| Field | Reported value |
|---|---|
| Agency | Department of Veterans Affairs |
| Office | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) |
| NAICS | 237990 — Other Heavy and Civil Engineering Construction |
| PSC | Y1PC — CONSTRUCTION OF UNIMPROVED REAL PROPERTY (LAND) |
| Parent award / vehicle | Not reported |
| Set-aside | SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $34.3M |
| Current contract value | $34.3M |
| Potential contract value / ceiling | $34.3M |
| Start date | Jun 15, 2021 |
| Current end date | Apr 8, 2026 |
| Potential end date | Apr 8, 2026 |
| Latest award activity | Apr 8, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 32 of 32 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Apr 8, 2026 | P00032 | $72.1K | P00032 IS TO INCORPORATE THE FOLLOWING ADMINISTRATIVE, SUPPLEMENTAL, AND CHANGE ORDER ACTIONS AUTHORIZED BY THE CONTRACTING OFFICER. |
| Jan 29, 2025 | P00031 | $0 | P00031 CLARIFICATION FOR P00030 |
| Jan 24, 2025 | P00030 | $8.3K | P00030 RFI 395 AND 404R1 |
| Jan 6, 2025 | P00026 | $90.4K | P00026 FINALIZE REA FOR CORTEGE LANE |
| Dec 30, 2024 | P00028 | $-2.8K | P00025 DESCOPE OF MODIFICATION P00028 DEOBLIGATION TO CORRECT FUNDING |
| Dec 30, 2024 | P00029 | $2.8K | P00029 - RE-OBLIGATION OF FUNDS TO CORRECT FUNDING |
| Dec 11, 2024 | P00023 | $4.1K | P00023 WINDOW LINTEL - CHANGE ORDER |
| Dec 11, 2024 | P00025 | $-66.2K | P00025 DESCOPE OF MODIFICATION P00021 US SPACE FORCE EMBLEM |
| Nov 26, 2024 | P00024 | $2.8K | P00024 - EXPANSION JOINTS |
| Sep 26, 2024 | P00022 | $2.9K | P00022 BULK STORAGE BEAM PAINTING |
| Jul 9, 2024 | P00021 | $66.2K | P00021 EMBLEMS |
| May 14, 2024 | P00020 | $5.9K | P00020 PIC RESTROOM ROOF REPLACEMENT - DEFINITIZE P00019 |
| Apr 29, 2024 | P00019 | $10.8K | P00019 PIC RESTROOM ROOF REPLACEMENT |
| Jan 2, 2024 | P00018 | $47.4K | P00018 REPAIR AND CONNECT EXISTING IRRIGATION TO NEW IRRIGATION. |
| Sep 20, 2023 | P00017 | $12.5K | EXISTING LIGHTNING PROTECTION NEEDS TO BE REMOVED PRIOR TO ROOF INSTALLATION, THEN REINSTALLED. |
| Jun 2, 2023 | P00016 | $0 | ADMINISTRATIVE MODIFICATION TO CHANGE PO# DUE TO IFAMS SYSTEM CHANGEOVER |
| May 10, 2023 | P00015 | $-439 | MODIFICATION P00015 REMOVE TERRAFLEX, REPLACE WITH ARCGIS SURVEY 123. |
| Feb 13, 2023 | P00014 | $135.9K | MODIFICATION P00014 NEW IGC FIELD - WEATHER CONTINGENCY |
| Jan 23, 2023 | P00013 | $427.0K | MODIFICATION P00013 NEW IGC FIELD - ACCELERATED DEPLETION RATE |
| Dec 20, 2022 | P00011 | $587.5K | MODIFICATION P00011 SETTLEMENT OF REA FOR GENERAL CONDITIONS UNDER MOD P00007. |
| Nov 18, 2022 | P00012 | $349.5K | PHASE 2 EXPANSION OF THE GREAT LAKES NATIONAL CEMETERY, CO-A00010, REPAIR CRACKS IN COLUMBARIUM STRUCTURE (ASI-11) |
| Oct 19, 2022 | A00010 | $1.0K | PHASE 2 EXPANSION OF THE GREAT LAKES NATIONAL CEMETERY, CO-A00010, REPAIR CRACKS IN COLUMBARIUM STRUCTURE (ASI-11) |
| Jun 13, 2022 | A00009 | $40.0K | PHASE 2 EXPANSION OF THE GREAT LAKES NATIONAL CEMETERY, CO-A00009, REPAIR GLNC ROADS |
| May 6, 2022 | P00007 | $1.3M | PHASE 2 EXPANSION OF THE GREAT LAKES NATIONAL CEMETERY, SA-A00004, REMOVAL OF UNDOCUMENTED FILL IN SECTIONS 19 PER RFI 035 |
| May 6, 2022 | P00008 | $0 | PHASE 2 EXPANSION OF THE GREAT LAKES NATIONAL CEMETERY, SA-A00004, REMOVAL OF UNDOCUMENTED FILL IN SECTIONS 19 PER RFI 035 |
| Feb 7, 2022 | P00006 | $0 | PHASE 2 EXPANSION OF THE GREAT LAKES NATIONAL CEMETERY, SA-A00004, REMOVAL OF UNDOCUMENTED FILL IN SECTIONS 19 PER RFI 035 |
| Feb 3, 2022 | P00005 | $0 | PHASE 2 EXPANSION OF THE GREAT LAKES NATIONAL CEMETERY, SA-A00004, REMOVAL OF UNDOCUMENTED FILL IN SECTIONS 19 PER RFI 035 |
| Jan 10, 2022 | A00004 | $210.8K | PHASE 2 EXPANSION OF THE GREAT LAKES NATIONAL CEMETERY, SA-A00004, REMOVAL OF UNDOCUMENTED FILL IN SECTIONS 19 PER RFI 035 |
| Nov 22, 2021 | A00002 | $29.5K | PHASE 2 EXPANSION OF THE GREAT LAKES NATIONAL CEMETERY, SA-A00002, REMOVE AND RELOCATE EXISTING 8 INCH IRRIGATION MAIN AND ASSOCIATED CONTROL WIRES |
| Nov 22, 2021 | A00003 | $2.3K | PHASE 2 EXPANSION OF THE GREAT LAKES NATIONAL CEMETERY, SA-A0003, INCREASE CONCRETE PSI FROM 4000PSI TO 5000PSI PER RFI-013 |
| Sep 22, 2021 | A00001 | $133.5K | PHASE 2 EXPANSION OF THE GREAT LAKES NATIONAL CEMETERY, SA-A00001, INSTALL ADDITIONAL DRAINAGE FOR EXISTING BURIAL SECTION 17 |
| May 12, 2021 | 0 | $30.8M | PHASE 2 EXPANSION OF THE GREAT LAKES NATIONAL CEMETERY |
Buyer contacts from matching notices
Matched on exact award/solicitation identifier and awarding agency. Source dates describe the notice, not current contact verification.
| Contact | Role | Published contact methods | Evidence | Source date |
|---|---|---|---|---|
| Jeffrey C Gerbensky | Contracting Officer | jeffrey.gerbensky@va.gov 224-610-7311 | Source | Jan 4, 2021 |
| Jeffrey C Gerbensky | Contracting Officer | jeffrey.gerbensky@va.gov 224-610-7311 | Source | Dec 21, 2020 |
| Jeffrey C Gerbensky | Contracting Officer | jeffrey.gerbensky@va.gov 224-610-7311 | Source | Dec 3, 2020 |
| Jeffrey C Gerbensky | Contracting Officer | jeffrey.gerbensky@va.gov 224-610-7311 | Source | Dec 1, 2020 |
| Jeffrey C Gerbensky | Contracting Officer | jeffrey.gerbensky@va.gov 224-610-7311 | Source | Nov 30, 2020 |
| Jeffrey C Gerbensky | Contracting Officer | jeffrey.gerbensky@va.gov 224-610-7311 | Source | Nov 20, 2020 |
| Jeffrey C Gerbensky | Contracting Officer | jeffrey.gerbensky@va.gov 224-610-7311 | Source | Oct 8, 2020 |
| Jeffrey C Gerbensky | Contract Specialist | Jeffrey.Gerbensky@va.gov 224-610-7330 | Source | Aug 7, 2020 |