Federal contract award
140P2024C0051
THIS PROJECT WILL RESTORE THE ROMO BARN AND SHED PREVIOUSLY DESTROYED BY FIRE.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of the Interior |
| Office | DSC CONTRACTING SERVICES DIVISION |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Y1AZ — CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS |
| Parent award / vehicle | Not reported |
| Set-aside | SMALL BUSINESS SET ASIDE - TOTAL |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $4.1M |
| Current contract value | $4.1M |
| Potential contract value / ceiling | $4.1M |
| Start date | Jul 1, 2024 |
| Current end date | Feb 21, 2026 |
| Potential end date | Feb 21, 2026 |
| Latest award activity | Feb 4, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 7 of 7 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Feb 4, 2026 | P00006 | $25.2K | ROCKY MOUNTAIN NATIONAL PARK - ROMO 316223 - THIS MODIFICATION IS TO: 1) PROVIDE COMPENSATION TO THE CONTRACTOR FOR THE EXCAVATION AND REMOVAL OF THE UNKNOWN BOULDERS AT THE JOB SITE. 2) ADD AN ADDITIONAL 14 DAYS TO THE PERIOD OF PERFORMANCE. |
| Nov 24, 2025 | P00005 | $28.3K | ROCKY MOUNTAIN NATIONAL PARK - ROMO 316223 - THIS MODIFICATION IS TO: 1) PROVIDE COMPENSATION TO THE CONTRACTOR FOR THE EXCAVATION AND REMOVAL OF THE UNKNOWN BOULDERS AT THE JOB SITE. 2) ADD AN ADDITIONAL 14 DAYS TO THE PERIOD OF PERFORMANCE. |
| Nov 18, 2025 | P00004 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO ENSURE COMPLIANCE WITH UPDATED FEDERAL GUIDANCE AND TO ELIMINATE NON-STATUTORY SUSTAINABILITY REQUIREMENTS, AS WELL AS ENHANCE THE REPRESENTATIONAL AND CERTIFICATION CLAUSES WITHIN THE CONTRACT. |
| Jul 1, 2025 | P00003 | $0 | ROCKY MOUNTAIN NATIONAL PARK - ROMO 316223 - THIS MODIFICATION IS TO: 1) UNSUSPEND WORK FOR THE REFERENCED PROJECT AS OF MAY 27, 2025. THIS WILL ADD 173 DAYS TO THE PROJECT DUE TO WINTER SHUTDOWN. 2)INSERT/DELETE CLAUSES ON THE ATTACHED DOCUMENT. |
| Dec 16, 2024 | P00002 | $0 | THIS PROJECT WILL RESTORE THE ROMO BARN AND SHED PREVIOUSLY DESTROYED BY FIRE. THIS ACTION EXERCISES OPTION B ADDING THE PHOTOVOLTAIC REQUIREMENT TO THE CONTRACT. |
| Aug 20, 2024 | P00001 | $103.8K | THIS PROJECT WILL RESTORE THE ROMO BARN AND SHED PREVIOUSLY DESTROYED BY FIRE. THIS ACTION EXERCISES OPTION B ADDING THE PHOTOVOLTAIC REQUIREMENT TO THE CONTRACT. |
| Jul 1, 2024 | 0 | $4.0M | THIS PROJECT WILL RESTORE THE ROMO BARN AND SHED PREVIOUSLY DESTROYED BY FIRE. |