 14, 2026
RENOVATE COMMAND CONFERENCE ROOM, MSC-K HQ BLDG. 388, CAMP CARROLL (PROJECT NO. HA-00001-3J)Department of Defense$126.4K obligationsEnds Apr 19, 2026
REPAIR BARRACKS, BLDG. #262 AT CAMP CARROLLDepartment of Defense$4.3M obligationsEnds Aug 21, 2026
REQUEST FOR PROPOSAL TO REPLACE DEFECTIVE HEATHT DETECTORS IN TWELVE (12) BSC BUILDINGS AT USAG DAEGU, INCLUDING VERIFICATION, REMOVAL, INSTALLATION, TESTING, AND COMMISSIONING…Department of Defense$27.4K obligationsEnds Jun 9, 2026
DPW, INSTALLATION OF BLDG TRANSCEIVER AT B1436 AND B1439, BUSAN SUPPORT FACILITY (BSF), SOUTH KOREA.Department of Defense$56.9K obligationsEnds Jul 17, 2026
REPLACE OLD WATER FOUNTAINS IN BARRACKS AND SLQ BUILDINGS AT CAMP CARROLL WITH NEW ADACOMPLIANT UNITS, INCLUDING REMOVAL, INSTALLATION, ELECTRICAL WORK, DEMOLITION, AND WALL…Department of Defense$59.8K obligationsEnds Aug 9, 2026
PROJECT TITLE: DPW, INSTALL SHOWER RODS, SLQ, CAMP WALKER AND CAMP HENRY, SOUTH KOREA (MATOC). PROJECT LOCATION: CAMP WALKER AND CAMP HENRY, SOUTH KOREA.Department of Defense$24.0K obligationsEnds Aug 14, 2026
INSTALL CURVED SHOWER RODS IN ALL SLQ CAMP CARROLLDepartment of Defense$25.8K obligationsEnds Jul 31, 2026
(MATOC) INSTALL CLOSETS IN ROOMS, B142 AND B143, CAMP CARROLLDepartment of Defense$65.3K obligationsEnds Jun 10, 2026
REPLACE VARIABLE AIR VOLUME (VAV) SYSTEM P-6004, USAG HUMPHREYSDepartment of Defense$1.8M obligationsEnds Sep 22, 2026
REPAIR VAV SYSTEM AT P-6006Department of Defense$1.8M obligationsEnds Nov 20, 2026
REPLACE VARIABLE AIR VOLUME (VAV) SYSTEM P-6001, USAG HUMPHREYSDepartment of Defense$1.8M obligationsEnds Sep 22, 2026
REPAIR FAILED AND MALFUNCTIONING HELIPAD LIGHTING CONTROL SYSTEM AND BROKEN FIELD LIGHTS AT CAMP WALKERDepartment of Defense$101.0K obligationsEnds Jan 23, 2026
REPLACE EXISTING DETERIORATED LIGHT FIXTURES AT VARIOUS FACILITIES AT CFA CHINHAE AND CNFK HQ BUSANDepartment of Defense$367.1K obligationsEnds Oct 31, 2025
REPLKACE VAV SYSTEM AT P-6005Department of Defense$1.8M obligationsEnds Oct 16, 2026
RCO DAEGU: INSTALLATION OF STAIRCASE AND HANDRAIL, B1020, FOS CARROLL. SEE ATTACHMENTS 0001 - STATEMENT OF WORK AND ATTACHMENT 0002 DRAWINGS.Department of Defense$45.7K obligationsEnds Jan 11, 2026
INSTALL PLATFORMS AT BLDG. 139, CAMP CARROLL AND BLDG. 1501, CAMP HENRYDepartment of Defense$88.3K obligationsEnds Dec 26, 2025
INSTALL FIRE SUPPRESSION SYSTEMS AT B520 CAMP CARROLL AND B720 CAMP WALKERDepartment of Defense$32.7K obligationsEnds Mar 26, 2026
REPAIR FAILING BREAK ROOM AND SHOWER ROOM AT B468, CAMP WALKER (PROJECT NO. J1-00062-4J)Department of Defense$261.9K obligationsEnds Jan 15, 2026