Federal contract award
12FPC322F0072
ASSUNPINK CREEK DAM NO. 8 WATERSHED REHABILITATION ASSISTANCE - DESIGN SERVICES TASK ORDER AWARDED FROM NATIONAL A/E IDIQ DESIGN SERVICES - REGION 1 (MAINE, NEW HAMPSHIRE, MASSACHUSETTS, MARYLAND, WASHINGTON DC, RHODE ISLAND, CONNECTICUT, VERMONT, N
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Agriculture |
| Office | FPAC BUS CNTR-ACQ DIV-WESTERN SEC |
| NAICS | 541330 — Engineering Services |
| PSC | C219 — Other Architect and Engineering Services |
| Parent award / vehicle | 12SPEC18D0023 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $842.0K |
| Current contract value | $842.0K |
| Potential contract value / ceiling | $842.0K |
| Start date | Apr 14, 2022 |
| Current end date | Jan 30, 2026 |
| Potential end date | Jan 30, 2026 |
| Latest award activity | Mar 25, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 9 of 9 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Mar 25, 2026 | P00008 | $-0 | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE TO DEC 19TH, 2025 TO ALLOW FOR TIME TO FINISH THE FINAL DESIGN, AS WELL AS ALLOW FOR A CONSULTANT PERIOD DURING THE PRE BID PHASE OF CONSTRUCTION. ALL OTHER TERMS AND CONDITIO |
| Jan 28, 2026 | P00007 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE TO DEC 19TH, 2025 TO ALLOW FOR TIME TO FINISH THE FINAL DESIGN, AS WELL AS ALLOW FOR A CONSULTANT PERIOD DURING THE PRE BID PHASE OF CONSTRUCTION. ALL OTHER TERMS AND CONDITIO |
| Apr 22, 2025 | P00006 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE TO DEC 19TH, 2025 TO ALLOW FOR TIME TO FINISH THE FINAL DESIGN, AS WELL AS ALLOW FOR A CONSULTANT PERIOD DURING THE PRE BID PHASE OF CONSTRUCTION. ALL OTHER TERMS AND CONDITIO |
| Dec 10, 2024 | P00005 | $0 | EXTEND PERFORMANCE DATE ASSUNPINK CREEK DAM NO. 8 WATERSHED REHAB - HAMILTON TOWNSHIP, NJ |
| Aug 23, 2024 | P00004 | $0 | EXTEND PERFORMANCE DATE ASSUNPINK CREEK DAM NO. 8 WATERSHED REHAB - HAMILTON TOWNSHIP, NJ |
| Jun 6, 2024 | P00003 | $0 | EXTEND PERFORMANCE DATE ASSUNPINK CREEK DAM NO. 8 WATERSHED REHAB - HAMILTON TOWNSHIP, NJ |
| Dec 14, 2023 | P00002 | $0 | BILATERAL MODIFICATION FOR A DESIGN CHANGE FROM AN OPEN LABYRINTH WEIR SPILLWAY TO A BURIED RCC CUT-OFF WALL IN THE EXISTING AUXILIARY SPILLWAY TO REDUCE CONSTRUCTION COSTS. ASSUNPINK CREEK DAM NO. 8 WATERSHED REHABILITATION ASSISTANCE - DESIGN SER |
| Oct 13, 2022 | P00001 | $-34.1K | BILATERAL MODIFICATION FOR A DESIGN CHANGE FROM AN OPEN LABYRINTH WEIR SPILLWAY TO A BURIED RCC CUT-OFF WALL IN THE EXISTING AUXILIARY SPILLWAY TO REDUCE CONSTRUCTION COSTS. ASSUNPINK CREEK DAM NO. 8 WATERSHED REHABILITATION ASSISTANCE - DESIGN SER |
| Apr 14, 2022 | 0 | $876.1K | ASSUNPINK CREEK DAM NO. 8 WATERSHED REHABILITATION ASSISTANCE - DESIGN SERVICES TASK ORDER AWARDED FROM NATIONAL A/E IDIQ DESIGN SERVICES - REGION 1 (MAINE, NEW HAMPSHIRE, MASSACHUSETTS, MARYLAND, WASHINGTON DC, RHODE ISLAND, CONNECTICUT, VERMONT, N |
Research next steps
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.