Federal contract award
140R6021C0002
MARYS LAKE RUNNER REPLACEMENT AND TURBINE OVERHAUL
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of the Interior |
| Office | GREAT PLAINS REGIONAL OFFICE |
| NAICS | 237990 — Other Heavy and Civil Engineering Construction |
| PSC | Z2MD — REPAIR OR ALTERATION OF EPG FACILITIES - HYDRO |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $6.1M |
| Current contract value | $6.1M |
| Potential contract value / ceiling | $6.1M |
| Start date | Mar 24, 2021 |
| Current end date | Oct 25, 2024 |
| Potential end date | Oct 25, 2024 |
| Latest award activity | May 19, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 27 of 27 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 19, 2026 | P00026 | $-8.3K | DEOBLIGATE EXCESS FUNDING FROM LINE 00040 BASED ON VARIATION OF ESTIMATED QUANTITIES. |
| Mar 26, 2026 | P00025 | $0 | THIS MODIFICATION EXTENDS THE PERIOD OF PERFORMANCE BASED ON A TIME IMPACT ANALYSIS AND CONSIDERATION. |
| Aug 21, 2025 | P00024 | $-160.7K | DEOBLIGATION FOR CONNECTING ROD AND COATING REPAIR FOR STATOR AND ROTOR DESCOPE |
| Jun 5, 2025 | P00023 | $-12.1K | DEFINITIZE CHANGE ORDER FOR GENERATOR SHAFT SPOT FACING |
| Sep 18, 2024 | P00022 | $87.0K | THRUST BEARING REFURBISHMENT - NEW THRUST RUNNER, NEW THRUST COLLAR, REFURBISH SPLIT KEYS AND BASE RING |
| May 6, 2024 | P00021 | $96.4K | SPARE THRUST BEARING - REBABBIT |
| Apr 15, 2024 | P00020 | $140.0K | THRUST BEARING ADDITIONAL WORK |
| Apr 10, 2024 | P00019 | $-4.7K | SPARE TURBINE GUIDE BEARING, DEFINITIZE OPERATING RING CHANGE ORDER, AND EXTEND THE POP. |
| Feb 13, 2024 | P00018 | $80.0K | CHANGE ORDER - GATE SHAFT ROCKER ARM |
| Sep 22, 2023 | P00017 | $100.0K | DISASSEMBLY - SPOT FACING AND HONE COUPLING BORES |
| Sep 21, 2023 | P00016 | $37.0K | SUPPLEMENTAL AGREEMENT FOR ADDITIONAL THRUST BEARING STATIONARY SEGMENTS IAW SPECIFICATION 48 13 17, REVISED 21SEP2023 |
| Aug 31, 2023 | P00015 | $43.1K | SUPPLEMENTAL AGREEMENT FOR MACHINING BOTTOM RING, OPERATING RING, HEADCOVER, TURBINE SHAFT, PACKING BOX, TURBINE GUIDE BEARING, JACKS AND BRAKES ASSEMBLIES |
| Aug 9, 2023 | P00014 | $1.3M | CHANGE ORDER FOR OPERATING RING SPECIFICATION 48 13 29 AND ADD INCREMENTAL FUNDING. |
| Aug 7, 2023 | P00013 | $70.2K | THIS MODIFICATION CHANGES THE QUANTITIES, UNIT PRICES AND TOTAL PRICES OF CLINS 1-2 & 1-3, COATING REPAIR OF SCROLL CASE AND DRAFT TUBE, PLUS CHANGES THE CONTRACTING OFFICER. |
| Feb 2, 2023 | P00012 | $0 | THIS MODIFICATION INCORPORATES THE WAGE RATE AND FRINGE FOR MILLWRIGHT HOURLY RATE $37.10 AND FRINGE 16.62 |
| Jan 19, 2023 | P00011 | $0 | THIS MODIFICATION CHANGES THE CO FROM GERRI VOTO-BRAUN TO STORMY GALLAGHER |
| Dec 1, 2022 | P00010 | $0 | : THIS MODIFICATION INCORPORATES THE FOLLOWING REVISED SPECIFICATION SECTIONS INTO AND A PART OF THE CONTRACT: SECTION 48 13 03 - PRE-TEARDOWN READINGS AND MEASUREMENTS SECTION 48 13 09 - CRITICAL CONNECTION FASTENERS SECTION 52 00 00 - DR |
| May 31, 2022 | P00009 | $1.3M | THIS MODIFICATION OBLIGATES ADDITIONAL FUNDING IN ACCORDANCE WITH PARAGRAPH I.37 LIMITATION OF FUNDING |
| May 30, 2022 | P00007 | $59.1K | THIS MODIFICATION EXERCISES OPTIONAL PRICE SCHEDULE CLINS 1-A2. 1A-3, 1A-5 AND 1A-6 |
| May 30, 2022 | P00008 | $0 | THIS MODIFICATION INCORPORATES REVISIONS TO VARIOUS SPECIFICATION SECTIONS |
| May 18, 2022 | P00006 | $0 | THIS MODIFICATION INCORPORATES CORRECTIONS TO SECTION B AND SECTION I |
| Dec 13, 2021 | P00005 | $0 | MARYS LAKE RUNNER REPLACEMENT |
| Dec 2, 2021 | P00004 | $0 | THIS MODIFICATION INCORPORATES REVISIONS TO SPECIFICATIONS SECTION 01 31 20 - CONSTRUCTION PROGRAM |
| Jul 22, 2021 | P00003 | $0 | THIS MODIFICATION INCORPORATES REVISIONS TO SECTION F AND SECTION I |
| Mar 27, 2021 | P00001 | $0 | MODIFICATION NO. P00001 INCORPORATES PORTIONS OF AMERICAN HYDRO'S PROPOSAL INTO AND A PART OF THE CONTRACT |
| Mar 27, 2021 | P00002 | $0 | MODIFICATION NO. P00002 CORRECTS THE AWARD AMOUNT IN PRISM |
| Mar 12, 2021 | 0 | $3.0M | MARYS LAKE RUNNER REPLACEMENT AND TURBINE OVERHAUL |
Buyer contacts from matching notices
Matched on exact award/solicitation identifier and awarding agency. Source dates describe the notice, not current contact verification.
| Contact | Role | Published contact methods | Evidence | Source date |
|---|---|---|---|---|
| Melnick, Linda | Contact | LMelnick@usbr.gov | Source | Jul 9, 2020 |
| Melnick, Linda | Contact | LMelnick@usbr.gov | Source | Jun 26, 2020 |
| Melnick, Linda | Contact | LMelnick@usbr.gov | Source | Jun 23, 2020 |
| Melnick, Linda | Contact | LMelnick@usbr.gov | Source | Jun 4, 2020 |
| Melnick, Linda | Contact | LMelnick@usbr.gov | Source | Apr 21, 2020 |
| Melnick, Linda | Contact | LMelnick@usbr.gov | Source | Mar 31, 2020 |
| Melnick, Linda | Contact | LMelnick@usbr.gov | Source | Feb 18, 2020 |
| Voto-Braun, Gerri | Contact | GVotoBraun@usbr.gov | Source | Dec 27, 2019 |