Federal contract award
140P1225F0024
GRSA REPLACE VISITOR CENTER ROOF
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of the Interior |
| Office | IMR INTERMOUNTAIN REGION(1200) |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Z1AZ — MAINTENANCE OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS |
| Parent award / vehicle | 140P1223D0008 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $1.1M |
| Current contract value | $1.1M |
| Potential contract value / ceiling | $1.1M |
| Start date | Jun 17, 2025 |
| Current end date | Mar 9, 2026 |
| Potential end date | Mar 9, 2026 |
| Latest award activity | Jan 16, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 6 of 6 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jan 16, 2026 | P00005 | $26.6K | DIFFERING SITE CONDITIONS |
| Dec 16, 2025 | P00004 | $8.2K | THE PURPOSE OF THIS MODIFICATION P00004 IS TO PROVIDE FUNDING IN THE AMOUNT OF $8,186.04 FOR THE DIFFERING SITE CONDITIONS ABANDONED GAS LINE AND DAMAGED DRAIN PIPES. THIS FUNDING INCREASES THE TOTAL AWARD VALUE TO $1,118,187.59. |
| Dec 5, 2025 | P00003 | $24.3K | THE PURPOSE OF THIS NO COST MODIFICATION P00002 EXTEND THE PERIOD OF PERFORMANCE FROM 11 NOVEMBER 025 TO 19 FEBRUARY 2026 PER THE REVISED SCHEDULE. THE POP EXTENSION IS REQUIRED TO ACCOMPLISH THE REMAINING WORK, INSPECTIONS, AND CLOSE OUT ACTIONS. |
| Nov 12, 2025 | P00002 | $0 | THE PURPOSE OF THIS NO COST MODIFICATION P00002 EXTEND THE PERIOD OF PERFORMANCE FROM 11 NOVEMBER 025 TO 19 FEBRUARY 2026 PER THE REVISED SCHEDULE. THE POP EXTENSION IS REQUIRED TO ACCOMPLISH THE REMAINING WORK, INSPECTIONS, AND CLOSE OUT ACTIONS. |
| Sep 9, 2025 | P00001 | $0 | GRSA REPLACE VISITOR CENTER ROOF |
| Jun 17, 2025 | 0 | $1.1M | GRSA REPLACE VISITOR CENTER ROOF |