Federal contract award
140R1022C0006
SURETY TAKING OVER AND COMPLETING THE WORK REQUIRED BY CONTRACT R16PC00143, AS MODIFIED, IN ACCORDANCE WITH ALL THE TERMS AND CONDITIONS OF THE CONTRACT UPON THE EXPRESS CONDITION THAT THE GOVERNMENT WILL PAY TO SURETY, IN THE MANNER PROVIDED IN THE
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of the Interior |
| Office | PACIFIC NW REGION PN 6615 |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Y1JZ — CONSTRUCTION OF MISCELLANEOUS BUILDINGS |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $7.7M |
| Current contract value | $7.7M |
| Potential contract value / ceiling | $7.7M |
| Start date | Sep 13, 2022 |
| Current end date | Oct 31, 2025 |
| Potential end date | Sep 1, 2026 |
| Latest award activity | Jan 29, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 72 of 72 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jan 29, 2026 | P00068 | $198.8K | THE PURPOSE OF P00068 IS TO DEFINITIZE UNILATERAL MODIFICATION P00005. |
| Jan 29, 2026 | P00069 | $134.2K | THIS MODIFICATION WILL OBLIGATE $134,195.00 TO COMPLETE THIS DEFINITIZATION. |
| Jan 29, 2026 | P00070 | $118.7K | MODIFICATION P00070 IS TO DEFINITIZE UNILATERAL MODIFICATION P00015 FOR $118,722.00. |
| Jan 29, 2026 | P00071 | $98.3K | THE PURPOSE OF P00071 IS TO DEFINITIZE ALL REMAINING CONTRACT ACTIONS FOR $98,293.00 AND CLOSEOUT THE SURETY TAKEOVER AGREEMENT. |
| Aug 6, 2025 | P00067 | $0 | MOD P00067 IS A UNILATERAL DEFINITIZATION OF MODIFICATION R16PC00143 P00020. |
| Apr 15, 2025 | P00066 | $-55.0K | MOD P00066 IS A UNILATERAL MODIFICATION TO RESCIND/CANCEL UNILATERAL MODIFICATION P00022. |
| Mar 20, 2025 | P00065 | $10.5K | P00064 IS A BILATERAL MODIFICATION TO PROVIDE THE COMPLETION CONTRACTOR AN EQUITABLE ADJUSTMENT FOR C2 CUSTOM LIGHT FIXTURES. |
| Dec 26, 2024 | P00064 | $29.8K | P00064 IS A BILATERAL MODIFICATION TO PROVIDE THE COMPLETION CONTRACTOR AN EQUITABLE ADJUSTMENT IN RESPONSE TO RFIS 557 & 608, REVISIONS TO THE ELEVATOR, FIRE ALARM AND 4-FOLD DOOR CONTROLS. |
| Sep 17, 2024 | P00063 | $73.4K | P00063 IS A BILATERAL MODIFICATION TO PROVIDE AN EQUITABLE ADJUSTMENT FOR THE BOILER CONTROLS AND PROGRAMMING. |
| Sep 16, 2024 | P00062 | $14.6K | P00062 IS A BILATERAL MODIFICATION TO PROVIDE AN EQUITABLE ADJUSTMENT IN RESPONSE TO RFI 537 CARD READERS. |
| Sep 9, 2024 | P00061 | $-168 | MOD P00061 IS A BILATERAL MODIFICATION TO DEFINITIZE P00022. |
| Aug 27, 2024 | P00060 | $7.5K | MOD P00060 IS A BILATERAL MODIFICATION TO PROVIDE THE COMPLETION CONTRACTOR AN EQUITABLE ADJUSTMENT FOR RESPONSES TO MULTIPLE RFIS FOR STRUCTURAL STEEL CHANGES. |
| Aug 12, 2024 | P00059 | $27.3K | MOD P00059 IS A BILATERAL MODIFICATION TO PROVIDE THE COMPLETION CONTRACTOR AN EQUITABLE ADJUSTMENT FOR RFI 451 GUARD RAILS, RFI 618 DOOR 102 ACCESS CONTROL REVISIONS AND DE-SCOPING THE CMU SEALANT |
| Aug 6, 2024 | P00057 | $62.7K | P00057 IS A BILATERAL MODIFICATION FOR AN EQUITABLE ADJUSTMENT TO RFI 514, 570, 585, 591, ELEVATOR PIPING, EXHAUST INSPECTIONS. |
| Aug 6, 2024 | P00058 | $28.5K | MOD P00058 IS A BILATERAL MODIFICATION TO PROVIDE THE COMPLETION CONTRACTOR AN EQUITABLE ADJUSTMENT FOR THE ACCESS CONTROLS RELOCATION INTO THE SERVER ROOM, RFI 577 LIGHT FIXTURE CAN DEPTH AND RFI 595 SOUTH GUTTER AND DOWNSPOUT MISALIGNMENT. |
| Jul 29, 2024 | P00056 | $-3.9K | MOD P00056 IS A BILATERAL MODIFICATION TO DEFINITIZE P00039. |
| Jul 22, 2024 | P00054 | $3.6K | P00054 IS A BILATERAL MODIFICATION TO PROVIDE AN EQUITABLE ADJUSTMENT FOR THE ELECTRICAL WORK PERFORMED IN ROOM 136. |
| Jul 22, 2024 | P00055 | $-226.7K | MOD P00055 IS A BILATERAL MODIFICATION TO DEFINITIZE P00032, P00037 AND P00038. |
| Jul 15, 2024 | P00053 | $-51.3K | P00053 IS A BILATERAL MODIFICATION TO DEFINITIZE P00014, P00027 AND P00040. |
| Jul 10, 2024 | P00051 | $25.1K | MOD P00051 IS A BILATERAL MODIFICATION TO PROVIDE AN EQUITABLE ADJUSTMENT IN RESPONSE TO RFI 517 STRUCTURAL STEEL IN ROOM 103 |
| Jul 10, 2024 | P00052 | $7.4K | P00052 IS A BILATERAL MODIFICATION TO PROVIDE A REAS IN RESPONSE TO RFI 568 FRAMED METAL CORNER AND STAIRWELL POST REVISIONS. |
| Jul 3, 2024 | P00050 | $21.3K | P00050 IS A BILATERAL MODIFICATION TO PROVIDE AN EQUITABLE ADJUSTMENT IN RESPONSE TO RFI 616 AV CONTROLS |
| Jun 24, 2024 | P00049 | $11.2K | MOD P00049 IS A BILATERAL MODIFICATION TO DEFINITIZE P00024, P00025, P00026, P00028 AND P00029 |
| Jun 6, 2024 | P00047 | $4.1K | P00047 IS A BILATERAL MODIFICATION TO PROVIDE THE CONTRACTOR AN EQUITABLE ADJUST IN RESPONSE TO RFI 580. |
| Jun 6, 2024 | P00048 | $5.8K | P00046 IS A BILATERAL MODIFICATION TO PROVIDE THE CONTRACTOR AN EQUITABLE ADJUSTMENT FOR REVISIONS TO THE LADDER IN ROOM 215. |
| Jun 3, 2024 | P00044 | $-5.2K | P00044 IS A BILATERAL MODIFICATION TO DEFINITIZE P00016 AND P00021. |
| Jun 3, 2024 | P00045 | $18.5K | P00045 IS A BILATERAL MODIFICATION IN RESPONSE TO RFI 589 EXHAUST GRILLES AND RFI 590 EXHAUST GRILL. |
| Jun 3, 2024 | P00046 | $11.1K | P00046 IS A BILATERAL MODIFICATION TO PROVIDE THE CONTRACTOR A REA TO REMOBILIZE AND PERFORM AN ELEVATOR INSPECTION. |
| May 29, 2024 | P00043 | $5.0K | P00043 IS A BILATERAL MODIFICATION TO DEFINITIZE R16PC00143 ICD MOD 52 |
| May 8, 2024 | P00042 | $49.7K | P00042 IS A BILATERAL MODIFICATION TO PROVIDE AN EQUITABLE ADJUSTMENT FOR LED LIGHTS IN THE APP BAY. |
| May 7, 2024 | P00041 | $17.0K | P00041 IS A BILATERAL MODIFICATION TO PROVIDE AN EQUITABLE ADJUSTMENT FOR CDMS. |
| May 2, 2024 | P00040 | $25.0K | P00040 IS A UNILATERAL MODIFICATION TO PROVIDE A SOLUTION FOR THE NOISE AND PERFORMANCE ISSUES IDENTIFIED IN RFI 614. |
| May 1, 2024 | P00039 | $80.0K | P00039 IS A UNILATERAL MODIFICATION FOR ELECTRICAL ROOM AND PANEL REVISIONS IN ACCORDANCE WITH THE SOW. |
| Apr 23, 2024 | P00038 | $0 | P00038 IS A UNILATERAL MODIFICATION TO ADD STATEMENT OF WORK REVISION 03 DATED 04/16/2024. |
| Apr 15, 2024 | P00036 | $6.5K | THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE THE CONTRACTOR AN EQUITABLE ADJUSTMENT IN RESPONSE TO RFI 576 FRAMED METAL WINDOW IN ROOM 202. |
| Apr 15, 2024 | P00037 | $0 | P00037 IS A UNILATERAL MODIFICATION TO ADD STATEMENT OF WORK REVISION 02 DATED 04/12/2024. |
| Apr 11, 2024 | P00033 | $5.3K | THE PURPOSE OF THIS MODIFICATION IS TO TRIM EIGHT CAN LIGHTS IN ROOM 222 TO CONCEAL RAW METAL OF THE CAN LIGHT FIXTURES. |
| Apr 11, 2024 | P00034 | $4.1K | THE PURPOSE OF THIS MODIFICATION IS TO REVISE THE CARD READER AND PEDESTAL LOCATIONS IN RESPONSE TO RFI 583. |
| Apr 11, 2024 | P00035 | $27.2K | THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE THE CONTRACTOR AN EQUITABLE ADJUSTMENT TO REMOVE THE PRIMER FROM THE STAIRWELL AND APPLY A RUST PREVENTION BASECOAT (PENETROL). |
| Apr 8, 2024 | P00031 | $11.2K | P00031 IS A BILATERAL MODIFICATION TO INSTALL INSULATION IN RESPONSE TO RFI 579 AS RECOMMENDED BY THE GOVERNMENT. |
| Apr 8, 2024 | P00032 | $400.0K | THE PURPOSE OF THIS MODIFICATION IS TO ADD FRESH AIR INTAKES FOR EVAPORATIVE COOLING UNITS 1 AND 3. TO ADD SOFT STARTS TO MOTORS 1 AND 3 AND TO CORRECT EXTEND THE FRESH AIR INTAKE ON THE SOUTH SIDE EXTERIOR ROOF OF THE APP BAY. |
| Mar 27, 2024 | P00030 | $3.8K | P00030 IS A BILATERAL MODIFICATION TO CHANGE THE PLUMBING FIXTURES IN RESPONSE TO RFI 605 AS RECOMMENDED BY THE GOVERNMENT. |
| Mar 13, 2024 | P00027 | $5.0K | P00027 IS A UNILATERAL MODIFICATION TO INSTALL A FIRE RATED DOOR IN ROOM 220. |
| Mar 13, 2024 | P00028 | $14.8K | P00028 IS A UNILATERAL MODIFICATION IN RESPONSE TO RFI 599 LANDSCAPE STABILIZATION AND LIGHT BOLLARD |
| Mar 13, 2024 | P00029 | $31.7K | P00029 IS A UNILATERAL MODIFICATION TO REVISE THE ELECTRICAL PANELS TO SUPPORT THE VOLTAGE FOR VARIOUS APPLIANCES |
| Mar 12, 2024 | P00026 | $6.9K | P00026 IS A UNILATERAL MODIFICATION TO INSTALL OCCUPANCY SENSORS IN HALLWAY 214. |
| Mar 1, 2024 | P00025 | $-5.0K | MODIFICATION P00025 IS A UNILATERAL ACTION TO RESCIND P00024. |
| Feb 26, 2024 | P00024 | $5.0K | UNILATERAL MODIFICATION TO INCORPORATE LIGHT CHANGES IN HALLWAY 214. |
| Jan 9, 2024 | P00023 | $0 | BILATERAL MODIFICATION TO DEFINITIZE R16PC00143 P00014 & P00015 |
| Dec 7, 2023 | P00021 | $45.0K | MOD P00021 UNILATERAL MODIFICATION TO INCORPORATE CHANGES TO THE DESIGN AND INSTALLATION OF THE EXTERIOR BUILDING SIGN. |
| Dec 7, 2023 | P00022 | $25.0K | MOD P00022 IS A UNILATERAL MODIFICATION TO INCORPORATE ELECTRICAL DETAILS IN THE SERVER ROOM IN RESPONSE TO RFI 598. |
| Nov 30, 2023 | P00020 | $0 | MOD P00020 IS A BILATERAL MODIFICATION TO ADD AND DELETE TERRAZZO FLOORING. |
| Nov 15, 2023 | P00019 | $0 | P00019 IS A BILATERAL MODIFICATION TO INCORPORATE RFI 593 CEILING FAN RESPONSE AS PROPOSED BY THE SURETY AND ACCEPTED BY THE GOVERNMENT. |
| Oct 27, 2023 | P00018 | $0 | MOD P00018 IS A BILATERAL MODIFICATION FOR A CHANGE TO THE SLIDING GLASS DOOR. |
| Sep 22, 2023 | P00017 | $3.8K | P00017 IS A BILATERAL MODIFICATION TO DEFINITIZE P00008. |
| Sep 20, 2023 | P00015 | $0 | P00015 IS A UNILATERAL MODIFICATION TO CHANGE THE LANDSCAPE DESIGN. |
| Sep 20, 2023 | P00016 | $30.0K | P00016 IS A UNILATERAL MODIFICATION TO INCORPORATE CHANGES TO THE DESIGN AND INSTALLATION OF THE EXTERIOR BUILDING SIGN. |
| Sep 18, 2023 | P00014 | $50.0K | P00014 IS A UNILATERAL MODIFICATION IN RESPONSE TO ASK-31 AND GASK-5 ASSOCIATED WITH THE STAIR 118 STOREFRONT HEAD ENCLOSURE. |
| Sep 1, 2023 | P00013 | $4.6K | MODIFICATION P00013 IS FOR AN EQUITABLE ADJUSTMENT IN RESPONSE TO RFIS 508 & 571. |
| Aug 31, 2023 | P00012 | $8.0K | MODIFICATION P00012 IS A BILATERAL MODIFICATION TO DEFINITIZE P00006 DOORS IN ROOMS 216, 217 AND 218. |
| Aug 29, 2023 | P00011 | $77.7K | MODIFICATION P00011 IS A BILATERAL MODIFICATION TO DEFINITIZE P00001 CMU WALLS. |
| Aug 21, 2023 | P00010 | $8.0K | MODIFICATION P00010 IS A BILATERAL MODIFICATION TO DEFINITIZE P00002 RADON VENT. |
| Aug 14, 2023 | P00009 | $4.7K | MODIFICATION P00009 IS A BILATERAL MODIFICATION TO DEFINITIZE P00007 JOGGLE CLEAT. |
| Jan 20, 2023 | P00007 | $1.5K | THE PURPOSE OF THIS MODIFICATION IS TO ADD A 2X4 WOOD NAILER TO THE INSIDE OF THE BENT STEEL PLATE TO SUPPORT THE JOGGLE CLEAT. |
| Jan 20, 2023 | P00008 | $9.8K | PROVIDE ALL THE MATERIAL, LABOR AND EQUIPMENT AND OTHER INCIDENTALS TO CONSTRUCT A CMU WALL ABOVE WINDOW K IN ACCORDANCE WITH THE GOVERNMENT RESPONSE TO RFI 526. |
| Nov 16, 2022 | P00005 | $4.7K | THE PURPOSE OF THIS MODIFICATION IS TO ALLOW FOR A FINISHED WEATHER STEEL PANELING ROOF INSTALLATION IN LIEU OF UNFINISHED METAL ROOF PANELING TO GUARANTEE A 20-YEAR ROOF WARRANTY. IN ACCORDANCE WITH THE SPECIFICATIONS, THE CONTRACTOR SHALL PROVIDE |
| Nov 16, 2022 | P00006 | $20.9K | THE PURPOSE OF THIS MODIFICATION IS TO DEMO/INSTALL THE FRAMES, DOORS, AND HARDWARE IN ROOMS 216, 217 AND 218 WITH FRAMES AND DOORS SWINGING INTO THE ROOMS RATHER THAN INTO THE HALLWAY TO COMPLY WITH LIFE, HEALTH, AND SAFETY CODES. |
| Oct 31, 2022 | P00003 | $0 | THE PURPOSE OF THE MODIFICATION IS TO INCORPORATE RFI 156 RESPONSE AS PROPOSED BY THE SURETY. |
| Oct 31, 2022 | P00004 | $7.1K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE ADJUSTMENTS FOR ELECTRICAL EQUIPMENT AND COMPRESSOR PLACEMENT ASSOCIATED WITH ELECTRICAL ROOM # 135 IN RESPONSE TO RFI 504 (SUPERSEDES PREVIOUS RESPONSES TO RFIS 338, 347, 383, 401, 405 & 435). |
| Oct 20, 2022 | P00001 | $20.0K | MOD P00001 IS A IS A UNILATERAL MODIFICATION TO INCORPORATE THE ATTACHED RFI 501.1 AS PROPOSED BY THE SURETY. |
| Oct 20, 2022 | P00002 | $2.0K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE DETAILS FOR THE RADON VENT IN RESPONSE TO RFIS 38.1, 335 AND 355. |
| Sep 13, 2022 | 0 | $6.1M | SURETY TAKING OVER AND COMPLETING THE WORK REQUIRED BY CONTRACT R16PC00143, AS MODIFIED, IN ACCORDANCE WITH ALL THE TERMS AND CONDITIONS OF THE CONTRACT UPON THE EXPRESS CONDITION THAT THE GOVERNMENT WILL PAY TO SURETY, IN THE MANNER PROVIDED IN THE |
Research next steps
- Verify whether remaining options may extend performance beyond the current end date.
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.