Federal contract award

140E0126F0001

PROJECT MANAGEMENT AND OVERSIGHT SERVICES FOR MAKE SAFE, DIAGNOSTICS, AND TEMPORARY ABANDONMENT OPERATIONS AT THE WEST DELTA 117H AND HIGH ISLAND A589 PLATFORMS IN THE GULF OF AMERICA OCS. THE OBJECTIVE OF THIS TASK ORDER IS TO OBTAIN PROJECT MANAGE

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of the Interior
OfficeACQUISITION MANAGEMENT DIVISION
NAICS237120 — Oil and Gas Pipeline and Related Structures Construction
PSCR408 — Program Management/Support Services
Parent award / vehicle140E0123D0005
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$804.0K
Current contract value$804.0K
Potential contract value / ceiling$1.8M
Start dateOct 20, 2025
Current end dateOct 19, 2026
Potential end dateOct 19, 2026
Latest award activityMay 6, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 5 of 5 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
May 6, 2026P00004$42.3KMOD P00004: EXTENDED OVERSITE AND WAITING ON WEATHER DELAY COSTS THE PURPOSE OF MODIFICATION P00004 IS TO ACCOUNT FOR AN ADDITIONAL 15 DAYS OF OVERSITE DUE TO DELAYS ASSOCIATED WITH VARIOUS WEATHER EVENTS FROM JANUARY 31ST THROUGH MARCH 16, 2026,
Mar 10, 2026P00003$53.6KMOD P00003: EXTENDED OVERSITE AND WAITING ON WEATHER DELAY COSTS THE PURPOSE OF THIS BILATERAL MODIFICATION IS TO ACCOUNT FOR 19 ADDITIONAL DAYS OF OVERSITE TOTALING $45,550.00 AND DELAYS ASSOCIATED WITH VARIOUS WEATHER EVENTS ON JANUARY 3RD, JANU
Jan 28, 2026P00002$25.0KMOD P00002: WAITING ON WEATHER DELAY COSTS THE PURPOSE OF THIS BILATERAL MODIFICATION IS TO ACCOUNT FOR DELAYS, ASSOCIATED WITH VARIOUS WEATHER EVENTS, FROM NOVEMBER 9, 2025, THROUGH DECEMBER 2, 2025, IN THE AMOUNT OF $25,014.00. THE TASK OR
Nov 20, 2025P00001$0MOD P00001: CHANGE KEY PERSONNEL AND CONTRACTING OFFICER THE PURPOSE OF THIS BILATERAL MODIFICATION IS TO MAKE THE FOLLOWING CHANGES: 1. THE PROJECT COORDINATOR IS CHANGED FROM MR. LUIS MOLINA TO MR. WARREN ACEVEDO AT NO ADDITIONAL COST TO TH
Oct 20, 20250$683.1KPROJECT MANAGEMENT AND OVERSIGHT SERVICES FOR MAKE SAFE, DIAGNOSTICS, AND TEMPORARY ABANDONMENT OPERATIONS AT THE WEST DELTA 117H AND HIGH ISLAND A589 PLATFORMS IN THE GULF OF AMERICA OCS. THE OBJECTIVE OF THIS TASK ORDER IS TO OBTAIN PROJECT MANAGE

Research next steps

  1. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.