Federal contract award
12970224C0061
THE LTBMU 2025 BARRIERS & FENCING CONSTRUCTION 8(A) PROJECT IS FOR THE FABRICATION AND INSTALLATION OF 22-INCH METAL FENCING, CONSTRUCTED METAL ACCESS STRUCTURES AND GATES AT SEVERAL LOCATIONS AROUND THE LAKE TAHOE BASIN AREA IN EL DORADO AND PLA
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Agriculture |
| Office | USDA FOREST SERVICE-SPOC SW |
| NAICS | 238990 — All Other Specialty Trade Contractors |
| PSC | Z2PZ — REPAIR OR ALTERATION OF OTHER NON-BUILDING FACILITIES |
| Parent award / vehicle | Not reported |
| Set-aside | 8(A) SOLE SOURCE |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $2.6M |
| Current contract value | $2.6M |
| Potential contract value / ceiling | $2.6M |
| Start date | Oct 18, 2024 |
| Current end date | Nov 7, 2025 |
| Potential end date | Nov 7, 2025 |
| Latest award activity | May 15, 2025 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 3 of 3 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 15, 2025 | P00002 | $-123 | P00002-FUNDING LINE CORRECTIONS THE LTBMU 2025 BARRIERS & FENCING CONSTRUCTION 8(A) PROJECT IS FOR THE FABRICATION AND INSTALLATION OF 22-INCH METAL FENCING, CONSTRUCTED METAL ACCESS STRUCTURES AND GATES AT SEVERAL LOCATIONS AROUND THE LAKE T |
| Nov 30, 2024 | P00001 | $0 | P00001-UPDATE PERIOD OF PERFORMANCE DATE & IAS AWARD FORM CORRECTION (ADMIN --SYSTEM ONLY) THE LTBMU 2025 BARRIERS & FENCING CONSTRUCTION 8(A) PROJECT IS FOR THE FABRICATION AND INSTALLATION OF 22-INCH METAL FENCING, CONSTRUCTED METAL ACC |
| Sep 30, 2024 | 0 | $2.6M | THE LTBMU 2025 BARRIERS & FENCING CONSTRUCTION 8(A) PROJECT IS FOR THE FABRICATION AND INSTALLATION OF 22-INCH METAL FENCING, CONSTRUCTED METAL ACCESS STRUCTURES AND GATES AT SEVERAL LOCATIONS AROUND THE LAKE TAHOE BASIN AREA IN EL DORADO AND PLA |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.