Federal contract award

0001

THE PURPOSE OF THIS FIRM FIXED PRICE TASK ORDER IS TO COVER CONTRACTOR FACILITY COSTS IN ACCORDANCE CONTRACT DTFAWA-17-D-00013 AND ATTACHED STATEMENT OF WORK DATED AUGUST 23, 2017. IGF::OT::IGF

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Transportation
Office693KA8 SYSTEM OPERATIONS CONTRACTS
NAICS541330 — Engineering Services
PSCK017 — Modification of Equipment: Aircraft Launching, Landing, and Ground Handling Equipment
Parent award / vehicleDTFAWA17D00013
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$7.6M
Current contract value$7.6M
Potential contract value / ceiling$7.6M
Start dateAug 24, 2017
Current end dateJul 3, 2026
Potential end dateJul 10, 2026
Latest award activityJul 9, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 33 of 33 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jul 9, 2026P00032$159.0KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING TO THE CURRENT FACILITY LEASE OPTION PERIOD. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED.
May 28, 2026P00031$0THE PURPOSE OF THIS MODIFICATION IS TO REALIGN FUNDING FROM ODCS TO THE FACILITY LEASE. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED.
May 19, 2026P00030$0EXTEND BY 6 WEEKS
Mar 2, 2026P00029$540.0KADD FUNDING
Jan 23, 2026P00027$0EXERCISE EXTENSION OPTION PERIOD 2
Jan 23, 2026P00028$0EXERCISE EXTENSION OPTION PERIOD 3
Aug 27, 2025P00026$168.7KADD FUNDING
Aug 7, 2025P00025$0EXERCISE EXTENSION OPTION PERIOD 1
Jun 10, 2025P00024$336.0KADD FUNDING
Apr 8, 2025P00023$0UPDATE PSC CODE
Feb 26, 2025P00022$258.0KADD FUNDING
Feb 20, 2025P00021$0EXTEND THE POP AND UPDATE LEASE PAYMENT AMOUNT
Jul 9, 2024P00020$397.7KADD FUNDING
Jun 25, 2024P00019$0EXTEND POP
May 24, 2023P00018$795.4KEXERCISE OPTION AND ADD FUNDING
Jan 5, 2023P00017$0ADMIN CHANGE
Aug 25, 2022P00016$335.0KADD FUNDING
Aug 3, 2022P00015$130.1KADD FUNDING
Jul 20, 2022P00014$198.9KEXERCISE OPTION PERIOD 5
Jun 13, 2022P00013$198.9KFUNDING ACTION
May 3, 2022P00012$132.6KFUNDING ACTION
Feb 1, 2022P00011$132.6KFUNDING ACTION
Aug 24, 2021P00010$0THE PURPOSE OF THIS MODIFICATION IS TO EXERCISE OPTION PERIOD 4 (OPTION YEAR 5) OF THE TASK ORDER. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED.
Jul 27, 2021P00009$376.6KADD FUNDING
Jun 22, 2021P00008$0ADMINISTRATIVE ACTION
May 17, 2021P00007$-389.8KDE-OBLIGATE FUNDS
Apr 23, 2021P00006$389.8KADD FUNDING
Apr 22, 2021P00005$0REDUCE THE FACILITY LEASE PRICING
Sep 10, 2020P00004$389.8KFUNDING
Jun 9, 2020P00003$505.0KFUNDING CONTRACT YEAR 4 COSTS
May 29, 2019P00002$873.0KFUNDING CONTRACT YEAR 2 COSTS IGF::OT::IGF
Jun 6, 2018P00001$851.6KFUNDING CONTRACT YEAR 2 COSTS IGF::OT::IGF
Aug 24, 20170$830.9KTHE PURPOSE OF THIS FIRM FIXED PRICE TASK ORDER IS TO COVER CONTRACTOR FACILITY COSTS IN ACCORDANCE CONTRACT DTFAWA-17-D-00013 AND ATTACHED STATEMENT OF WORK DATED AUGUST 23, 2017. IGF::OT::IGF

Research next steps

  1. Verify whether remaining options may extend performance beyond the current end date.
  2. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.