DAM REHABILITATION - MARGARET CREEK STRUCTURES 1 AND 6 - SUPPLEMENTAL PLAN&ENVIRONMENTAL ASSESSMENT, OHIO
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Agriculture |
| Office | FPAC BUS CNTR-ACQ DIV-WESTERN SEC |
| NAICS | 541330 — Engineering Services |
| PSC | C219 — Other Architect and Engineering Services |
| Parent award / vehicle | 12SPEC18D0005 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $987.6K |
| Current contract value | $987.6K |
| Potential contract value / ceiling | $987.6K |
| Start date | May 1, 2020 |
| Current end date | May 30, 2026 |
| Potential end date | May 30, 2026 |
| Latest award activity | Feb 11, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 13 of 13 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Feb 11, 2026 | P00012 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE COMPLETION DATE FROM 2/28/2026 TO 5/30/2026. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. |
| Sep 24, 2025 | P00011 | $0 | DAM REHABILITATION - MARGARET CREEK STRUCTURES 1 AND 6 - SUPPLEMENTAL PLAN & ENVIRONMENTAL ASSESSMENT, OHIO EXTEND PERFORMANCE DATE TO FEBRUARY 28, 2026 |
| Sep 19, 2025 | P00010 | $-14.2K | EXTEND PERFORMANCE DATE DAM REHABILITATION - MARGARET CREEK STRUCTURES 1 AND 6 - SUPPLEMENTAL PLAN & ENVIRONMENTAL ASSESSMENT, OHIO |
| Jan 22, 2025 | P00009 | $0 | EXTEND PERFORMANCE DATE DAM REHABILITATION - MARGARET CREEK STRUCTURES 1 AND 6 - SUPPLEMENTAL PLAN & ENVIRONMENTAL ASSESSMENT, OHIO |
| Apr 8, 2024 | P00008 | $27.2K | ADD ADDITIONAL WORK WITHIN SCOPE DAM REHABILITATION - MARGARET CREEK STRUCTURES 1 AND 6 - SUPPLEMENTAL PLAN & ENVIRONMENTAL ASSESSMENT, OHIO |
| Jul 11, 2023 | P00007 | $45.1K | 1) COMPLETING ADDITIONAL SCOPE ASSOCIATED WITH FIELD VERIFICATION OF WETLANDS: CLEAN WATER ACT (CWA) WETLANDS AND WATERS OF THE US (WOUS) SECTION 404 AND 401 COMPLIANCE 2) UPDATES TO THE REHABILITATION PLAN ASSOCIATED WITH THREATENED AND ENDANGERED |
| Feb 24, 2023 | P00006 | $0 | EXTEND PERIOD OF PERFORMANCE TO FEBRUARY 28, 2023 DUE TO HQ APPROVAL AND PUBLIC OUTREACH DAM REHABILITATION - MARGARET CREEK STRUCTURES 1 AND 6 - SUPPLEMENTAL PLAN & ENVIRONMENTAL ASSESSMENT, OHIO |
| Aug 31, 2022 | P00005 | $0 | EXTEND PERIOD OF PERFORMANCE TO FEBRUARY 28, 2023 DUE TO HQ APPROVAL AND PUBLIC OUTREACH DAM REHABILITATION - MARGARET CREEK STRUCTURES 1 AND 6 - SUPPLEMENTAL PLAN & ENVIRONMENTAL ASSESSMENT, OHIO |
| Apr 29, 2022 | P00004 | $0 | DAM REHABILITATION - MARGARET CREEK STRUCTURES 1 AND 6 - SUPPLEMENTAL PLAN & ENVIRONMENTAL ASSESSMENT, OHIO EXTEND PERIOD OF PERFORMANCE TO APRIL 30, 2022 DUE TO GOVERNMENT DELAYS |
| Dec 1, 2021 | P00003 | $0 | DAM REHABILITATION - MARGARET CREEK STRUCTURES 1 AND 6 - SUPPLEMENTAL PLAN & ENVIRONMENTAL ASSESSMENT, OHIO EXTEND PERIOD OF PERFORMANCE TO APRIL 30, 2022 DUE TO GOVERNMENT DELAYS |
| May 27, 2021 | P00002 | $0 | DAM REHABILITATION - MARGARET CREEK STRUCTURES 1 AND 6 - SUPPLEMENTAL PLAN & ENVIRONMENTAL ASSESSMENT, OHIO |
| Sep 1, 2020 | P00001 | $0 | DAM REHABILITATION - MARGARET CREEK STRUCTURES 1 AND 6 - SUPPLEMENTAL PLAN&ENVIRONMENTAL ASSESSMENT, OHIO |
| May 1, 2020 | 0 | $929.6K | DAM REHABILITATION - MARGARET CREEK STRUCTURES 1 AND 6 - SUPPLEMENTAL PLAN&ENVIRONMENTAL ASSESSMENT, OHIO |