Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Veterans Affairs
OfficeOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)
NAICS237990 — Other Heavy and Civil Engineering Construction
PSCY1PC — CONSTRUCTION OF UNIMPROVED REAL PROPERTY (LAND)
Parent award / vehicleNot reported
Set-asideSERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Pricing typeFIRM FIXED PRICE
Obligations$31.4M
Current contract value$62.0M
Potential contract value / ceiling$62.0M
Start dateOct 19, 2020
Current end dateAug 4, 2026
Potential end dateAug 4, 2026
Latest award activityAug 4, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 62 of 62 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Aug 4, 2026P00046$-6.4KFINAL CONTRACT BOND ADJUSTMENT
Apr 6, 2026P00045$-330.2KCONSTRUCTION PROJECT DE-SCOPE
Mar 26, 2025P00044$125.0KPROVIDE STOCK PILE AND ROAD REPAIR
Feb 27, 2025P00043$60.4KSERVICE PROVIDER SUPPLY ISSUES
Sep 30, 2024A00063$5.3KDESIGN ERROR
Sep 30, 2024A00064$5.1KSERVICE PROVIDER SUPPLY ISSUES
Aug 9, 2024A00062$43.4KRESOLVE EXISTING CONDITION.
Jul 19, 2024A00058$0LIFE SAFETY
Jul 19, 2024A00059$0CONTRACTOR REQUESTED CHANGE.
Jul 19, 2024A00060$-3.9KCAPTURE CREDITS FROM DESIGN/FIELD CHANGES
Jul 19, 2024A00061$0WEATHER DELAY MOD - NO COST
May 21, 2024A00057$0DESIGN ERRROR
May 7, 2024A00056$0WEATHER DELAY MOD - NO COST
May 1, 2024A00055$0CLIENT REQUEST AND CAPTURE CREDIT
Apr 22, 2024A00050$0DESIGN OMISSION
Apr 22, 2024A00051$0DESIGN ERROR/OMISSION
Apr 22, 2024A00052$0DIFFERING SITE CONDITION - INVESTIGATION FOR RESOLUTION
Apr 22, 2024A00053$0INTERNAL CHANGE TO REDUCE CLIENT MAINTENANCE
Apr 22, 2024A00054$0WEATHER DELAY MOD - NO COST
Mar 4, 2024A00043$0WEATHER DELAY MOD - NO COST
Mar 4, 2024A00044$2.8KCLIENT REQUEST
Mar 4, 2024A00045$4.6KUNFORESEEN CONDITION.
Mar 4, 2024A00046$9.2KDIFFERING SITE CONDITION
Mar 4, 2024A00047$0DESIGN OMISSION
Mar 4, 2024A00049$0WEATHER DELAY MOD - NO COST
Feb 21, 2024P00041$272.5KADMINISTRATIVE: CHANGE OF CONTRACTING OFFICER
Feb 6, 2024A00048$3.8KFUNDING CORRECTION
Jan 26, 2024A00040$39.9KDESIGN OMISSION.
Jan 25, 2024A00033$24.7KDIFFERING SITE CONDITION
Jan 25, 2024A00034$3.7KDESIGN OMISSION
Jan 25, 2024A00035$0REQUESTED CHANGE BY CONTRACTOR.
Jan 25, 2024A00036$0CLIENT CHANGE REQUEST/DESIGN ERROR.
Jan 25, 2024A00037$0WEATHER DAY TIME EXTENSION
Jan 25, 2024A00038$2.6KCLIENT REQUEST.
Jan 25, 2024A00039$213.3KDESIGN OMISSION
Sep 7, 2023A00026$45.5KDESIGN ERROR/OMISSION FOR THE AREA DRAINS AROUND THE NEW ADMINISTRATION BUILDING AND THE DOMESTIC WATER LINE.
Sep 7, 2023A00027$4.2KFIELD ADJUSTMENT TO ALLOW FOR MORE ACCESSIBILITY FOR FUTURE MAINTENANCE FROM THE CLIENT.
Sep 7, 2023A00028$8.5KDESIGN ERROR WITH NEW MAINTENANCE BUILDING LOCKER ROOM WINDOWS, SHOWER STALL REDESIGN AND CEMENT BACKER BOARD DEMOLITION.
Sep 7, 2023A00029$8.3KDESIGN OMISSION OF ATTIC STOCK FOR ALL FINISHES WITHIN THE BASE CONTRACT.
Sep 7, 2023A00030$0DESIGN ERROR. CORRECTS ADA ACCESSIBILITY FOR MEN'S SHOWER STALL IN LOCKER ROOM.
Sep 7, 2023A00031$-50.2KTHIS MODIFICATION ADJUSTS THE DMARC ROUTING TO MITIGATE ANY NETWORK DOWNTIME THAT WOULD DISRUPT NCA OPERATIONS.
Sep 7, 2023A00032$0UNFORESEEN SITE CONDITION.
Aug 24, 2023A00025$73.9KADD A CONCRETE SLAB TO THE SOIL STORAGE BUILDING AND A SIDEWALK ADJOINING THE NEW NE PARKING LOT WITH THE EXISTING, IN ORDER TO PROVIDE SAFE EGRESS TO THE CLIENT.
Aug 22, 2023A00021$0WEATHER DELAY MODIFICATION TO INCORPORATE 20 NON COMPENSABLE CALENDAR DAYS OF TIME EXTENSION TO THE BASE CONTRACT.
Aug 22, 2023A00022$0WEATHER DELAY MODIFICATION TO INCORPORATE 2 NON COMPENSABLE CALENDAR DAYS OF TIME EXTENSION TO THE BASE CONTRACT.
Aug 22, 2023A00023$5.0KBUDGET FOR REO INSPECTION TOOLS IN ORDER TO SUCCESSFULLY CARRY OUT DUTIES AND RESPONSIBILITIES.
Aug 22, 2023A00024$1.3KADDITIONAL KEY CYLINDERS FOR EXISTING FACILITIES TO TIE INTO THE NEW KEY SCHEDULE PROVIDED WITHIN THIS CONTRACT.
Jul 6, 2023P00020$0ADMINISTRATIVE: CHANGE OF ADMINISTRATIVE CONTRACTING OFFICER
May 22, 2023A00019$2.1KREQUIRED BY NCA FOR CONTRACT PHASING.
Apr 25, 2023A00018$9.8KMODIFICATION ADDRESSES DESIGN OMISSION OF THE PAINT FINISH FOR THE WOOD AWNING AROUND THE NEW ADMINISTRATION BUILDING. WILL NOW MATCH EXISTING FACILITIES.
Apr 18, 2023A00017$-2.9KMODIFICATION CAPTURES THE CREDIT FOR A FIELD ADJUSTMENT ON THE SIZE OF THE NEW NE PARKING LOT AS A RESULT OF A DESIGN ERROR (CIVIL VS PLANTING PLAN).
Mar 3, 2023A00016$22.3KMODIFICATION ADDRESSES A DESIGN ERROR AND OMISSION. SEGMENT OF THE SECONDARY CONDUITS FROM THE PAD MOUNTED TRANSFORMER WERE TO REMAIN HOWEVER DID NOT HAVE THE CAPACITY FOR THE NEW CONDUCTORS TO BE INSTALLED.
Nov 9, 2022P00010$0ADMINISTRATIVE: CHANGE OF CONTRACTING OFFICER
Sep 13, 2022A00008$129.0KUNFORESEEN SITE CONDITIONS - NCA TRAILERS (IN CONTRACT) WERE IN A DETERIORATED STATE. THIS CHANGE COVERS LEASING COSTS FOR FOR NEW TRAILERS FOR CONTRACT PHASING.
Jul 15, 2022A00007$32.2KDESIGN ERROR, ADDED WORK
Jul 7, 2022A00005$13.7KDUE TO UNFORESEEN CONDITION, SLEEVING OF DRILLED PIERS WAS NEEDED AS THERE WAS WATER INTRUSION, EFFECTING CONCRETE POUR.
Jan 6, 2022P00006$3.0KUNFORESEEN SITE CONDITIONS - ELECTRICAL CONDUIT DEFICIENCIES
Aug 23, 2021P00004$0CHANGE IN CO ADMINISTRATION
Dec 21, 2020P00003$0CHANGE IN CO ADMINISTRATION
Dec 7, 2020A00001$0RELOCATION OF RE OFFICE AT NO COST NO TIME DUE TO ISSUE OF CONTRACT LOCATION, CHANGED TO NEW LOCATION
Sep 30, 2020P00001$0DALLAS FORT WORTH NATIONAL CEMETERY, PHASE 5, DESIGN-BID-BUILD ADMINISTRATIVE MODIFICATION REFLECTING CORRECT PROJECT ADDRESS
Sep 28, 20200$30.6MDALLAS FORT WORTH NATIONAL CEMETERY, PHASE 5, DESIGN-BID-BUILD

Buyer contacts from matching notices

Matched on exact award/solicitation identifier and awarding agency. Source dates describe the notice, not current contact verification.

ContactRolePublished contact methodsEvidenceSource date
Crystal D. ColeContactCrystal.Cole2@va.govSourceJul 24, 2020
Crystal D. ColeContactCrystal.Cole2@va.govSourceJul 22, 2020
Crystal D. ColeContactCrystal.Cole2@va.govSourceJul 17, 2020
Crystal D. ColeContactCrystal.Cole2@va.govSourceJul 17, 2020
Crystal D. ColeContactCrystal.Cole2@va.govSourceJul 16, 2020
Crystal D. ColeContactCrystal.Cole2@va.govSourceJul 15, 2020
Crystal D. ColeContactCrystal.Cole2@va.govSourceJul 13, 2020
Crystal D. ColeContactCrystal.Cole2@va.govSourceJul 9, 2020
Crystal D. ColeContactCrystal.Cole2@va.govSourceApr 2, 2020

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.