Federal contract award
140R4024C0004
RIVER OUTLET WORKS PIPE RELINING AT GLEN CANYON POWER PLANT
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of the Interior |
| Office | UPPER COLORADO REGIONAL OFFICE |
| NAICS | 238320 — Painting and Wall Covering Contractors |
| PSC | Y1MD — CONSTRUCTION OF EPG FACILITIES - HYDRO |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $7.5M |
| Current contract value | $7.5M |
| Potential contract value / ceiling | $7.5M |
| Start date | Apr 8, 2024 |
| Current end date | Oct 5, 2025 |
| Potential end date | Oct 5, 2025 |
| Latest award activity | Oct 29, 2025 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Oct 29, 2025 | P00006 | $-150.0K | RIVER OUTLET WORKS PIPE RELINING AT GLEN CANYON POWER PLANT. THE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE EXCESS FUNDS AND CLOSE THE CONTRACT |
| May 2, 2025 | P00005 | $0 | RIVER OUTLET WORKS PIPE RELINING AT GLEN CANYON POWER PLANT. THE PURPOSE OF THIS ADMINISTRATIVE MODIFICATION IS TO CORRECT CLIN DATES. |
| Apr 17, 2025 | P00004 | $2.0M | RIVER OUTLET WORKS PIPE RELINING AT GLEN CANYON POWER PLANT. THE PURPOSE OF THIS MODIFICATION IS TO EXERCISE THE 3RD OPTION FOR OUTLET PIPE 4. |
| Feb 26, 2025 | P00003 | $1.9M | RIVER OUTLET WORKS PIPE RELINING AT GLEN CANYON POWER PLANT. THE PURPOSE OF THIS MODIFICATION IS TO EXERCISE THE 2ND OPTION FOR OUTLET PIPE 3. |
Buyer contacts from matching notices
Matched on exact award/solicitation identifier and awarding agency. Source dates describe the notice, not current contact verification.
| Contact | Role | Published contact methods | Evidence | Source date |
|---|---|---|---|---|
| Hilton, Lisa | Contact | LHilton@usbr.gov 801-524-3808 | Source | Sep 27, 2023 |
| Hilton, Lisa | Contact | LHilton@usbr.gov 801-524-3808 | Source | Sep 20, 2023 |
| Hilton, Lisa | Contact | LHilton@usbr.gov 801-524-3808 | Source | Aug 31, 2023 |
| Hilton, Lisa | Contact | LHilton@usbr.gov 801-524-3808 | Source | Aug 10, 2023 |
| Hilton, Lisa | Contact | LHilton@usbr.gov 801-524-3808 | Source | Jun 21, 2023 |
| Hilton, Lisa | Contact | LHilton@usbr.gov 801-524-3808 | Source | Jun 16, 2023 |
| Hilton, Lisa | Contact | LHilton@usbr.gov 801-524-3808 | Source | Apr 28, 2023 |
| Handy, Jennifer | Contact | JHandy@usbr.gov 435-885-3228 | Source | Nov 21, 2022 |
| Handy, Jennifer | Contact | JHandy@usbr.gov 435-885-3228 | Source | Nov 21, 2022 |
| Handy, Jennifer | Contact | JHandy@usbr.gov 435-885-3228 | Source | Nov 21, 2022 |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.