Federal contract award

19BK8025P0380

SWITCHGEAR SEQUENCE OF OPERATIONS CHANGE/GENERATOR CONTROLLER-ANNUNCIATOR REPLACEMENT.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of State
OfficeU.S. EMBASSY SARAJEVO
NAICS238210 — Electrical Contractors and Other Wiring Installation Contractors
PSCN061 — Installation of Equipment: Electric Wire, and Power and Distribution Equipment
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$74.7K
Current contract value$74.7K
Potential contract value / ceiling$74.7K
Start dateSep 5, 2025
Current end dateSep 7, 2025
Potential end dateDec 31, 2025
Latest award activitySep 5, 2025
Source loadedAug 15, 2026

Funding and modification history

Showing the latest 1 of 1 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Sep 5, 20250$74.7KSWITCHGEAR SEQUENCE OF OPERATIONS CHANGE/GENERATOR CONTROLLER-ANNUNCIATOR REPLACEMENT.

Research next steps

  1. Verify whether remaining options may extend performance beyond the current end date.
  2. Check the stated set-aside against the solicitation and current certifications.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.