Federal contract award
140P5125C0021
THE PRIMARY OBJECTIVE OF THE PROJECT IS TO REPLACE THE PONY PEN HAY BARN. THE PROJECT SHALL DEMOLISH THE OLD BARN BUILDING DOWN TO PILINGS AND GIRDERS AND CONSTRUCTION OF NEW BARN, LEAN TOO SHED ROOF AND WALLS TO REMAIN AND BE REATTACHED TO NEW BUILD
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of the Interior |
| Office | SER EAST MABO(51000) |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Z1JZ — MAINTENANCE OF MISCELLANEOUS BUILDINGS |
| Parent award / vehicle | Not reported |
| Set-aside | WOMEN OWNED SMALL BUSINESS |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $260.2K |
| Current contract value | $260.2K |
| Potential contract value / ceiling | $260.2K |
| Start date | Jul 21, 2025 |
| Current end date | Apr 30, 2026 |
| Potential end date | Apr 30, 2026 |
| Latest award activity | Mar 11, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Mar 11, 2026 | P00003 | $8.6K | THE PURPOSE OF THIS MODIFICATION IS FOR IN-SCOPE CHANGES. CONTRACT LINE ITEM NUMBER 00030 IS ADDED IN THE AMOUNT OF $8,589.25 FOR IN-SCOPE CHANGES TO INSTALL TRIM AROUND THE WALL VENTS AND BOX-IN ROOF EAVES. THE TOTAL COST OF THE CONTRACT HAS |
| Jan 16, 2026 | P00002 | $27.3K | THE PURPOSE OF THIS MODIFICATION IS FOR IN-SCOPE CHANGES AND EXTEND THE PERIOD OF PERFORMANCE. DUE TO UNFORESEEN SITE CONDITIONS CONTRACT LINE ITEM NUMBER 00020 IS ADDED IN THE AMOUNT OF $27,287.75 FOR IN-SCOPE CHANGES. THE TOTAL COST OF THE CO |
| Nov 18, 2025 | P00001 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO ENSURE COMPLIANCE WITH UPDATED FEDERAL GUIDANCE AND TO ELIMINATE NON-STATUTORY SUSTAINABILITY REQUIREMENTS, AS WELL AS ENHANCE THE REPRESENTATIONAL AND CERTIFICATION CLAUSES WITHIN THE CONTRACT. |
| Jul 23, 2025 | 0 | $224.3K | THE PRIMARY OBJECTIVE OF THE PROJECT IS TO REPLACE THE PONY PEN HAY BARN. THE PROJECT SHALL DEMOLISH THE OLD BARN BUILDING DOWN TO PILINGS AND GIRDERS AND CONSTRUCTION OF NEW BARN, LEAN TOO SHED ROOF AND WALLS TO REMAIN AND BE REATTACHED TO NEW BUILD |
Buyer contacts from matching notices
Matched on exact award/solicitation identifier and awarding agency. Source dates describe the notice, not current contact verification.