Federal contract award

140F0822F0016

CONSTRUCT NEW VISITOR'S CENTER AT SENEY NATIONAL WILDLIFE REFUGE

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of the Interior
OfficeFWS, GAOA
NAICS236220 — Commercial and Institutional Building Construction
PSCY1AA — CONSTRUCTION OF OFFICE BUILDINGS
Parent award / vehicle140F0822D0006
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$10.1M
Current contract value$10.1M
Potential contract value / ceiling$10.1M
Start dateSep 16, 2022
Current end dateJul 28, 2026
Potential end dateJul 28, 2026
Latest award activityJun 12, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 30 of 30 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jun 12, 2026P00029$0MOD 29: POP EXTENSION
Mar 12, 2026P00028$0MOD 28: CHANGE CO FROM RYAN BOISVERT TO JUSTINE COLEMAN
Dec 15, 2025P00027$0MOD 27: TO DEFINITIZE A MANUAL MODIFICATION LETTER WHICH RESCINDED THE GOVERNMENT'S NOTICE OF TERMINATION FOR DEFAULT.
Aug 6, 2025P00026$0CONSTRUCT NEW VISITOR'S CENTER AT SENEY NATIONAL WILDLIFE REFUGE
Jul 1, 2025P00025$18.0KCONSTRUCT NEW VISITOR'S CENTER AT SENEY NATIONAL WILDLIFE REFUGE MOD 25: HVAC RELATED WORK/TRUSS REDESIGN
Jun 2, 2025P00024$6.2KCONSTRUCT NEW VISITOR'S CENTER AT SENEY NATIONAL WILDLIFE REFUGE MOD 24: GLB CONNECTION, RECEPTION ROOM 102 SOFFIT, AND HARD CEILING SUPPORT CHANGES
May 22, 2025P00023$0CONSTRUCT NEW VISITOR'S CENTER AT SENEY NATIONAL WILDLIFE REFUGE MOD 23: POP EXTENSION
Apr 30, 2025P00022$1.9KCONSTRUCT NEW VISITOR'S CENTER AT SENEY NATIONAL WILDLIFE REFUGE MOD 22: WATER FOUNTAIN CHANGES
Apr 8, 2025P00021$0CONSTRUCT NEW VISITOR'S CENTER AT SENEY NATIONAL WILDLIFE REFUGE MOD 21: POP EXTENSION
Feb 5, 2025P00020$23.5KCONSTRUCT NEW VISITOR'S CENTER AT SENEY NATIONAL WILDLIFE REFUGE MOD 20: TRUSS MODIFICATION
Dec 19, 2024P00019$17.3KCONSTRUCT NEW VISITOR'S CENTER AT SENEY NATIONAL WILDLIFE REFUGE MOD 19: EXHIBIT ALTERATIONS
Aug 23, 2024P00018$-8.6KCONSTRUCT NEW VISITOR'S CENTER AT SENEY NATIONAL WILDLIFE REFUGE MOD 18: INTRUSION DETECTION SYSTEM
Aug 21, 2024P00017$56.4KCONSTRUCT NEW VISITOR'S CENTER AT SENEY NATIONAL WILDLIFE REFUGE MOD 17: ELECTRICAL TRANSFORMER INSTALLATION
Aug 6, 2024P00016$0CONSTRUCT NEW VISITOR'S CENTER AT SENEY NATIONAL WILDLIFE REFUGE MOD 16: CHANGE ORDER FOR ELECTRICAL TRANSFORMER INSTALLATION
Jul 17, 2024P00015$31.1KCONSTRUCT NEW VISITOR'S CENTER AT SENEY NATIONAL WILDLIFE REFUGE MOD 15: SUB-SLAB WORK
Jan 24, 2024P00014$272.2KCONSTRUCT NEW VISITOR'S CENTER AT SENEY NATIONAL WILDLIFE REFUGE MOD 14: CHANGE ORDER
Dec 6, 2023P00013$0CONSTRUCT NEW VISITOR'S CENTER AT SENEY NATIONAL WILDLIFE REFUGE MOD 13: CHANGE ORDER
Oct 30, 2023P00012$15.9KCONSTRUCT NEW VISITOR'S CENTER AT SENEY NATIONAL WILDLIFE REFUGE MOD 12: SUPPLEMENTAL AGREEMENT
Sep 18, 2023P00011$34.6KCONSTRUCT NEW VISITOR'S CENTER AT SENEY NATIONAL WILDLIFE REFUGE MOD 11: SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE
Sep 11, 2023P00010$0CONSTRUCT NEW VISITOR'S CENTER AT SENEY NATIONAL WILDLIFE REFUGE MOD 10: PAYMENT CLAUSE UPDATE
Aug 25, 2023P00009$0CONSTRUCT NEW VISITOR'S CENTER AT SENEY NATIONAL WILDLIFE REFUGE
Aug 16, 2023P00008$9.6KCONSTRUCT NEW VISITOR'S CENTER AT SENEY NATIONAL WILDLIFE REFUGE
Aug 3, 2023P00007$31.0KCONSTRUCT NEW VISITOR'S CENTER AT SENEY NATIONAL WILDLIFE REFUGE
Jul 17, 2023P00006$9.6KCONSTRUCT NEW VISITOR'S CENTER AT SENEY NATIONAL WILDLIFE REFUGE
Jun 21, 2023P00005$23.2KCONSTRUCT NEW VISITOR'S CENTER AT SENEY NATIONAL WILDLIFE REFUGE
Jun 20, 2023P00004$29.4KCONSTRUCT NEW VISITOR'S CENTER AT SENEY NATIONAL WILDLIFE REFUGE
Apr 18, 2023P00003$0CONSTRUCT NEW VISITOR'S CENTER AT SENEY NATIONAL WILDLIFE REFUGE MOD 2: PERIOD OF PERFORMANCE EXTENSION
Jan 10, 2023P00002$0CONSTRUCT NEW VISITOR'S CENTER AT SENEY NATIONAL WILDLIFE REFUGE MOD 2: PERIOD OF PERFORMANCE EXTENSION
Jan 5, 2023P00001$-2.9KCONSTRUCT NEW VISITOR'S CENTER AT SENEY NATIONAL WILDLIFE REFUGE MOD 1: DEOBLIGATE FUNDS DUE TO DAMAGE ON SITE
Sep 16, 20220$9.6MCONSTRUCT NEW VISITOR'S CENTER AT SENEY NATIONAL WILDLIFE REFUGE