Federal contract award

2031JG23F00303

TASK ORDER: 2031JG18D00005/2031JG23F00303-CHILLER REPLACEMENT-UNITED STATES MINT-PHILADELPHIA

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of the Treasury
OfficeUS MINT HEADQUARTERS
NAICS236210 — Industrial Building Construction
PSCZ2EC — REPAIR OR ALTERATION OF PRODUCTION BUILDINGS
Parent award / vehicle2031JG18D00005
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$5.8M
Current contract value$5.8M
Potential contract value / ceiling$5.8M
Start dateAug 18, 2023
Current end dateSep 27, 2026
Potential end dateSep 27, 2026
Latest award activityOct 16, 2025
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 6 of 6 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Oct 16, 2025P00009$99.4KRELOCATION OF THE COOLING TOWERS SKID, FURNISH TWO COOLING TOWER ISOLATION VALVES, INSTALLATION OF HEAT TRACE CONTROLLERS REQUIRED FOR SYSTEM INTEGRATION AND INSTALLATION OF CHEMICAL TREATMENT PIPING.
Sep 5, 2025P00008$18.6KTHIS MODIFICATION IS TO 1) EXTEND THE POP END DATE TO 27 SEP 2026, AND 2) INCORPORATE CHANGE ORDER PROPOSAL FROM LORENZON TO FURNISH AND INSTALL COOLING TOWER NOZZLES.
May 2, 2025P00007$51.0KTHIS MODIFICATION IS TO INCORPORATE CHANGE ORDER PROPOSAL FROM LORENZON IN FOR LOTO PLACARDS, REPLACEMENT OF EXISTING CHILLED WATER VALVES, AND REPAIR OF 1ST FLOOR CRACKED DRAIN REPAIR.
Mar 18, 2025P00005$-4.2KTHIS MODIFICATION IS TO INCORPORATE CHANGE ORDER PROPOSAL DATED 29 AUGUST 2024 CORRECTING THE PREVIOUS CHANGE ORDER AND ISSUING A CREDIT TO THE MINT.
Feb 24, 2025P00006$258.3KTHIS MODIFICATION IS TO INCORPORATE CHANGE ORDER PROPOSAL #5 IN RESPONSE TO REVISIONS TO MECH, ELECTRICAL, AND STRUCTURAL-PROCESSED PCHW SKID RELOCATIONS- SCHP-3&4 ELECTRICAL WORK.
Oct 21, 2024P00004$0THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE END DATE TO 27 SEPTEMBER 2025 TO ALLOW FOR WORK TO BE COMPLETED.