Federal contract award
140P8323F0019
TASK ORDER TO FABRICATE AND INSTALL REPLACEMENT SPALDING VISITOR CENTER MUSEUM EXHIBITS AGAINST ESTABLISHED NATIONAL PARK SERVICE (NPS) IDIQ CONTRACT, NEZ PERCE NATIONAL HISTORICAL PARK (NEPE)
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of the Interior |
| Office | PWR OLYM MABO(83000) |
| NAICS | 337212 — Custom Architectural Woodwork and Millwork Manufacturing |
| PSC | Y1PB — CONSTRUCTION OF EXHIBIT DESIGN (NON-BUILDING) |
| Parent award / vehicle | 140P2122D0007 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $1.3M |
| Current contract value | $1.3M |
| Potential contract value / ceiling | $1.3M |
| Start date | May 10, 2023 |
| Current end date | Oct 31, 2025 |
| Potential end date | Oct 31, 2025 |
| Latest award activity | Jul 30, 2025 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 7 of 7 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jul 30, 2025 | P00006 | $0 | MODIFICATION 6: EXTEND PERIOD OF PERFORMANCE (COMPLETION DATE CHANGED TO 10/31/25). MODIFICATION 5: EXTEND PERIOD OF PERFORMANCE (COMPLETION DATE CHANGED TO 8/29/25). MODIFICATION 4: CORRECTION TO UPDATE COMPLETION DATE OF CLIN10, 20, AND 30, TO MATC |
| Jul 28, 2025 | P00005 | $0 | MODIFICATION 5: EXTEND PERIOD OF PERFORMANCE. MODIFICATION 4: CORRECTION TO UPDATE COMPLETION DATE OF CLIN10, 20, AND 30, TO MATCH COMPLETION DATE OF CLIN40 WHICH WAS ADDED AT TIME OF MOD 3. MODIFICATION 3: ADDITIONAL WORK WITHIN SCOPE AND EXTEND PER |
| Jul 19, 2024 | P00004 | $0 | MODIFICATION 4: CORRECTION TO UPDATE COMPLETION DATE OF CLIN10, 20, AND 30, TO MATCH COMPLETION DATE OF CLIN40 WHICH WAS ADDED AT TIME OF MOD 3. MODIFICATION 3: ADDITIONAL WORK WITHIN SCOPE AND EXTEND PERIOD OF PERFORMANCE. MODIFICATION 2: UNILATERAL |
| Feb 5, 2024 | P00003 | $21.1K | MODIFICATION 3: ADDITIONAL WORK WITHIN SCOPE AND EXTEND PERIOD OF PERFORMANCE. MODIFICATION 2: UNILATERAL ADMIN MOD TO CHANGE RECEIVER ROLE NAME FOR IPP INVOICE PROCESSING AND PAYMENT TERM FROM PP30 TO ACCP TO MATCH IDIQ CONTRACT PAYMENT TERM. MODIFI |
| Sep 11, 2023 | P00002 | $0 | MODIFICATION 2: UNILATERAL ADMIN MOD TO CHANGE RECEIVER ROLE NAME FOR IPP INVOICE PROCESSING AND PAYMENT TERM FROM PP30 TO ACCP TO MATCH IDIQ CONTRACT PAYMENT TERM. MODIFICATION 1: EXERCISE OPTION TO ADD FILMING INTO THE TASK ORDER. ORIGINAL DESCRIPT |
| Aug 25, 2023 | P00001 | $122.8K | MODIFICATION 2: EXERCISE OPTION TO ADD FILMING INTO THE TASK ORDER. MODIFICATION 1: EXTEND PERIOD OF PERFORMANCE. ORIGINAL DESCRIPTION: TASK ORDER TO FABRICATE AND INSTALL REPLACEMENT SPALDING VISITOR CENTER MUSEUM EXHIBITS AGAINST ESTABLISHED NATION |
| May 10, 2023 | 0 | $1.2M | TASK ORDER TO FABRICATE AND INSTALL REPLACEMENT SPALDING VISITOR CENTER MUSEUM EXHIBITS AGAINST ESTABLISHED NATIONAL PARK SERVICE (NPS) IDIQ CONTRACT, NEZ PERCE NATIONAL HISTORICAL PARK (NEPE) |
Research next steps
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.