GRAND COULEE THIRD POWERPLANT CRANE CONTROLS PART II INSPECTION, EVALUATION, AND DESIGN MODIFICATIONS, GRAND COULEE POWER OFFICE (GCPO), GRAND COULEE, WA
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of the Interior |
| Office | PACIFIC NW REGION PN 6615 |
| NAICS | 541330 — Engineering Services |
| PSC | C211 — Architect - Engineer Services (including landscaping, interior layout, and designing) |
| Parent award / vehicle | INR13PC10008 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $1.5M |
| Current contract value | $1.5M |
| Potential contract value / ceiling | $1.5M |
| Start date | Aug 10, 2018 |
| Current end date | Dec 19, 2025 |
| Potential end date | Dec 19, 2025 |
| Latest award activity | Jun 4, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 22 of 22 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jun 4, 2026 | P00021 | $0 | GRAND COULEE THIRD POWER PLANT CRANE CONTROLS A/E TO - P00020 CLOSEOUT |
| Jun 2, 2026 | P00020 | $-0 | GRAND COULEE THIRD POWER PLANT CRANE CONTROLS A/E TO - P00020 CLOSEOUT |
| Oct 14, 2025 | P00019 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO CORRECT ALL CLINS TO THE EXISTING PERIOD OF PERFORMANCE. |
| Sep 14, 2025 | P00018 | $35.4K | THE PURPOSE OF THIS MODIFICATION IS TO CHANGE THE PERIOD OF PERFORMANCE AND AUTHORIZE ADDITIONAL CONSTRUCTION SUPPORT THROUGH THE COMPLETION OF CONSTRUCTION. |
| Apr 14, 2025 | P00017 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO CHANGE THE CONTRACTING OFFICER FROM SCOTT COOPER TO COLBY CLIFFORD. |
| Feb 21, 2025 | P00016 | $-1.7K | THE PURPOSE OF THIS MODIFICATION IS DEFINITIZE UNILATERAL MODIFICATIONS P00013 AND P00015. |
| Nov 22, 2024 | P00015 | $0 | THE PURPOSE OF THIS CHANGE ORDER IS TO EXTEND THE PERIOD OF PERFORMANCE FOR CONSTRUCTION SUPPORT SERVICES TO COINCIDE WITH THE PROJECTED CONSTRUCTION COMPLETION DATE. |
| Sep 5, 2024 | P00014 | $62.1K | THE PURPOSE OF THIS MODIFICATION IS TO EXERCISE OPTIONAL TASK 6 FOR 30 ADDITIONAL RFI REVIEWS. |
| Aug 23, 2024 | P00013 | $49.8K | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE FOR CONSTRUCTION SUPPORT SERVICES TO COINCIDE WITH THE CONSTRUCTION COMPLETION DATE. |
| Apr 10, 2024 | P00012 | $37.9K | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE FOR CONSTRUCTION SUPPORT SERVICES TO COINCIDE WITH THE CONSTRUCTION COMPLETION DATE. |
| Feb 22, 2024 | P00011 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO CORRECT ALL CLINS TO THE EXISTING PERIOD OF PERFORMANCE. |
| Jun 23, 2023 | P00010 | $346.7K | THE STATEMENT OF WORK ADDS REVIEWS OF SUBMITTALS, RFIS, PROPOSALS AND A SITE VISIT. AN OPTIONAL TASK HAS BEEN INCLUDED TO REVIEW ADDITIONAL RFIS IF REQUIRED. THE PERIOD OF PERFORMANCE IS ALSO BEING EXTENDED. |
| Apr 12, 2023 | P00009 | $98.0K | THE PURPOSE OF THIS MODIFICATION IS TO SETTLE A REQUEST FOR EQUITABLE ADJUSTMENT AS PROPOSED BY THE CONTRACTOR. |
| Mar 23, 2023 | P00008 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE FROM 03/24/2023 TO 10/23/2023 AND THE CONTRACTING OFFICER DUTIES ARE BEING TRANSFERRED FROM COLBY CLIFFORD TO SCOTT COOPER. |
| Feb 1, 2022 | P00007 | $-99.3K | THE PURPOSE OF THIS MODIFICATION IS TO DESCOPE ENGINEERING SUPPORT FOR THIRD POWER PLANT RAHCO 2000-TON CRANE. DEFINING TASK 5 OPTIONAL TASK - ENGINEERING SUPPORT DURING CONSTRUCTION FOR ONLY THE 70 TON DRAFT TUBE GANTRY CRANE. |
| Jan 21, 2022 | P00006 | $0 | THE PURPOSE OF THIS ADMINISTRATIVE MODIFICATION IS TO COMPLETE THE ACTIONS NEEDED TO EXTEND THE PERIOD OF PERFORMANCE EXECUTED IN MODIFICATION P00005. |
| Nov 17, 2021 | P00005 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE TO 03/24/2023. |
| May 25, 2021 | P00004 | $442.9K | GRAND COULEE THIRD POWERPLANT CRANE CONTROLS, MODIFICATION P00004 EXERCISES OPTIONAL TASK - ENGINEERING SUPPORT DURING CONSTRUCTION. |
| Mar 9, 2021 | P00003 | $0 | GRAND COULEE THIRD POWERPLANT CRANE CONTROLS, MODIFICATION P00003 CHANGES CONTRACTING AUTHORITY TO COLBY A. CLIFFORD. |
| Aug 14, 2019 | P00002 | $0 | GRAND COULEE THIRD POWERPLANT CRANE CONTROLS, MODIFICATION P00002 CHANGES CONTRACTING AUTHORITY TO CONNIE GORDON FROM PREVIOUSLY NAME CONTRACTING OFFICER. |
| Jul 12, 2019 | P00001 | $130.3K | MODIFICATION P00001 REVISES SOW, CHANGES DELIVERY DATE FOR CLIN 00010, AND CLARIFIES DELIVERY DESCRIPTION OF CLIN00020. |
| Aug 10, 2018 | 0 | $361.1K | GRAND COULEE THIRD POWERPLANT CRANE CONTROLS PART II INSPECTION, EVALUATION, AND DESIGN MODIFICATIONS, GRAND COULEE POWER OFFICE (GCPO), GRAND COULEE, WA |