PROPOSED PROJECT INCLUDES THE REMOVAL OF THE EXISTING 72" RCP AT THE CROSSING OF THE TRIBUTARY OF CYPER CRK AND FSR 610A. ALSO INCLUDED IS THIS CULVERT'S REPLACEMENT WITH A NEW 18'10"X5'8" ALUMINIZED STEEL PLATE ARCH WIT

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Agriculture
OfficeUSDA-FS, CSA EAST 12
NAICS237310 — Highway, Street, and Bridge Construction
PSCY1LB — CONSTRUCTION OF HIGHWAYS, ROADS, STREETS, BRIDGES, AND RAILWAYS
Parent award / vehicle12445224D0024
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$302.4K
Current contract value$302.4K
Potential contract value / ceiling$302.4K
Start dateSep 18, 2024
Current end dateAug 15, 2025
Potential end dateAug 15, 2025
Latest award activityJul 22, 2025
Source loadedAug 15, 2026

Funding and modification history

Showing the latest 3 of 3 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jul 22, 2025P00003$27.7KTHE PURPOSE OF THIS MODIFICATION IS FOR UNANTICIPATED ROCK EXCAVATION NEEDED TO INSTALL THE NEW CULVERT. ALSO ADDRESSED ARE VARIATIONS IN SOME OF THE QUANTITIES AND TO CHANGE THE END DATE FROM 6/13/25 TO 8/15/25.
Apr 30, 2025P00002$0THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE POP 45 DAYS CHANGING THE END DATE FROM 4/29/25 TO 6/13/25
Feb 11, 2025P00001$0THE PURPOSE OF THIS MODIFICATION IS TO CORRECT THE POP END DATE OF THIS TASK ORDER TO END 4/29/25 INSTEAD OF THE 5-YEAR IDIQ END DATE IN 2029.