Federal contract award
127EAX26C0003
PROJECT IS TO CONSTRUCT ADDITIONAL PAVED PARKING AREAS AT THE CHINA WALL OHV STAGING AREA. PROJECT INCLUDES BUT IS NOT LIMITED TO, SITE CLEARING AND GRUBBING, GRADING, SAW CUTTING EXISTING ASPHALT, SUBBASE AND BASE PREPARATION, DRAINAGE FEATURES, AGG
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Agriculture |
| Office | USDA-FS, CSA SOUTHWEST 7 |
| NAICS | 237310 — Highway, Street, and Bridge Construction |
| PSC | Z2LB — REPAIR OR ALTERATION OF HIGHWAYS/ROADS/STREETS/BRIDGES/RAILWAYS |
| Parent award / vehicle | Not reported |
| Set-aside | SMALL BUSINESS SET ASIDE - TOTAL |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $1.1M |
| Current contract value | $1.1M |
| Potential contract value / ceiling | $1.1M |
| Start date | Dec 5, 2025 |
| Current end date | Oct 30, 2026 |
| Potential end date | Oct 30, 2026 |
| Latest award activity | Mar 12, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 2 of 2 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Mar 12, 2026 | P00001 | $0 | PROJECT IS TO CONSTRUCT ADDITIONAL PAVED PARKING AREAS AT THE CHINA WALL OHV STAGING AREA. PROJECT INCLUDES BUT IS NOT LIMITED TO, SITE CLEARING AND GRUBBING, GRADING, SAW CUTTING EXISTING ASPHALT, SUBBASE AND BASE PREPARATION, DRAINAGE FEATURES, AGG |
| Dec 2, 2025 | 0 | $1.1M | PROJECT IS TO CONSTRUCT ADDITIONAL PAVED PARKING AREAS AT THE CHINA WALL OHV STAGING AREA. PROJECT INCLUDES BUT IS NOT LIMITED TO, SITE CLEARING AND GRUBBING, GRADING, SAW CUTTING EXISTING ASPHALT, SUBBASE AND BASE PREPARATION, DRAINAGE FEATURES, AGG |
Buyer contacts from matching notices
Matched on exact award/solicitation identifier and awarding agency. Source dates describe the notice, not current contact verification.
| Contact | Role | Published contact methods | Evidence | Source date |
|---|---|---|---|---|
| Troy A. McCullough | Contact | troy.mccullough@usda.gov | Source | Aug 21, 2025 |
| Troy A. McCullough | Contact | troy.mccullough@usda.gov | Source | Aug 20, 2025 |
| Troy A. McCullough | Contact | troy.mccullough@usda.gov | Source | Aug 18, 2025 |
| Troy A. McCullough | Contact | troy.mccullough@usda.gov | Source | Aug 18, 2025 |
| Troy A. McCullough | Contact | troy.mccullough@usda.gov | Source | Aug 4, 2025 |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.