Federal contract award

140A1621F0113

HOPI DETENTION CENTER DESIGN BUILD

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of the Interior
OfficeBUREAU OF INDIAN AFFAIRS
NAICS236220 — Commercial and Institutional Building Construction
PSCY1JZ — CONSTRUCTION OF MISCELLANEOUS BUILDINGS
Parent award / vehicle140A1618D0009
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$38.5M
Current contract value$38.5M
Potential contract value / ceiling$38.5M
Start dateOct 4, 2021
Current end dateOct 31, 2025
Potential end dateOct 31, 2025
Latest award activitySep 22, 2025
Source loadedAug 15, 2026

Funding and modification history

Showing the latest 13 of 13 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Sep 22, 2025P00012$489.4KADDITIONAL WORK TO MAKE THE DETENTION CENTER FUNCTIONAL UPON COMMISSIONING.
Jul 17, 2025P00011$7.5KADDITIONAL WORK TO MAKE THE DETENTION CENTER FUNCTIONAL UPON COMMISSIONING.
Apr 3, 2025P00010$1.1MADDITIONAL WORK TO MAKE THE DETENTION CENTER FUNCTIONAL UPON COMMISSIONING.
Mar 14, 2025P00009$63.6KMODIFICATION IN RESPONSE TO REA FOR MATERIAL PRICE ESCALATION CAUSED BY GOVERNMENTAL DELAYS.
Dec 17, 2024P00008$612.6KADD SPRINKLER COVERINGS IN THE MALE AND FEMALE DORMITORIES AND MOVEABLE FF&E FOR BREAKROOMS AND OFFICES. EXTEND PERIOD OF PERFORMANCE COMPLETION DATE TO 04/24/2025 FOR THE HOPI DETENTION CENTER DESIGN-BUILD PROJECT
Aug 1, 2024P00007$553.6KADD SECURITY SYSTEM AND SHADE STRUCTURE UPGRADES. EXTEND PERIOD OF PERFORMANCE COMPLETION DATE TO 12/24/2024 FOR THE HOPI DETENTION CENTER DESIGN-BUILD PROJECT
May 10, 2024P00006$144.0KADDITIONAL WATER CONNECTIONS, METERS AND EXTEND PERIOD OF PERFORMANCE COMPLETION DATE TO 10/25/2024 FOR THE HOPI DETENTION CENTER DESIGN/BUILD PROJECT
Nov 29, 2023P00005$0EXTEND PERIOD OF PERFORMANCE COMPLETION DATE TO 7/31/2024 FOR THE HOPI DETENTION CENTER DESIGN/BUILD PROJECT
Apr 17, 2023P00004$34.6KADD WATERPROOF LIGHTS IN THE DETAINEE AREAS FOR HOPI DETENTION CENTER DESIGN BUILD PROJECT
Mar 21, 2023P00003$202.8KHOPI DETENTION CENTER DESIGN BUILD
Apr 13, 2022P00002$174.4KHOPI DETENTION CENTER DESIGN BUILD
Mar 15, 2022P00001$611.7KHOPI DETENTION CENTER DESIGN BUILD
Sep 7, 20210$34.5MHOPI DETENTION CENTER DESIGN BUILD