Federal contract award
12445525C0024
INTERIOR AND EXTERIOR REPAIRS DUE TO HELENE STORM DAMAGE INCLUDING FRAMING AND FINISHES, PLUMBING, ELECTRICAL, DOORS, AND MINOR SITE WORK.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Agriculture |
| Office | USDA-FS, CSA EAST 13 |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Z2AA — REPAIR OR ALTERATION OF OFFICE BUILDINGS |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $336.6K |
| Current contract value | $336.6K |
| Potential contract value / ceiling | $336.6K |
| Start date | Oct 8, 2025 |
| Current end date | Mar 23, 2026 |
| Potential end date | Mar 23, 2026 |
| Latest award activity | Mar 2, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Mar 2, 2026 | P00003 | $8.2K | INTERIOR AND EXTERIOR REPAIRS DUE TO HELENE STORM DAMAGE INCLUDING FRAMING AND FINISHES, PLUMBING, ELECTRICAL, DOORS, AND MINOR SITE WORK. DIFFERING SITE CONDITIONS WERE ENCOUNTERED AT THE MORTIMER WORK CENTER DURING PERFORMANCE. MOISTURE DAMAGE |
| Feb 20, 2026 | P00002 | $0 | INTERIOR AND EXTERIOR REPAIRS DUE TO HELENE STORM DAMAGE INCLUDING FRAMING AND FINISHES, PLUMBING, ELECTRICAL, DOORS, AND MINOR SITE WORK. THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE COMPLETION DATE OF THE CONTRACT FROM FEBRUARY 20, 2026 TO |
| Dec 9, 2025 | P00001 | $0 | INTERIOR AND EXTERIOR REPAIRS DUE TO HELENE STORM DAMAGE INCLUDING FRAMING AND FINISHES, PLUMBING, ELECTRICAL, DOORS, AND MINOR SITE WORK. THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE COMPLETION DATE OF THE CONTRACT FROM JANUARY 6, 2025 TO F |
| Sep 24, 2025 | 0 | $328.4K | INTERIOR AND EXTERIOR REPAIRS DUE TO HELENE STORM DAMAGE INCLUDING FRAMING AND FINISHES, PLUMBING, ELECTRICAL, DOORS, AND MINOR SITE WORK. |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.