Date filters select awards with transaction activity in the period. Amounts below are lifetime award obligations. IDV values remain separate.
ALL EQUIPMENT, SUPERVISION, MATERIALS, AND LABOR NECESSARY TO PROVIDE BOTTLED WATER SERVICEGeneral Services Administration$52.7K obligationsEnds Jul 24, 2027
PROJECT REPAIR FAN POWER BOX 5TH FLOOR FOR NY0355ZZ ALFONSE M. D'AMATO U.S. COURTHOUSEGeneral Services Administration$4.1K obligationsEnds Sep 12, 2026
FURNISH AND INSTALL (3) CLIMATE MASTER UNITS TO REPLACE CUSGeneral Services Administration$392.3K obligationsEnds Nov 12, 2026
NY0355ZZ REPLACE SPILL BUCKET IN UST @ NY0355ZZ - ALFONSE D'AMATO COURTHOUSE AND FEDERAL BUILDINGGeneral Services Administration$3.0K obligationsEnds Sep 11, 2026
THE CONTRACTOR SHALL PROVIDE ALL EQUIPMENT, SUPERVISION, MATERIALS, AND LABOR NECESSARY TO RESTORE OPERATION OF THE SECURITY GATE.General Services Administration$5.0K obligationsEnds Aug 31, 2026
REPLACE COMPRESSOR IN RTU 4General Services Administration$16.1K obligationsEnds Sep 21, 2026
NY0355ZZ GSA ENG 2176 REPAIR BOILER 1 @ NY0355ZZ - ALFONSE D'AMATO COURTHOUSE AND FEDERAL BUILDINGGeneral Services Administration$4.7K obligationsEnds Aug 14, 2026
FIRE SPRINKLER ISOLATION VALVE REPAIR FIRE SYSTEM DRY SYSTEM REPLACE GARAGE SUMP PUMP FLOATSGeneral Services Administration$25.6K obligationsEnds Sep 6, 2026
REPLACE ELECTRICAL AND DATA LINES FOR BUILDING CAMERA SYSTEM AT THE D'AMATO COURTHOUSE IN ISLIP, NYGeneral Services Administration$32.8K obligationsEnds Sep 7, 2026
THE CONTRACTOR SHALL PROVIDE ALL EQUIPMENT, SUPERVISION, MATERIALS, AND LABOR NECESSARY TO REPLACE THE BOILER BLADDER EXPANSION TANK.General Services Administration$12.6K obligationsEnds Sep 3, 2026
EQUIPMENT, SUPERVISION, MATERIALS, AND LABOR NECESSARY TO PERFORM: REPLACE THE BLOWER ASSEMBLY IN CU 1 FOR EAST MAIN ELECTRICAL ROOM AT THE D'AMATO COURTHOUSE IN ISLIP, NYGeneral Services Administration$11.6K obligationsEnds Aug 16, 2026
47PC5526F0454 REPLACE BREAKERS AND REBUILD CONDENSER WATER PUMP AT THE D'AMATO COURTHOUSE IN CENTRAL ISLIP, NYGeneral Services Administration$49.6K obligationsEnds Oct 14, 2026
THE O&M CONTRACTOR SHALL PROVIDE LABOR AND SUPERVISION TO REPLACE ATS 1, 7 AND 10 MODELS AT 100 FED PLAZA, CENTRAL ISLIP, NY 11722.General Services Administration$180.8K obligationsEnds Mar 13, 2027
REPLACE DRAIN PAN IN RTU 2 @ NY0355ZZ - ALFONSE D'AMATO COURTHOUSE AND FEDERAL BUILDINGGeneral Services Administration$6.7K obligationsEnds Sep 4, 2026
DAMATO - TCSWO 1242 PRESSURE WASH EXTERIORGeneral Services Administration$10.2K obligationsEnds Aug 14, 2026
REPAIR OF A SOUND ATTENUATION BAFFLE THAT IS RUSTING/CORRODING AT 100 FEDERAL PLAZA, CENTRAL ISLIP, NY 11722.General Services Administration$155.0K obligationsEnds Aug 12, 2026
PROJECT FY 2026 SNOW REMOVAL DAMATO COURTHOUSE FOR NY0355ZZ - ALFONSE D'AMATO COURTHOUSE AND FEDERAL BUILDINGGeneral Services Administration$96.8K obligationsEnds May 12, 2026
CONTRACTOR TO REMOVE MIST ELIMINATORS IN AHU 10, 12 AND 14.General Services Administration$9.6K obligationsEnds Aug 9, 2026
DAMATO SERVICES - REPLACE 3RD SECTION OF CONDENSER WATER PIPE 4TH FLOORGeneral Services Administration$21.4K obligationsEnds Apr 30, 2026
REPLACE 8 FIRE SPRINKLERS STANDPIPE GAGESGeneral Services Administration$33.1K obligationsEnds Jul 30, 2026
REPLACE ISOLATION VALVES CHILLER 1 AND 2General Services Administration$19.7K obligationsEnds Jul 31, 2026
D AMATO SERVICES - FY 2026 ABM OVERTIMEGeneral Services Administration$44.1K obligationsEnds Jul 3, 2026
REBUILD SEWER EJECTOR PUMPGeneral Services Administration$13.6K obligationsEnds Jul 10, 2026
REPLACE NON CONFORMING SPRINKLER HEADS, GSA ENG 1977General Services Administration$179.6K obligationsEnds Jan 10, 2027
REBUILD HOT WATER PUMP # 2$General Services Administration$9.6K obligationsEnds Jul 10, 2026