Federal contract award

12FPC322F0072

ASSUNPINK CREEK DAM NO. 8 WATERSHED REHABILITATION ASSISTANCE - DESIGN SERVICES TASK ORDER AWARDED FROM NATIONAL A/E IDIQ DESIGN SERVICES - REGION 1 (MAINE, NEW HAMPSHIRE, MASSACHUSETTS, MARYLAND, WASHINGTON DC, RHODE ISLAND, CONNECTICUT, VERMONT, N

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Agriculture
OfficeFPAC BUS CNTR-ACQ DIV-WESTERN SEC
NAICS541330 — Engineering Services
PSCC219 — Other Architect and Engineering Services
Parent award / vehicle12SPEC18D0023
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$842.0K
Current contract value$842.0K
Potential contract value / ceiling$842.0K
Start dateApr 14, 2022
Current end dateJan 30, 2026
Potential end dateJan 30, 2026
Latest award activityMar 25, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 9 of 9 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Mar 25, 2026P00008$-0THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE TO DEC 19TH, 2025 TO ALLOW FOR TIME TO FINISH THE FINAL DESIGN, AS WELL AS ALLOW FOR A CONSULTANT PERIOD DURING THE PRE BID PHASE OF CONSTRUCTION. ALL OTHER TERMS AND CONDITIO
Jan 28, 2026P00007$0THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE TO DEC 19TH, 2025 TO ALLOW FOR TIME TO FINISH THE FINAL DESIGN, AS WELL AS ALLOW FOR A CONSULTANT PERIOD DURING THE PRE BID PHASE OF CONSTRUCTION. ALL OTHER TERMS AND CONDITIO
Apr 22, 2025P00006$0THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE TO DEC 19TH, 2025 TO ALLOW FOR TIME TO FINISH THE FINAL DESIGN, AS WELL AS ALLOW FOR A CONSULTANT PERIOD DURING THE PRE BID PHASE OF CONSTRUCTION. ALL OTHER TERMS AND CONDITIO
Dec 10, 2024P00005$0EXTEND PERFORMANCE DATE ASSUNPINK CREEK DAM NO. 8 WATERSHED REHAB - HAMILTON TOWNSHIP, NJ
Aug 23, 2024P00004$0EXTEND PERFORMANCE DATE ASSUNPINK CREEK DAM NO. 8 WATERSHED REHAB - HAMILTON TOWNSHIP, NJ
Jun 6, 2024P00003$0EXTEND PERFORMANCE DATE ASSUNPINK CREEK DAM NO. 8 WATERSHED REHAB - HAMILTON TOWNSHIP, NJ
Dec 14, 2023P00002$0BILATERAL MODIFICATION FOR A DESIGN CHANGE FROM AN OPEN LABYRINTH WEIR SPILLWAY TO A BURIED RCC CUT-OFF WALL IN THE EXISTING AUXILIARY SPILLWAY TO REDUCE CONSTRUCTION COSTS. ASSUNPINK CREEK DAM NO. 8 WATERSHED REHABILITATION ASSISTANCE - DESIGN SER
Oct 13, 2022P00001$-34.1KBILATERAL MODIFICATION FOR A DESIGN CHANGE FROM AN OPEN LABYRINTH WEIR SPILLWAY TO A BURIED RCC CUT-OFF WALL IN THE EXISTING AUXILIARY SPILLWAY TO REDUCE CONSTRUCTION COSTS. ASSUNPINK CREEK DAM NO. 8 WATERSHED REHABILITATION ASSISTANCE - DESIGN SER
Apr 14, 20220$876.1KASSUNPINK CREEK DAM NO. 8 WATERSHED REHABILITATION ASSISTANCE - DESIGN SERVICES TASK ORDER AWARDED FROM NATIONAL A/E IDIQ DESIGN SERVICES - REGION 1 (MAINE, NEW HAMPSHIRE, MASSACHUSETTS, MARYLAND, WASHINGTON DC, RHODE ISLAND, CONNECTICUT, VERMONT, N

Research next steps

  1. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.