Federal contract award
140P8524C0005
HAWK HILL PHASE 3 IMPROVEMENTS, GOLDEN GATE NATIONAL RECREATION AREA, SAUSALITO, CALIFORNIA.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of the Interior |
| Office | PWR SF/SEA MABO(85000) |
| NAICS | 238990 — All Other Specialty Trade Contractors |
| PSC | Y1PA — CONSTRUCTION OF RECREATION FACILITIES (NON-BUILDING) |
| Parent award / vehicle | Not reported |
| Set-aside | 8(A) SOLE SOURCE |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $3.5M |
| Current contract value | $3.5M |
| Potential contract value / ceiling | $3.5M |
| Start date | Sep 20, 2024 |
| Current end date | Dec 4, 2025 |
| Potential end date | Dec 4, 2025 |
| Latest award activity | Nov 20, 2025 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Nov 20, 2025 | P00003 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO ENSURE COMPLIANCE WITH UPDATED FEDERAL GUIDANCE AND TO ELIMINATE NON-STATUTORY SUSTAINABILITY REQUIREMENTS, AS WELL AS ENHANCE THE REPRESENTATIONAL AND CERTIFICATION CLAUSES WITHIN THE CONTRACT. |
| Sep 24, 2025 | P00002 | $-65.8K | HAWK HILL PHASE 3 IMPROVEMENTS, GOLDEN GATE NATIONAL RECREATION AREA, SAUSALITO, CALIFORNIA. MODIFICATION P00002 IS FOR EIGHT FIELD CHANGES LISTED UNDER ARCHITECT'S SUPPLEMENTAL INSTRUCTIONS (ASI) 12, 20, 17, 9, 19, AND RFI 14. THIS MODIFICA |
| Jun 5, 2025 | P00001 | $27.3K | HAWK HILL PHASE 3 IMPROVEMENTS, GOLDEN GATE NATIONAL RECREATION AREA, SAUSALITO, CALIFORNIA. MODIFICATION P00001 IS IN RESPONSE TO RFI 01 R2 AND REA 01 R2 FOR ADDITIONAL BMPS REQUIRED FOR THE INSTALLATION OF THE TEMPORARY ACCESS ROAD AND FOR ADDI |
| Sep 20, 2024 | 0 | $3.5M | HAWK HILL PHASE 3 IMPROVEMENTS, GOLDEN GATE NATIONAL RECREATION AREA, SAUSALITO, CALIFORNIA. |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.