Federal contract award

140R6020C0015

WEBSTER DAM SPILLWAY CHUTE REPLACEMENT, WEBSTER UNIT, SOLOMON UNIT DIVISION, PICK-SLOAN MISSOURI BASIN PROGRAM, KANSAS

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of the Interior
OfficeGREAT PLAINS REGIONAL OFFICE
NAICS237990 — Other Heavy and Civil Engineering Construction
PSCZ2PA — REPAIR OR ALTERATION OF RECREATION FACILITIES (NON-BUILDING)
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$26.6M
Current contract value$26.6M
Potential contract value / ceiling$26.6M
Start dateOct 1, 2020
Current end dateJun 23, 2024
Potential end dateJun 23, 2024
Latest award activityMay 7, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 26 of 26 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
May 7, 2026P00025$-901.5KWEBSTER DAM SPILLWAY CHUTE REPLACEMENT, WEBSTER UNIT, SOLOMON DIVISION, PICK-SLOAN MISSOURI BASIN PROGRAM, KANSAS
May 29, 2024P00024$408.4KWEBSTER DAM SPILLWAY CHUTE REPLACEMENT, WEBSTER UNIT, SOLOMON DIVISION, PICK-SLOAN MISSOURI BASIN PROGRAM, KANSAS
May 28, 2024P00023$150.0KWEBSTER DAM SPILLWAY CHUTE REPLACEMENT, WEBSTER UNIT, SOLOMON DIVISION, PICK-SLOAN MISSOURI BASIN PROGRAM, KANSAS
Mar 21, 2024P00022$1.9MWEBSTER DAM SPILLWAY CHUTE REPLACEMENT, WEBSTER UNIT, SOLOMON DIVISION, PICK-SLOAN MISSOURI BASIN PROGRAM, KANSAS
Nov 7, 2023P00021$0WEBSTER DAM SPILLWAY CHUTE REPLACEMENT, WEBSTER UNIT, SOLOMON DIVISION, PICK-SLOAN MISSOURI BASIN PROGRAM, KANSAS
Jun 28, 2023P00020$650.0KWEBSTER DAM SPILLWAY CHUTE REPLACEMENT, WEBSTER UNIT, SOLOMON DIVISION, PICK-SLOAN MISSOURI BASIN PROGRAM, KANSAS
Apr 6, 2023P00019$0WEBSTER DAM SPILLWAY CHUTE REPLACEMENT, WEBSTER UNIT, SOLOMON DIVISION, PICK-SLOAN MISSOURI BASIN PROGRAM, KANSAS
Nov 4, 2022P00017$0THIS MODIFICATION INCORPORATES CHANGES TO SPECIFICATION SECTION 03 30 00 - CAST-IN-PLACE CONCRETE
Nov 4, 2022P00018$0THIS MODIFICATION INCORPORATES REVISIONS TO SPECIFICATION SECTION 01 14 12 - WORK RESTRICTIONS AND LIMITATIONS
Sep 16, 2022P00016$420.0KTHIS MODIFICATION OBLIGATES ADDITIONAL FUNDING TO COVER WORK UNDER UNILATERAL MODIFICATION NO. P00013
Aug 7, 2022P00015$0THIS MODIFICATION DIRECTS THE CONTRACTOR TO INSTALL A 2-INCH HDPE PIPE FOR THE CONTROLLING THE GROUNDWATER SEEP AT STATION 15+48 AS ADDRESSED IN SL 13 - NTE $15,000
Jul 26, 2022P00014$0THIS MODIFICATION DIRECTS THE CONTRACTOR TO INSTALL A CONCRETE COLLAR IN LIEU OF COUPLING, AS ADDRESSED IN THEIR RFI 26
Jun 8, 2022P00013$120.0KTHIS MODIFICATION DIRECTS THE CONTRACTOR ON HOW TO ADDRESS THE SHALE FOUNDATION
Apr 28, 2022P00012$0THIS MODIFICATION INCORPORATES REVISIONS TO SPECIFICATION SECTION NO 03 20 30 GROUTED ANCHOR BARS, IN RESPONSE TO RFI 019 LETTER, DATED JANUARY 21, 2022.
Apr 5, 2022P00009$838.8KTHIS MODIFICATION PROVIDES AN EQUITABLE ADJUSTMENT FOR CHANGING THE SOURCE FOR AGGREGATES, AS ADDRESSED ON THE CO LETTER DATED JULY 19, 2021
Apr 5, 2022P00010$0THIS MODIFICATION INCORPORATES THE FOLLOWING REVISED SPECIFICATION INTO AND MADE A PART OF THE CONTRACT: 03 30 00 - CAST-IN-PLACE CONCRETE REV 9-16-2021
Apr 5, 2022P00011$0THIS MODIFICATION INCORPORATES REVISIONS TO SPECIFICATION SECTION NO. 52 00 00 - DRAWINGS AND DRAWINGS 486-D-60004 AND 486-D-60006 IN RESPONSE TO YOUR RFI 017 LETTER, DATED NOVEMBER 3, 2021.
Mar 20, 2022P00008$812.4KTHIS MODIFICATION PROVIDES AN EQUITABLE ADJUSTMENT FOR ALL WORK ASSOCIATED WITH THE PERIMETER REPAIRS, AS ADDRESSED ON THE CO LETTER DATED JULY 1, 2021
Feb 10, 2022P00007$0THIS MODIFICATION INCORPORATES REVISIONS TO SPECIFICATION SECTION 01 14 12, SECTION 32 92 20, AND SECTION F
Jun 24, 2021P00004$0THIS MODIFICATION INCORPORATES CHANGES TO SPECIFICATION SECTION 03 30 00 - CAST-IN-PLACE CONCRETE
Jun 24, 2021P00005$0THIS MODIFICATION INCORPORATES CHANGES TO SPECIFICATION SECTION 31 23 02 - COMPACTING EARTH MATERIALS
Jun 24, 2021P00006$34.2KTHIS MODIFICATION PROVIDES AN EQUITABLE ADJUSTMENT TO THE CONTRACTOR FOR ALL WORK ASSOCIATED WITH REALIGNING THE ACCESS ROAD, AS DISCUSSED IN THE CONTRACTING OFFICER'S LETTER DATED APRIL 26, 2021
Apr 25, 2021P00003$5.2MTHIS MODIFICATION OBLIGATES ADDITIONAL FUNDING IN ACCORDANCE WITH WBR 1452.232-80 LIMITATION OF FUNDS
Mar 21, 2021P00002$0THIS MODIFICATION INCORPORATES REVISIONS TO SHEET NO. 4., DRAWING NO. 468-D-60029
Feb 4, 2021P00001$0THIS MODIFICATION EXTENDS THE REQUIRED COMPLETION DATE BY 58 DAYS AS A RESULT OF THE SUSPENSION OF WORK.
Sep 16, 20200$17.0MWEBSTER DAM SPILLWAY CHUTE REPLACEMENT, WEBSTER UNIT, SOLOMON UNIT DIVISION, PICK-SLOAN MISSOURI BASIN PROGRAM, KANSAS

Buyer contacts from matching notices

Matched on exact award/solicitation identifier and awarding agency. Source dates describe the notice, not current contact verification.

ContactRolePublished contact methodsEvidenceSource date
Gallagher, StormyContactSGallagher@usbr.govSourceJul 28, 2020
Gallagher, StormyContactSGallagher@usbr.govSourceJul 28, 2020
Gallagher, StormyContactSGallagher@usbr.govSourceJul 24, 2020
Gallagher, StormyContactSGallagher@usbr.govSourceJul 23, 2020
Gallagher, StormyContactSGallagher@usbr.govSourceJul 20, 2020
Gallagher, StormyContactSGallagher@usbr.govSourceJul 13, 2020
Gallagher, StormyContactSGallagher@usbr.govSourceJul 2, 2020
Gallagher, StormyContactSGallagher@usbr.govSourceJun 16, 2020
Gallagher, StormyContactSGallagher@usbr.govSourceJun 12, 2020
Gallagher, StormyContactSGallagher@usbr.govSourceApr 10, 2020

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.