Federal contract award

1240LT23C0058

GAOA ASPEN/SOPRIS RANGER DISTRICT OFFICE RECONSTRUCTION, CARBONDALE, COLORADO ALL WORK IS TO BE PERFORMED IAW THE SOLICITATION: 1240LT23R0076 INCLUDING THE STATEMENT OF WORK, AND ALL APPLICABLE DOCUMENTATION WITHIN THE GUIDELINES AND COST OF YOUR QU

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Agriculture
OfficeUSDA-FS, CSA INTERMOUNTAIN 8
NAICS236220 — Commercial and Institutional Building Construction
PSCY1AA — CONSTRUCTION OF OFFICE BUILDINGS
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$7.2M
Current contract value$7.2M
Potential contract value / ceiling$7.2M
Start dateOct 1, 2023
Current end dateDec 1, 2025
Potential end dateDec 1, 2025
Latest award activityFeb 10, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Feb 10, 2026P00016$-5.8KDEOBLIGATION & CLOSEOUT 1240LT23C0058 - ASPEN/SOPRIS ADMINISTRATIVE BUILDING MODIFICATION P0016 DEOBLIGATES $5,800.00 OF FUNDS IN ORDER TO CLOSE THE ASSOCIATED CONTRACT/ORDER, PURSUANT TO FAR 4.804. THIS MODIFICATION HEREBY DEOBLIGATED ALL
Aug 1, 2025P00015$239.1KCHANGE ORDERS: 14-15-16-17-18 ASPEN/SOPRIS ADMINISTRATIVE BUILDING DOGE APPROVAL - NOT APPLICABLE TOTAL MODIFICATION P0015 FUNDING WITHIN THE 20% COST RULE. MODIFICATION P0015 52.243-4 CHANGES AUTHORIZES THE GOVERNMENT TO MAKE MUTUALLY AGREED
May 25, 2025P00014$0PERIOD OF PERFORMANCE EXTENSION: THIS IS A CONSTRUCTION CONTRACT FOR A DISTRICT OFFICE REBUILD. DURING PROJECT PERFORMANCE MULTIPLE CHANGE ORDER REQUESTS (COR) WERE SUBMITTED BY THE CONTRACTOR AND APPROVED BY THE CONTRACTING OFFICER (E.G. COR #2-FEB
Jan 15, 2025P00013$48.3KCHANGE ORDER P00013 GAOA CARBONDALE OFFICE ADDITIONAL FRAMING FLASHING AND DUCTWORK MODIFICATION UNDER COR 13 RFI CLARIFICATIONS. ALL WORK IS TO BE PERFORMED IAW THESE CHANGES AS WELL AS THE SOLICITATION, SPECIFICATIONS, STATEMENT OF WORK, AND A

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.