Federal contract award

140R1023C0008

CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of the Interior
OfficePACIFIC NW REGION PN 6615
NAICS237990 — Other Heavy and Civil Engineering Construction
PSCY1PZ — CONSTRUCTION OF OTHER NON-BUILDING FACILITIES
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$57.9M
Current contract value$61.4M
Potential contract value / ceiling$61.4M
Start dateSep 13, 2023
Current end dateJun 1, 2027
Potential end dateJun 1, 2027
Latest award activitySep 2, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 54 of 54 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Sep 2, 2026P00054$15.0KCLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 228, GRAVITY DRAINAGE SYSTEM FLOOR DRAIN TRAPS UNILATERAL CHANGE ORDER
Sep 1, 2026P00053$1.7MCLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: DEFINITIZATION OF P00032 FLOW & DIVERSION CHANGES
Aug 4, 2026P00052$369.7KCLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: DEFINITIZE P00033 UNWATERING PLAN CHANGES AND DEMO REMOVAL OF TEMPORARY OUTFALL
Jun 12, 2026P00051$19.0KCLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI-229 LOUVERS
May 18, 2026P00050$0CLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: CONCRETE PEDESTAL REBAR CHANGES
Mar 27, 2026P00049$434.2KCLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: DEFINITIZATION OF P00009, P00010, P00015, AND P00028 TEMPORARY CONTAINMENT STRUCTURE
Mar 19, 2026P00048$10.0KCLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RIVERBED CHANGES
Feb 13, 2026P00046$0CLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 218 HI 9.8 PUMP SPEC CHANGE
Feb 13, 2026P00047$16.7KCLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 186 EQUIPMENT BOLLARDS
Dec 31, 2025P00045$2.7KCLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 206 FALSE WEIR DRAIN VALVE STEM GUIDE
Dec 30, 2025P00043$12.0KCLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: PIT TAG BLOCK OUTS
Dec 30, 2025P00044$3.6KCLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 198 FISH LOCK WALL REVISIONS
Dec 29, 2025P00042$31.0KCLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: STILLING BASIN CLEANING FOR REPAIR IDENTIFICATION
Dec 15, 2025P00041$667CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: DEFINITIZE P00018 DAVIT ARM SYSTEMS
Dec 8, 2025P00040$16.0KCLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: DEFINITIZE P00005 ADDITIONAL DEWATERING AND OBSERVATION WELLS
Sep 18, 2025P00039$9.8MCLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: FY 25 SWEPT INCREMENTAL FUNDING
Sep 12, 2025P00038$11.1KCLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 163 FLIPPER GATE AIR CYLINDER
Sep 11, 2025P00037$110.2KCLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFP 0001 PIT TAG CONDUIT AND JUNCTION BOXES
Aug 18, 2025P00036$23.1KCLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 147 INTAKE SCREENS SLIDE GATES CONTROLS
Aug 13, 2025P00035$0CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: LIFT PARTIAL SUSPENSION OF WORK AND INCORPORATES REVISED ENVIRONMENTAL PERMITS FOR THE CLE ELUM DAM FISH PASSAGE
Jul 17, 2025P00034$0CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 158 TRENCH DRAIN CORRECTIONS
Jun 10, 2025P00033$336.7KCLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: UNWATERING PLAN CHANGES AND DEMO/REMOVAL OF TEMPORARY OUTFALL CHANGE ORDER.
Jun 7, 2025P00032$610.0KCLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 165 & 166 DIVERSION AND CARE OF FLOWS DURING CONSTRUCTION AND TEMPORARY OUTLET WORKS DIVERSION
May 19, 2025P00031$3.6KCLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 159 SECURITY CAMERAS
May 9, 2025P00030$18.2KCLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: CLSM PIPE TRENCH CHANGE ORDER
May 7, 2025P00029$0CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFIS 130 AND 131 SPLITTER WALL CHANGES
May 2, 2025P00027$6.9KCLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 66 PHONE AND BOOSTER
May 2, 2025P00028$3.9MCLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: ADDITIONAL FUNDING FOR TEMPORARY CONTAINMENT STRUCTURE
Apr 25, 2025P00025$0CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: PERIOD OF PERFORMANCE EXTENSION
Apr 25, 2025P00026$7.9KCLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 111 OIL WATER SEPARATOR SLAB
Apr 11, 2025P00024$0CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFIS 64 EPOXY REBAR ANCHORS
Mar 13, 2025P00022$0CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 148 CJP WELD DELETE
Mar 13, 2025P00023$68.4KCLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFIS 96 FISH SCREENS GUARDRAIL CLASH
Mar 5, 2025P00018$2.9KCLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 98 DAVIT ARMS SYSTEMS UNILATERAL CHANGE ORDER
Mar 5, 2025P00019$0CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 115 HVAC FANS, NO COST UNILATERAL CHANGE ORDER
Mar 5, 2025P00020$21.6KCLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 35 SIGNAGE AND PANEL DRAWINGS UNILATERAL CHANGE ORDER
Mar 5, 2025P00021$21.0KCLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFIS 72, 76, 110, 112, 114, 127, AND 146, MISC. MECHANICAL PUMPS, UNILATERAL CHANGE ORDER
Feb 11, 2025P00017$0CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 100 UNIT SKYLIGHTS NO COST UNILATERAL CHANGE ORDER
Feb 5, 2025P00016$0CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: P00016 COMMUNICATION CABLING, TELEPHONE, SECURITY, AND SURVEILLANCE SYSTEM
Dec 3, 2024P00015$5.1MCLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: P00010 SUPPLEMENTAL FUNDING CHANGE ORDER
Sep 20, 2024P00013$45.0KCLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: MOTOR CONTROL CENTER (MCC) UNILATERAL CHANGE ORDER
Sep 18, 2024P00012$4.3MCLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: INCREMENTAL FUNDING END OF YEAR FY2024
Sep 12, 2024P00011$0CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: CHANGE ORDER, VERTICAL ATTRACTION PUMPS, TRENCH SUMP VERTICAL PUMPING UNITS
Sep 10, 2024P00010$2.9MCLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: TEMPORARY CONTAINMENT STRUCTURE WORK PLAN #2
Aug 27, 2024P00008$0CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: WEIR BLAD MATERIAL CHANGE NO-COST BILATERAL CHANGE ORDER
Aug 27, 2024P00009$5.0MCLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: TEMPORARY CONTAINMENT STRUCTURE WORK PLAN
Jun 27, 2024P00007$0CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: LAND USE AND SAFETY QUALIFICATIONS BILATERAL CHANGE ORDER
Apr 19, 2024P00006$0CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: STOREFRONT WINDOWS BILATERAL CHANGE ORDER
Mar 14, 2024P00005$879.8KCLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: ADDITIONAL DEWATERING WELLS CHANGE ORDER
Mar 7, 2024P00004$932.4KCLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 2 AND 3 SLIDE GATE AND SCREEN ACTUATORS CHANGE ORDER.
Oct 26, 2023P00003$4.8KCLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: PARTNERING SESSION MOD
Oct 17, 2023P00002$0CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: PERIOD OF PERFORMANCE AND TABLE OF CONTENTS REVISION
Sep 19, 2023P00001$2.5MCLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: INCREMENTAL FUNDING ONLY
Sep 13, 20230$18.6MCLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON

Estimated positioning window

Nov 1, 2026 – Jan 30, 2027

Recompete signal:
80/100

Why this recompete signal

Contract timing and recorded acquisition signals at the time of calculation.

Stored score: 80/100. Available recorded signals: 75 points.

Contract end 2027-06-01 (212 days from calculation)
+35 points
9 historical awards in this buyer and category group
+15 points
54 recorded award transactions
+10 points
Latest award action: 2026-09-02
+5 points
Parent award identifier recorded
+0 points
Solicitation identifier recorded
+10 points
Linked official forecast
+0 points
Calculated on
2026-11-01 10:17:53.997580+00:00

The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.

Rule-based research score; it does not measure your chance of winning.

This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.

USAspending award record

. Rule-based research score; positioning dates are estimates.

Recompete score calculated Nov 1, 2026.

Buyer contacts from matching notices

Matched on exact award/solicitation identifier and awarding agency. Source dates describe the notice, not current contact verification.

ContactRolePublished contact methodsEvidenceSource date
Fleming, LanceContactlfleming@usbr.gov
2083785338
SourceJun 8, 2023
Fleming, LanceContactlfleming@usbr.gov
2083785338
SourceJun 6, 2023
Fleming, LanceContactlfleming@usbr.gov
2083785338
SourceJun 5, 2023
Fleming, LanceContactlfleming@usbr.gov
2083785338
SourceMay 19, 2023
Fleming, LanceContactlfleming@usbr.gov
2083785338
SourceMay 10, 2023
Fleming, LanceContactlfleming@usbr.gov
2083785338
SourceMay 4, 2023
Fleming, LanceContactlfleming@usbr.gov
2083785338
SourceApr 25, 2023
Fleming, LanceContactlfleming@usbr.gov
2083785338
SourceMar 20, 2023
Fleming, LanceContactlfleming@usbr.gov
2083785338
SourceDec 16, 2022

Research next steps

  1. Check the linked forecast or SAM for a confirmed solicitation and current timing.
  2. Check the stated set-aside against the solicitation and current certifications.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.