Federal contract award

140R6024F0006

THE PURPOSE OF THIS TASK ORDER IS TO TO REPAIR SECTIONS OF THE CUNNINGHAM TUNNEL INVERT LINING.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of the Interior
OfficeGREAT PLAINS REGIONAL OFFICE
NAICS236220 — Commercial and Institutional Building Construction
PSCZ2LC — REPAIR OR ALTERATION OF TUNNELS AND SUBSURFACE STRUCTURES
Parent award / vehicle140A1623D0026
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$3.1M
Current contract value$3.1M
Potential contract value / ceiling$3.1M
Start dateJan 18, 2024
Current end dateOct 15, 2025
Potential end dateDec 30, 2025
Latest award activityDec 3, 2025
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 7 of 7 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Dec 3, 2025P00006$-114.9KTHE PURPOSE OF THIS MODIFICATION IS TO FINALIZE COST/PRICE FOR MATERIAL USAGE DURING THE PROJECT.
Oct 30, 2025P00005$0THE PURPOSE OF THIS MODIFICATION IS TO AUTHORIZE IN-SCOPE REPAIRS TO STATION 220+00 AND 237+50.
Apr 9, 2025P00004$1.0MTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING FOR THE REMAINDER OF THE CONSTRUCTION PROJECT.
Sep 19, 2024P00003$0THE PURPOSE OF THIS CHANGE ORDER IS TO DEFINE REQUIREMENTS WITHIN SCOUR 2 OF THE PROJECT.
Aug 14, 2024P00002$0THE PURPOSE OF THIS MODIFICATION IS TO CHANGE SPEC SECTION 31 23 16 - TUNNEL MATERIAL REMOVAL.
Jul 25, 2024P00001$0THE PURPOSE OF THIS MODIFICATION IS TO CHANGE CO AND CHANGE SPEC SECTION 03 30 00.
Jan 18, 20240$2.2MTHE PURPOSE OF THIS TASK ORDER IS TO TO REPAIR SECTIONS OF THE CUNNINGHAM TUNNEL INVERT LINING.

Buyer contacts from matching notices

Matched on exact award/solicitation identifier and awarding agency. Source dates describe the notice, not current contact verification.

ContactRolePublished contact methodsEvidenceSource date
Stone, StevenContactsstone@usbr.gov
0000000000
SourceMar 29, 2023

Research next steps

  1. Verify whether remaining options may extend performance beyond the current end date.
  2. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.