Federal contract award

12445525C0024

INTERIOR AND EXTERIOR REPAIRS DUE TO HELENE STORM DAMAGE INCLUDING FRAMING AND FINISHES, PLUMBING, ELECTRICAL, DOORS, AND MINOR SITE WORK.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Agriculture
OfficeUSDA-FS, CSA EAST 13
NAICS236220 — Commercial and Institutional Building Construction
PSCZ2AA — REPAIR OR ALTERATION OF OFFICE BUILDINGS
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$336.6K
Current contract value$336.6K
Potential contract value / ceiling$336.6K
Start dateOct 8, 2025
Current end dateMar 23, 2026
Potential end dateMar 23, 2026
Latest award activityMar 2, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Mar 2, 2026P00003$8.2KINTERIOR AND EXTERIOR REPAIRS DUE TO HELENE STORM DAMAGE INCLUDING FRAMING AND FINISHES, PLUMBING, ELECTRICAL, DOORS, AND MINOR SITE WORK. DIFFERING SITE CONDITIONS WERE ENCOUNTERED AT THE MORTIMER WORK CENTER DURING PERFORMANCE. MOISTURE DAMAGE
Feb 20, 2026P00002$0INTERIOR AND EXTERIOR REPAIRS DUE TO HELENE STORM DAMAGE INCLUDING FRAMING AND FINISHES, PLUMBING, ELECTRICAL, DOORS, AND MINOR SITE WORK. THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE COMPLETION DATE OF THE CONTRACT FROM FEBRUARY 20, 2026 TO
Dec 9, 2025P00001$0INTERIOR AND EXTERIOR REPAIRS DUE TO HELENE STORM DAMAGE INCLUDING FRAMING AND FINISHES, PLUMBING, ELECTRICAL, DOORS, AND MINOR SITE WORK. THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE COMPLETION DATE OF THE CONTRACT FROM JANUARY 6, 2025 TO F
Sep 24, 20250$328.4KINTERIOR AND EXTERIOR REPAIRS DUE TO HELENE STORM DAMAGE INCLUDING FRAMING AND FINISHES, PLUMBING, ELECTRICAL, DOORS, AND MINOR SITE WORK.

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.