Federal contract award
1240LU24F0001
THE PROJECT SCOPE INCLUDES THE FOLLOWING SUBTASKS. SUBTASK 1 INCLUDES SURVEYING THE FULL CAMPGROUND COMPLEX AS WELL AS THE PROPOSED EXPANSION AREA. SUBTASKS 2 AND 4 ARE SEPARATE PROJECT LOCATIONS IN THE CAMPGROUND COMPLEX. SUB TASK 1AND2 ARE BASE
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Agriculture |
| Office | USDA-FS, CSA INTERMOUNTAIN 9 |
| NAICS | 541330 — Engineering Services |
| PSC | C220 — ARCHITECT AND ENGINEERING- GENERAL: STRUCTURAL ENGINEERING |
| Parent award / vehicle | 12034320D0040 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $217.0K |
| Current contract value | $217.0K |
| Potential contract value / ceiling | $217.0K |
| Start date | Oct 2, 2023 |
| Current end date | Oct 31, 2025 |
| Potential end date | Oct 31, 2025 |
| Latest award activity | Sep 25, 2025 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 6 of 6 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Sep 25, 2025 | P00005 | $0 | THE PROJECT SCOPE INCLUDES THE FOLLOWING SUBTASKS. SUBTASK 1 INCLUDES SURVEYING THE FULL CAMPGROUND COMPLEX AS WELL AS THE PROPOSED EXPANSION AREA. SUBTASKS 2 AND 4 ARE SEPARATE PROJECT LOCATIONS IN THE CAMPGROUND COMPLEX. SUB TASK 1AND2 ARE BASE |
| May 6, 2025 | P00004 | $0 | THE PROJECT SCOPE INCLUDES THE FOLLOWING SUBTASKS. SUBTASK 1 INCLUDES SURVEYING THE FULL CAMPGROUND COMPLEX AS WELL AS THE PROPOSED EXPANSION AREA. SUBTASKS 2 AND 4 ARE SEPARATE PROJECT LOCATIONS IN THE CAMPGROUND COMPLEX. SUB TASK 1AND2 ARE BASE |
| Nov 18, 2024 | P00003 | $0 | THE PROJECT SCOPE INCLUDES THE FOLLOWING SUBTASKS. SUBTASK 1 INCLUDES SURVEYING THE FULL CAMPGROUND COMPLEX AS WELL AS THE PROPOSED EXPANSION AREA. SUBTASKS 2 AND 4 ARE SEPARATE PROJECT LOCATIONS IN THE CAMPGROUND COMPLEX. SUB TASK 1AND2 ARE BASE |
| Apr 5, 2024 | P00002 | $0 | THE PROJECT SCOPE INCLUDES THE FOLLOWING SUBTASKS. SUBTASK 1 INCLUDES SURVEYING THE FULL CAMPGROUND COMPLEX AS WELL AS THE PROPOSED EXPANSION AREA. SUBTASKS 2 AND 4 ARE SEPARATE PROJECT LOCATIONS IN THE CAMPGROUND COMPLEX. SUB TASK 1AND2 ARE BASE |
| Mar 27, 2024 | P00001 | $0 | THE PROJECT SCOPE INCLUDES THE FOLLOWING SUBTASKS. SUBTASK 1 INCLUDES SURVEYING THE FULL CAMPGROUND COMPLEX AS WELL AS THE PROPOSED EXPANSION AREA. SUBTASKS 2 AND 4 ARE SEPARATE PROJECT LOCATIONS IN THE CAMPGROUND COMPLEX. SUB TASK 1AND2 ARE BASE |
| Oct 2, 2023 | 0 | $217.0K | THE PROJECT SCOPE INCLUDES THE FOLLOWING SUBTASKS. SUBTASK 1 INCLUDES SURVEYING THE FULL CAMPGROUND COMPLEX AS WELL AS THE PROPOSED EXPANSION AREA. SUBTASKS 2 AND 4 ARE SEPARATE PROJECT LOCATIONS IN THE CAMPGROUND COMPLEX. SUB TASK 1AND2 ARE BASE |
Research next steps
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.