Federal contract award
140R4024F0076
THE PURPOSE OF THIS PROJECT IS TO UPDATE THE OUTLET WORKS AT HYRUM DAM, APPROXIMATELY 10 MILES SOUTH OF LOGAN, UTAH IN CACHE COUNTY. THE PRINCIPLE COMPONENTS OF THE WORK ARE AS FOLLOWS: REMOVE THE EXISTING 24-INCH OUTLET WORKS PIPE, REMOVE THE CONCRE
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of the Interior |
| Office | UPPER COLORADO REGIONAL OFFICE |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Z2KA — REPAIR OR ALTERATION OF DAMS |
| Parent award / vehicle | 140F0822D0057 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $2.7M |
| Current contract value | $2.7M |
| Potential contract value / ceiling | $2.7M |
| Start date | Sep 20, 2024 |
| Current end date | May 31, 2025 |
| Potential end date | May 31, 2025 |
| Latest award activity | May 8, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 6 of 6 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 8, 2026 | P00005 | $54.1K | HYRUM DAM UPPER OUTLET WORKS IMPROVEMENT PROJECT |
| Apr 1, 2026 | P00004 | $-138.3K | HYRUM DAM UPPER OUTLET WORKS IMPROVEMENT PROJECT |
| Mar 9, 2026 | P00003 | $7.7K | HYRUM DAM UPPER OUTLET WORKS IMPROVEMENT PROJECT |
| Feb 23, 2026 | P00002 | $18.7K | THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE FUNDING FOR THE LEAD SPECIALIST AND THE UPDATED REMOVAL METHODOLOGY DUE TO UNFORESEEN LEAD CONCENTRATIONS IN THE PIPE. |
| Dec 6, 2024 | P00001 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO FORMALLY RESPOND TO THE CONTRACTOR'S NOTICE OF CONCERN DATED 11/21/2024, CHANGE ORDER REQUEST 001 DATED 11/22/2024, AND FOLLOW-UP TO RFI 009. |
| Sep 20, 2024 | 0 | $2.7M | THE PURPOSE OF THIS PROJECT IS TO UPDATE THE OUTLET WORKS AT HYRUM DAM, APPROXIMATELY 10 MILES SOUTH OF LOGAN, UTAH IN CACHE COUNTY. THE PRINCIPLE COMPONENTS OF THE WORK ARE AS FOLLOWS: REMOVE THE EXISTING 24-INCH OUTLET WORKS PIPE, REMOVE THE CONCRE |
Research next steps
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.