RYDELL MAINTENANCE BUILDING
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of the Interior |
| Office | FWS, CONSTRUCTION A/E TEAM 2 |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Y1AA — CONSTRUCTION OF OFFICE BUILDINGS |
| Parent award / vehicle | 140F0822D0054 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $3.1M |
| Current contract value | $3.1M |
| Potential contract value / ceiling | $3.1M |
| Start date | Sep 20, 2024 |
| Current end date | Jun 6, 2026 |
| Potential end date | Jun 6, 2026 |
| Latest award activity | May 8, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 10 of 10 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 8, 2026 | P00009 | $2.6K | EO 14398 - MOD-P00009 FOR RYDELL MAINTENANCE BUILDING IS ISSUED TO EXTEND THE PERIOD OF PERFORMANCE BY (37) CALENDAR DAYS TO SATURDAY, JUNE 6, 2026, AND INCREASE THE TOTAL CONTRACT VALUE FOR ADDITIONAL WORK BY $2,567.24 FOR A NEW TOTAL CONTRACT VALUE |
| Apr 3, 2026 | P00008 | $0 | MOD-P00008 FOR RYDELL MAINTENANCE BUILDING IS ISSUED TO EXTEND THE PERIOD OF PERFORMANCE BY (69) CALENDAR DAYS TO THURSDAY, APRIL 30, 2026. |
| Jan 21, 2026 | P00007 | $4.2K | MOD-P00007 IS ISSUED TO EXTEND THE PERIOD OF PERFORMANCE BY (28) CALENDAR DAYS AND INCREASE THE TOTAL CONTRACT VALUE FOR ADDITIONAL WORK BY $4,163.50 FOR A NEW TOTAL CONTRACT VALUE OF $3,118,990.86. |
| Jan 14, 2026 | P00006 | $19.2K | MOD-P00006 IS ISSUED TO INCREASE THE TOTAL CONTRACT VALUE BY $19,234.60, FOR THE FOLLOWING ADDITIONAL WORK: INSTALL ICE MAKER. REMOVAL, TRANSPORTATION, AND INSTALLATION OF FUEL TANKS. |
| Jan 13, 2026 | P00005 | $31.7K | THE PURPOSE OF THIS MODIFICATION IS FOR ADDITIONAL WORK/ENSURE COMPLIANCE WITH UPDATED FEDERAL GUIDANCE AND TO ELIMINATE NON-STATUTORY SUSTAINABILITY REQUIREMENTS, AS WELL AS ENHANCE THE REPRESENTATIONAL AND CERTIFICATION CLAUSES WITHIN THE CONTRACT. |
| Sep 16, 2025 | P00004 | $14.3K | MOD-P00004 FOR RYDELL MAINTENANCE BUILDING IS ISSUED TO EXTEND THE PERIOD OF PERFORMANCE BY (14) CALENDAR DAYS TO MONDAY, OCTOBER 20, 2025, AND INCREASE THE TOTAL CONTRACT VALUE FOR ADDITIONAL WORK BY $14,302.89 FOR A NEW TOTAL CONTRACT VALUE OF $3,0 |
| Aug 4, 2025 | P00003 | $0 | MOD-P00003 IS ISSUED TO EXTEND THE PERIOD OF PERFORMANCE, AT NO COST, TO MONDAY, OCTOBER 6, 2025. |
| Jul 17, 2025 | P00002 | $5.6K | MOD-P00002 IS ISSUED TO INCREASE THE TOTAL CONTRACT VALUE BY $5,551.50, FOR ADDITIONAL WORK TO EXECUTE SEPTIC SYSTEM UPGRADES PER POLK COUNTY, MN SEPTIC PERMIT. THESE INCLUDE INCREASING THE SIZE OF THE SEPTIC TANK FROM 1,000 GALLONS TO 1,500 GALLONS, |
| May 1, 2025 | P00001 | $0 | MOD-P00001 FOR RYDELL MAINTENANCE BUILDING IS ISSUED TO UNILATERALLY MODIFY THE ADMINISTRATIVE POINTS OF CONTACT OF THE CONTRACTING OFFICER (CO) AND CONTRACTING OFFICERS REPRESENTATIVE (COR). |
| Sep 20, 2024 | 0 | $3.0M | RYDELL MAINTENANCE BUILDING |