Federal contract award

15BFA025C00000013

REPAIR SEWER LINE AT FCI SEAGOVILLE- 25Z5AD3

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Justice
OfficeFAO
NAICS237110 — Water and Sewer Line and Related Structures Construction
PSCZ2FF — REPAIR OR ALTERATION OF PENAL FACILITIES
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$1.1M
Current contract value$1.1M
Potential contract value / ceiling$1.1M
Start dateFeb 19, 2025
Current end dateNov 30, 2025
Potential end dateNov 30, 2025
Latest award activityJan 22, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jan 22, 2026P00003$0REPAIR SEWER LINE AT FCI SEAGOVILLE- 25Z5AD3 30-DAY NO-COST TIME EXTENSION FOR DIRT REMOVAL AND FINAL CLOSEOUT FOR PROJECT COMPLETION
Aug 1, 2025P00002$514.6KREPAIR SEWER LINE AT FCI SEAGOVILLE- 25Z5AD3 MOD 2- ADDITIONAL 306 LF OF SEWER PIPING
Jun 20, 2025P00001$61.7KREPAIR SEWER LINE AT FCI SEAGOVILLE- 25Z5AD3 INCREASE FOR ADDITIONAL REMOVAL AND PERIOD OF PERFORMANCE- $61,690.76
Feb 12, 20250$536.7KREPAIR SEWER LINE AT FCI SEAGOVILLE- 25Z5AD3

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.