Federal contract award

1282B124F0143

THE WORK INCLUDES: 1.CONSTRUCTING NEW ROADWAYS, CAMPSITE SPURS AND PATHWAYS. 2.INSTALLING NEW FAMILY UNITS WITH SITE FURNITURE, SIGNS AND GATES. 3.INSTALLING NEW VAULT TOILETS.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Agriculture
OfficeUSDA FOREST SERVICE-SPOC IM
NAICS236220 — Commercial and Institutional Building Construction
PSCZ1AZ — MAINTENANCE OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS
Parent award / vehicle1240LR21D0002
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$2.0M
Current contract value$2.0M
Potential contract value / ceiling$2.0M
Start dateMar 31, 2025
Current end dateJun 30, 2026
Potential end dateJun 30, 2026
Latest award activityJun 24, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 7 of 7 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jun 24, 2026P00006$33.7KTHE PURPOSE OF THIS MODIFICATION IS TO: 1. DIRECT THE CONTRACTOR TO INSTALL SEVERAL FRENCH DRAINS AND DITCHES TO REDIRECT THE WATER.
Feb 23, 2026P00005$140.1KTHE PURPOSE OF THIS MODIFICATION IS TO: 1. RAISE THE SAGEHEN BOAT RAMP VAULT TOILET APPROXIMATELY 10.5 INCHES DUE TO INCORRECT ELEVATIONS REFLECTED ON THE DRAWINGS. 2. INSTALL GRAVEL SUMPS PER DETAIL PROVIDED BY USFS AT THREE LOCATIONS. 3. REMOVE
Oct 14, 2025P00004$0. THE CONTRACTOR STILL HAS A LOT OF ASPHALT TO PLACE AND THE TEMPERATURES WILL BE TOO LOW FOR PAVING SO THE CONTRACT WILL NEED TO BE EXTENDED TO JUNE 30TH 2026.
Aug 27, 2025P00003$0THE CONTRACTOR GOT A SLOW START AND THE ASPHALT GRINDING TOOK LONGER THAN EXPECTED SO THEY HAVE FALLEN BEHIND SCHEDULE ON THIS PROJECT. IF THE CONTRACT POP ISNT EXTENDED THEN THE 2 CAMPGROUNDS BEING RENOVATED WOULD BE UNUSABLE AS THEY HAVE ALREADY TO
Aug 1, 2025P00002$91.5KTHE WORK INCLUDES: 1.HAUL ROAD MIX FROM MILL CREEK PIT TO SAGE HEN JOB SITE. 2.FURNISH AND INSTALL 2X50 LINEAR FEET OF 12-INCH GALV. STEEL CORRUGATED METAL PIPE (16 GAGE, 2 2/3"X1/2" CORRUGATIONS) WITHIN THE COMPLETED CAMPGROUND TO ADDRE
Nov 22, 2024P00001$0THE WORK INCLUDES: 1.CONSTRUCTING NEW ROADWAYS, CAMPSITE SPURS AND PATHWAYS. 2.INSTALLING NEW FAMILY UNITS WITH SITE FURNITURE, SIGNS AND GATES. 3.INSTALLING NEW VAULT TOILETS.
Sep 17, 20240$1.7MTHE WORK INCLUDES: 1.CONSTRUCTING NEW ROADWAYS, CAMPSITE SPURS AND PATHWAYS. 2.INSTALLING NEW FAMILY UNITS WITH SITE FURNITURE, SIGNS AND GATES. 3.INSTALLING NEW VAULT TOILETS.