Federal contract award

12905B25C0002

TRANSFORMER PROJECT II: INTERNAL BUILDING TRANSFORMERS AND DISCONNECT SWITCHES (KIMBERLY, ID)

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Agriculture
OfficeUSDA ARS AFM APD
NAICS237130 — Power and Communication Line and Related Structures Construction
PSCY1NZ — CONSTRUCTION OF OTHER UTILITIES
Parent award / vehicleNot reported
Set-asideSMALL BUSINESS SET ASIDE - TOTAL
Pricing typeFIRM FIXED PRICE
Obligations$226.7K
Current contract value$226.7K
Potential contract value / ceiling$226.7K
Start dateJun 3, 2025
Current end dateJul 31, 2026
Potential end dateJul 31, 2026
Latest award activityJul 17, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 3 of 3 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jul 17, 2026P00002$3.6KTRANSFORMER PROJECT II: INTERNAL BUILDING TRANSFORMERS AND DISCONNECT SWITCHES (KIMBERLY, ID)
Dec 8, 2025P00001$0TRANSFORMER PROJECT II: INTERNAL BUILDING TRANSFORMERS AND DISCONNECT SWITCHES (KIMBERLY, ID)
Jun 3, 20250$223.1KTRANSFORMER PROJECT II: INTERNAL BUILDING TRANSFORMERS AND DISCONNECT SWITCHES (KIMBERLY, ID)

Buyer contacts from matching notices

Matched on exact award/solicitation identifier and awarding agency. Source dates describe the notice, not current contact verification.

ContactRolePublished contact methodsEvidenceSource date
Spencer HamiltonContactspencer.hamilton@usda.govSourceDec 17, 2024
Spencer HamiltonContactspencer.hamilton@usda.govSourceDec 5, 2024
Spencer HamiltonContactspencer.hamilton@usda.govSourceDec 2, 2024
Spencer HamiltonContactspencer.hamilton@usda.govSourceNov 13, 2024
Spencer HamiltonContactspencer.hamilton@usda.govSourceNov 1, 2024
Spencer HamiltonContactspencer.hamilton@usda.govSourceOct 16, 2024

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.