Federal contract award

12970222F0040

THE WALKER MINE TAILINGS SITE REMOVAL ACTION IMPLEMENTATION PROJECT IS A COMPETITIVE TO UNDER THE R5 CERCLA ENVIRONMENTAL RESPONSE IDIQ FOR ACTIVITY V- REMEDIAL ACTION IMPLEMENTATION WORK. THE PROJECT IS THE IMPLEMENTATION OF THE 2019 REVEGETATION PL

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Agriculture
OfficeUSDA FOREST SERVICE-SPOC SW
NAICS562910 — Remediation Services
PSCR499 — Other Professional Services
Parent award / vehicle1291S818D0002
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$3.8M
Current contract value$3.8M
Potential contract value / ceiling$3.8M
Start dateSep 21, 2022
Current end dateDec 31, 2025
Potential end dateDec 31, 2025
Latest award activityDec 10, 2024
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 6 of 6 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Dec 10, 2024P00005$0THE WALKER MINE TAILINGS SITE REMOVAL ACTION IMPLEMENTATION PROJECT IS A COMPETITIVE TO UNDER THE R5 CERCLA ENVIRONMENTAL RESPONSE IDIQ FOR ACTIVITY V- REMEDIAL ACTION IMPLEMENTATION WORK. THE PROJECT IS THE IMPLEMENTATION OF THE 2019 REVEGETATION PL
Jul 19, 2024P00004$475.8KTHE WALKER MINE TAILINGS SITE REMOVAL ACTION IMPLEMENTATION PROJECT IS A COMPETITIVE TO UNDER THE R5 CERCLA ENVIRONMENTAL RESPONSE IDIQ FOR ACTIVITY V- REMEDIAL ACTION IMPLEMENTATION WORK. THE PROJECT IS THE IMPLEMENTATION OF THE 2019 REVEGETATION PL
Jul 29, 2023P00003$55.6KTHE WALKER MINE TAILINGS SITE REMOVAL ACTION IMPLEMENTATION PROJECT IS A COMPETITIVE TO UNDER THE R5 CERCLA ENVIRONMENTAL RESPONSE IDIQ FOR ACTIVITY V- REMEDIAL ACTION IMPLEMENTATION WORK. THE PROJECT IS THE IMPLEMENTATION OF THE 2019 REVEGETATION PL
Mar 27, 2023P00002$1.3MTHE WALKER MINE TAILINGS SITE REMOVAL ACTION IMPLEMENTATION PROJECT IS A COMPETITIVE TO UNDER THE R5 CERCLA ENVIRONMENTAL RESPONSE IDIQ FOR ACTIVITY V- REMEDIAL ACTION IMPLEMENTATION WORK. THE PROJECT IS THE IMPLEMENTATION OF THE 2019 REVEGETATION PL
Jan 6, 2023P00001$0THE WALKER MINE TAILINGS SITE REMOVAL ACTION IMPLEMENTATION PROJECT IS A COMPETITIVE TO UNDER THE R5 CERCLA ENVIRONMENTAL RESPONSE IDIQ FOR ACTIVITY V- REMEDIAL ACTION IMPLEMENTATION WORK. THE PROJECT IS THE IMPLEMENTATION OF THE 2019 REVEGETATION PL
Sep 21, 20220$2.0MTHE WALKER MINE TAILINGS SITE REMOVAL ACTION IMPLEMENTATION PROJECT IS A COMPETITIVE TO UNDER THE R5 CERCLA ENVIRONMENTAL RESPONSE IDIQ FOR ACTIVITY V- REMEDIAL ACTION IMPLEMENTATION WORK. THE PROJECT IS THE IMPLEMENTATION OF THE 2019 REVEGETATION PL