Federal contract award

1240LN25F0016

1. REMOVAL OF (5) CONDENSING UNITS AND ASSOCIATED FAN COILS ALONG WITH REFRIGERANT PIPING, CONDENSATE PIPING, THERMOSTATS, ASSOCIATED ELECTRICAL, ETC... AS SHOWN ON THE DRAWINGS AND DESCRIBED IN THE SPECIFICATIONS. 2. INSTALLATION OF (5) NEW CONDENS

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Agriculture
OfficeUSDA-FS, CSA INTERMOUNTAIN 3
NAICS236220 — Commercial and Institutional Building Construction
PSCZ1AZ — MAINTENANCE OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS
Parent award / vehicle1240LR21D0002
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$506.0K
Current contract value$506.0K
Potential contract value / ceiling$506.0K
Start dateSep 23, 2025
Current end dateApr 17, 2026
Potential end dateApr 17, 2026
Latest award activityApr 17, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 2 of 2 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Apr 17, 2026P00001$8.6KTHE PURPOSE OF THIS MODIFICATION IS TO: 1. TO CORRECT A DESIGN ERROR IN THE GOVERNMENT'S PLANS; THE GOVERNMENT WANTS TO ADD 3-PHASE POWER FOR THE INDOOR UNIT. THIS WAS NOT PREVIOUSLY ADDRESSED IN THE ORIGINAL PLANS.
Sep 23, 20250$497.4K1. REMOVAL OF (5) CONDENSING UNITS AND ASSOCIATED FAN COILS ALONG WITH REFRIGERANT PIPING, CONDENSATE PIPING, THERMOSTATS, ASSOCIATED ELECTRICAL, ETC... AS SHOWN ON THE DRAWINGS AND DESCRIBED IN THE SPECIFICATIONS. 2. INSTALLATION OF (5) NEW CONDENS