Federal contract award
140P8424P0060
THE NATIONAL PARK SERVICE (NPS) AT LASSEN VOLCANIC NATIONAL PARK HAS A REQUIREMENT FOR SUPPLY AND DELIVERY OF CONCRETE PARKING BUMPERS. THE PROJECT IS LOCATED AT LASSEN VOLCANIC NATIONAL PARK, LASSEN, PLUMAS, TEHAMA, AND SHASTA COUNTIES, CA.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of the Interior |
| Office | PWR PORE MABO (84000) |
| NAICS | 238990 — All Other Specialty Trade Contractors |
| PSC | 5620 — Tile, Brick, and Block |
| Parent award / vehicle | Not reported |
| Set-aside | SMALL BUSINESS SET ASIDE - TOTAL |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $128.7K |
| Current contract value | $128.7K |
| Potential contract value / ceiling | $128.7K |
| Start date | Jun 26, 2024 |
| Current end date | Dec 20, 2024 |
| Potential end date | Dec 20, 2024 |
| Latest award activity | Sep 15, 2025 |
| Source loaded | Aug 15, 2026 |
Funding and modification history
Showing the latest 2 of 2 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Sep 15, 2025 | P00002 | $-3.3K | THE PURPOSE OF THIS MODIFICATION P00002 IS TO DE-OBLIGATE REMAINING FUNDING IN THE AMOUNT OF $3333.33. THE TOTAL CONTRACT AMOUNT WILL BE REDUCED BY $3333.33 AND HAVE AN ENDING CONTRACT AMOUNT OF $128,748.92. THE NATIONAL PARK SERVICE (NPS) AT LASS |
| Dec 9, 2024 | P00001 | $0 | THE PURPOSE OF THIS MODIFICATION P00001 IS TO EXTEND THE PERIOD OF PERFORMANCE FROM 10/31/2024 TO 12/20/2024 WITH THE CONSIDERATION OF A $3,333.34 DEDUCTION IN THE FINAL CONTRACT PRICE AND TO DESIGNATE JOE PETTEGREW AS THE COR FOR THE REMAINDER OF TH |
Buyer contacts from matching notices
Matched on exact award/solicitation identifier and awarding agency. Source dates describe the notice, not current contact verification.
Research next steps
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.