THE PURPOSE OF THIS ORDER IS FOR THE ELECTRICAL VAULT UPGRADE AT THE GOVERNMENT ACCOUNTABILITY OFFICE HEADQUARTERS PERIOD OF PERFORMANCE SEPTEMBER 30, 2025 - AUGUST 29, 2026Government Accountability Office$2.9M obligationsEnds Mar 30, 2027
THIS ORDER IS FOR THE FULL-TIME CONSTRUCTION & QUALITY ASSURANCE TECHNICAL MONITOR SERVICE FOR VARIOUS CONSTRUCTIONS AT THE GAO HEADQUARTERS BUILDING.Government Accountability Office$450.6K obligationsEnds Feb 15, 2027
THIS ORDER IS FOR ENGINEERING AND DESIGN SERVICES FOR RESTROOM RENOVATIONS AT THE GAO HQ BUILDING.. TORNGovernment Accountability Office$380.2K obligationsEnds Nov 30, 2026
A&E FIRM TO IDENTIFY AND COMMUNICATE THE PHYSICAL DEFICIENCIES OF ELECTRICAL SYSTEMS AT THE GAO HQ BUILDING, PRESENT THEM WITHIN THE PERSPECTIVE OF THEIR REMAINING USEFUL LIFE…Government Accountability Office$541.0K obligationsEnds Jun 28, 2023
THE PURPOSE OF THIS ORDER IS FOR THE 4TH FLOOR ELEVATOR ENCLOSURE DESIGN AT THE GOVERNMENT ACCOUNTABILITY OFFICE HEADQUARTERS. PERIOD OF PERFORMANCE JULY 16, 2026 - DECEMBER 15…Government Accountability Office$159.9K obligationsEnds Dec 15, 2026
DESIGN COSTS FOR TF CABINETS, COUNTERS AND SINK AREA IN MULTI-PURPOSE ROOM 1184SGovernment Accountability Office$23.3K obligationsEnds Jan 12, 2022
AE FIRM TO PROVIDE RESEARCH, BEST PRACTICES AND DESIGN CONCEPTS FROM OTHER HISTORIC LAW LIBRARIES TO PERFORM A THOROUGH SURVEY OF THE GAO HISTORIC LAW LIBRARYGovernment Accountability Office$94.5K obligationsEnds Sep 30, 2022
THIS ORDER IS FOR THE ELECTRICAL LOAD STUDY, ELECTRICAL MASTER PLAN & SUPPORTING INFORMATION FOR BUDGETING & FISCAL YEAR PROGRAMMING TORN DATED 8/30/2023Government Accountability Office$617.0K obligationsEnds Jan 31, 2025
THIS ORDER IS FOR THE GAO HQ LEARNING CENTER RELOCATION, NEW CONFERENCE CENTER, AND MISSION TEAM REALIGNMENT PLANNING PROJECT.Government Accountability Office$1.1M obligationsEnds Apr 1, 2027
DESIGN SERVICES FOR 7TH FLOOR EXECUTIVE AREA - ZONE A AND 7TH FLOOR HISTORIC SUITE - ZONE B + SPATIAL STUDY AREA ZONE AGovernment Accountability Office$100.2K obligationsEnds Apr 30, 2027
THIS ORDER IS FOR THE FULL-TIME CONSTRUCTION & QUALITY ASSURANCE TECHNICAL MONITOR (TM) SERVICE FOR VARIOUS CONSTRUCTIONS AT THE GAO HEADQUARTERS BUILDING. TORN DATED 8/3/23.Government Accountability Office$1.1M obligationsEnds Mar 29, 2026
THIS ORDER IS FOR THE NEW ROOF AND SOLAR DESIGN TORNGovernment Accountability Office$661.4K obligationsEnds Oct 31, 2025