Federal contract award

1305M423CNAAA0015

MANCHESTER SEAWATER SYSTEM REPLACEMENT AT MANCHESTER RESEARCH STATION IN PORT ORCHARD, WASHINGTON

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Commerce
OfficeDEPT OF COMMERCE NOAA
NAICS237110 — Water and Sewer Line and Related Structures Construction
PSCZ2NZ — REPAIR OR ALTERATION OF OTHER UTILITIES
Parent award / vehicleNot reported
Set-asideSMALL BUSINESS SET ASIDE - TOTAL
Pricing typeFIRM FIXED PRICE
Obligations$13.2M
Current contract value$13.2M
Potential contract value / ceiling$13.3M
Start dateSep 1, 2023
Current end dateJun 1, 2025
Potential end dateJun 1, 2025
Latest award activityJul 31, 2025
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 16 of 16 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jul 31, 2025P25015$0THE PURPOSE OF THIS MODIFICATION IS TO REMOVE AND REPLACE SECTION C) CONTRACT VALUE IN ITS ENTIRETY FROM MODIFICATION P25014, DUE TO TYPOGRAPHICAL ERRORS.
Jul 15, 2025P25014$421.0KTHE PURPOSE OF THIS MODIFICATION IS TO EXECUTE THE INCREASED VALUE FOR THE EMMP RFC 13 RFC 14 REA 08 AND REA 09
May 6, 2025P25013$432.3KTHE PURPOSE OF THIS MODIFICATION IS TO EXECUTE THE INCREASED VALUE FOR THE EMMP MANAGEMENT, CONFLICTS WITH ABANDONED INFRASTRUCTURE AND INCORPORATE THE VAULT BACKFILL MATERIAL
Feb 5, 2025P25012$107.4KTHE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE SETTLEMENT TERMS REACHED FOR REA 07 EXECUTE RFC 12 AND ADD FUNDING TO CLIN 0003 FOR CONFLICT WITH ABANDONED INFRASTRUCTURE
Jan 28, 2025P25011$2.4MTHE PURPOSE OF THIS MODIFICATION IS TO CREATE A NEW CLIN TO ADD FUNDING ASSOCIATED WITH RFC 010 AND ITS ADDITIONAL EMMP EFFORTS VIA CLIN 0007 AND ADD OPTIONAL CLIN 0006 FOR PAVEMENT REPAIRS.
Jan 2, 2025P25010$85.6KTHE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE REQUEST FOR CHANGES RFC NO 11 REA 04 ADD THE 91 DAYS FOR RFC 10 AND INCREASE THE NTE VALUE OF CLIN 0004 ASPHALT REPAIR
Sep 17, 2024P24009$271.8KTHE PURPOSE OF THIS MODIFICATION IS TO EXECUTE REQUEST FOR CHANGES RFCS NO 07 08 AND 09 CAMPUS ADDITION BUILDING TIE IN ASPHALT REPAIR PRICING AND REQUEST FOR INFORMATION RFIS 101 102 AND 111
Aug 27, 2024P24008$229.2KINCORPORATE SETTLEMENT TERMS REACHED FOR REA 03 PROPOSAL FOR ADJUSTMENT UNILATERAL MODIFICATION P24002 ON SITE SOIL EMBANKMENT INCORPORATE SETTLEMENT TERMS REACHED FOR REA 05 REQUEST FOR EQUITABLE ADJUSTMENT SUBSURFACE CONCRETE DEMOLITION AT HEAD TA
Aug 1, 2024P24007$541.9KINCORPORATE SETTLEMENT TERMS REACHED FOR REA 01 PROPOSAL FOR ADJUSTMENT 60 DAY SUSPENSION OF GROUND DISTURBING ACTIVITIES INCORPORATE SETTLEMENT TERMS REACHED FOR REA 0 PROPOSAL FOR ADJUSTMENT 30 DAY SUSPENSION OF GROUND DISTURBING ACTIVITIES (PART
Jul 18, 2024P24006$47.2KTHE PURPOSE OF THIS MODIFICATION IS TO EXECUTE REQUEST FOR CHANGE NO 06 RFIS 81, 91, 93, 95, 96 AND 103 CHANGES AND GFE ANCHOR BOLT DESIGN AND POTHOLING WATER HANDLING
May 9, 2024P24005$239.8KTHE PURPOSE OF THIS MODIFICATION IS TO PERFORM THE FOLLOWING ACTIONS EXECUTE REQUEST FOR CHANGE NO 01 POTHOLING PROCEDURE EXECUTE REQUEST FOR CHANGE NO 02 REQUEST FOR INFORMATION (RFI) AND SUBMITTAL CHANGES EXECUTE REQUEST FOR CHANGE NO 04 PLUMBIN
Apr 23, 2024P24004$0MODIFY THE CONTRACT TO INCLUDE THE FINAL ENVIRONMENTAL ASSESSMENT (EA) ), PREVIOUSLY INCORPORATED VIA NOTICE TO PROCEED ISSUED OCTOBER 03, 2023; AND INCORPORATE THE FINAL ENVIRONMENTAL MEDIA MANAGEMENT PLAN DATED APRIL 15, 2024.
Mar 27, 2024P24003$1.3MPROVIDE DRAFT ENVIRONMENTAL MEDIA MANAGEMENT PLAN (EMMP) DATED MARCH 5, 2024, ASSOCIATED NTE AMOUNT AND UPDATE GUIDANCE PROVIDED IN MODIFICATION P24002
Mar 11, 2024P24002$0INCORPORATE IMMEDIATE USE INSTRUCTIONS FOR SEAWATER ONSITE STOCKPILING AND FILL LOCATION(S). REVISED LANGUAGE.
Mar 1, 2024P24001$0INCORPORATE IMMEDIATE USE INSTRUCTIONS FOR SEAWATER ONSITE STOCKPILING AND FILL LOCATION(S).
Jun 30, 20230$7.1MMANCHESTER SEAWATER SYSTEM REPLACEMENT AT MANCHESTER RESEARCH STATION IN PORT ORCHARD, WASHINGTON

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.