Federal contract award

12445225F0013

NFSR 4030 MP 0.1 BRIDGE WAS WASHED ~200FT DOWNSTREAM BY HIGH STORM FLOWS DURING HURRICANE HELENE, SO A NEW BRIDGE WILL BE CONSTRUCTED TO REPLACE THE DAMAGED BRIDGE FOR PASSAGE OVER CURTIS CREEK.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Agriculture
OfficeUSDA-FS, CSA EAST 12
NAICS237310 — Highway, Street, and Bridge Construction
PSCY1LB — CONSTRUCTION OF HIGHWAYS, ROADS, STREETS, BRIDGES, AND RAILWAYS
Parent award / vehicle12445224D0049
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$1.7M
Current contract value$1.7M
Potential contract value / ceiling$1.7M
Start dateApr 1, 2025
Current end dateMar 1, 2026
Potential end dateMar 1, 2026
Latest award activityDec 15, 2025
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 5 of 5 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Dec 15, 2025P00004$0LESS THAN THE ESTIMATED AMOUNTS OF MACHINE PLACED RIP RAP AND STEEL PILE WERE USED ON-SITE. A TOTAL OF 62.32 TON OF MACHINE PLACED RIPRAP WILL NOT BE USED FOR A SAVINGS OF $6,855.20 AND A TOTAL OF 48.5 LF OF STEEL PILE WILL NOT BE USED FOR A SAVINGS
Sep 15, 2025P00003$-51.4KTHE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE FUNDING BASED ON CHANGES IDENTIFIED IN MODIFICATION P0001. 200 LF STEEL BACKED TIMBER AT $774.00/LF WAS REMOVED FROM THE CONTRACT TOTALING $154,800.00 AND 200 LF VERTICAL CONCRETE BARRIER AT $400.00/
Jul 14, 2025P00002$47.2KTHE PURPOSE OF THIS MODIFICATION IS TO ADD AN ADDITIONAL 51 LF OF PILE LENGTH TO THE CONTRACT. THE ADDITIONAL PILE LENGTH IS REQUIRED TO ANCHOR THE BRIDGE INTO BEDROCK. THE PRICE PER LF FOR THE ADDITIONAL 51 LF WILL BE $925.00 FOR A TOTAL OF $47,12
May 5, 2025P00001$0THE PURPOSE OF THIS NO COST MODIFICATION IS TO UPDATE THE SCHEDULE OF ITEMS # 55601ON THE BARRIER RAIL.
Apr 1, 20250$1.7MNFSR 4030 MP 0.1 BRIDGE WAS WASHED ~200FT DOWNSTREAM BY HIGH STORM FLOWS DURING HURRICANE HELENE, SO A NEW BRIDGE WILL BE CONSTRUCTED TO REPLACE THE DAMAGED BRIDGE FOR PASSAGE OVER CURTIS CREEK.