Federal contract award
36C10F23C0007
CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Veterans Affairs |
| Office | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Y1DA — CONSTRUCTION OF HOSPITALS AND INFIRMARIES |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $215.2M |
| Current contract value | $215.2M |
| Potential contract value / ceiling | $215.2M |
| Start date | Sep 22, 2023 |
| Current end date | Mar 25, 2027 |
| Potential end date | Mar 25, 2027 |
| Latest award activity | Sep 4, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 200 of 265 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Sep 4, 2026 | P00267 | $447.8K | PCI 970225 RFI 0871 RESIDENT BEDROOM HEADWALL DESIGN CLARIFICATIONS |
| Aug 31, 2026 | P00262 | $110.2K | DEFINITIZE P00249 PCI 970258 PATIENT LIFT RAILS DEFINITIZE |
| Aug 31, 2026 | P00263 | $23.7K | PCI 970251 CONNECTIONS FOR NPW AND TANK BYPASS |
| Aug 31, 2026 | P00264 | $65.2K | PAYMENT FOR MATERIALS STORED OFFSITE FABULOUS FLOORS |
| Aug 31, 2026 | P00266 | $12.9K | PCI 970236 RFI 0944 IN WALL MILLWORK SUPPORT STEEL |
| Aug 25, 2026 | P00258 | $18.3K | PCI 970239 RFI 0954 B1 AND L1 TV NICHE CHANGES |
| Aug 25, 2026 | P00259 | $19.4K | PCI 970252 RFI 0966 ADDED SUPPORT AT WINDOW 07 |
| Aug 25, 2026 | P00260 | $110.4K | PCI 970144 RFI-0642 AND 0645 SIGNAGE UPDATES |
| Aug 25, 2026 | P00261 | $355.0K | CHANGE ORDER PCI 970219R1 IN RELATION TO CHANGE ORDER P00199 EDGE OF SLAB CONFLICTS LTSCI VA DALLAS 549 820B |
| Aug 18, 2026 | P00256 | $0 | EXECUTIVE MILLWORK PAYMENT FOR MATERIALS STORED OFFSITE |
| Aug 18, 2026 | P00257 | $0 | PAYMENT FOR MATERIALS STORED OFFSITE FABULOUS FLOORS |
| Aug 14, 2026 | P00254 | $9.6K | PCI 970253 RFI 0982 AREA A AND F ROOF MATERIAL TRANSITION |
| Aug 12, 2026 | P00255 | $-14.4K | PCI 970249 RFI 0938 REMOVE FIRE RATING OPENING 2A002 |
| Aug 11, 2026 | P00250 | $34.4K | PCI 970234 RFI 0828 ADDED FRAMING AT MAIN ENTRY CANOPY |
| Aug 11, 2026 | P00251 | $33.7K | PCI 970206 RFI 0927 PATIO FINISH CONFIRMATION |
| Aug 11, 2026 | P00252 | $18.4K | PCI 970254 RFI 0978 BRIDGE ROOF DRAIN PIPING |
| Aug 11, 2026 | P00253 | $27.7K | PCI 970238 ELEVATOR AUXILIARY POWER OPERATION PANEL |
| Aug 10, 2026 | P00248 | $6.8K | PCI 970227 RFI 0729 D0 D1 AND E ZVB CONFLICTS |
| Aug 5, 2026 | P00246 | $32.4K | DOOR FRAMES AT L1 POD BALCONIES |
| Aug 5, 2026 | P00249 | $368.0K | CHANGE ORDER PATIENT LIFT RAILING CEILING COORDINATION |
| Aug 3, 2026 | P00247 | $7.3K | DUCT IN ELEVATOR MACHINE ROOMS |
| Jul 30, 2026 | P00245 | $46.2K | PCI 970185 RFI-0825 L1 AND L2 LOUVER SUPPORT STEEL |
| Jul 28, 2026 | P00202 | $40.0K | PCI 970223 RFI 0918 AND 0971 BAA COMPLIANCE AND WALL FINISHES |
| Jul 21, 2026 | P00241 | $60.0K | PCI 970194 RFI 0861 CHANGES AT GLAZING |
| Jul 21, 2026 | P00243 | $0 | EXECUTIVE MILLWORK APPROVAL OF PAYMENT FOR MATERIALS STORED OFF SITE |
| Jul 20, 2026 | P00239 | $35.5K | PCI 970229 PARAPET COPING CLARIFICATIONS |
| Jul 20, 2026 | P00244 | $0 | APPROVED PAYMENT STORED MATERIALS FABULOUS FLOORS |
| Jul 17, 2026 | P00242 | $-19.1K | DEFINITIZE CHANGE ORDER P00188 REMOVE EMERGENCY CALL BOXES |
| Jul 16, 2026 | P00240 | $9.6K | FHV CABINET CLEARANCE |
| Jul 15, 2026 | P00235 | $-5.0K | PCI 970197 CREDIT CEILING FINISHES |
| Jul 10, 2026 | P00232 | $10.0K | PCI 970224 RFI 0859 SLAB EDGE DISCREPANCIES |
| Jul 10, 2026 | P00234 | $27.4K | PLUMBING CHANGES |
| Jul 10, 2026 | P00236 | $4.0K | RFI-0926 FRAMED JAMBS AT B1F004 FIRE SHUTTER |
| Jul 10, 2026 | P00237 | $42.1K | RFI 0845 WINDOWS 22 35 36 37 STEEL CONFLICT |
| Jun 30, 2026 | P00238 | $0 | PAYMENT FOR MATERIALS STORED OFFSITE TEXAS INDUSTRIAL GLASS |
| Jun 29, 2026 | P00228 | $176.5K | PCI 970132 - INTEGRATED DOOR ASSEMBLY CONFIRMATIONS |
| Jun 29, 2026 | P00229 | $34.6K | PCI 970222 ST5 LIMESTONE CLARIFICATION |
| Jun 29, 2026 | P00230 | $15.4K | PCI 970216 - PRECAST ADJUSTMENTS AT ROOFING |
| Jun 29, 2026 | P00231 | $16.7K | PCI 970228 RFI HEAT TRACE AND CIRCUITRY CHANGES |
| Jun 29, 2026 | P00233 | $54.7K | PCI 970193 MONUMENT SIGN CLARIFICATION |
| Jun 12, 2026 | P00227 | $8.7K | PCI 970208 RFI0908 POD NURSE STATION SINK DISCREPANCIES |
| Jun 11, 2026 | P00226 | $27.9K | PCI 970135 LEVEL 1 SLEEVES IN CONFLICT WITH JOISTS |
| Jun 10, 2026 | P00224 | $0 | APPROVAL OF PAYMENT FOR MATERIALS STORED OFFSITE EXECUTIVE MILLWORK |
| Jun 10, 2026 | P00225 | $15.1K | AREA F INSULATION AND PARAPET CONFLICTS |
| Jun 5, 2026 | P00216 | $5.7K | PCI 970220 LEVEL 2 ELECTRICAL CLARIFICATIONS |
| Jun 5, 2026 | P00217 | $7.8K | PCI 970195 ADDED FRAMING BUILDUP AT VESTIBULE |
| Jun 5, 2026 | P00218 | $36.9K | PCI 970200 MILLWORK IN PUBLIC ELEVATOR LOBBIES |
| Jun 5, 2026 | P00219 | $7.0K | PCI 970213 WIDENED EXPANSION JOINT AT GL 1 |
| Jun 4, 2026 | P00220 | $10.5K | PCI 970215 ADDED BELLOWS AT POD AND SPINE EXPANSION JOINTS |
| Jun 4, 2026 | P00221 | $47.2K | PCI 970226 MOTORIZED SHELVING CLARIFICATIONS |
| Jun 4, 2026 | P00222 | $113.2K | PCI 970068 ASI02 DOOR HARDWARE CHANGES |
| Jun 4, 2026 | P00223 | $27.1K | URC 004 GLASS RAILING HEIGHT INCREASE |
| Jun 2, 2026 | P00213 | $11.4K | ADDED FLASHING AT WINDOW 20 |
| Jun 2, 2026 | P00215 | $77.2K | LPR RISER DISCREPANCIES |
| May 28, 2026 | P00211 | $0 | DEFINITIZE P00065 AND P00112 TIE FORCE REBAR |
| May 28, 2026 | P00212 | $19.9K | LOUVER DISCREPANCIES |
| May 28, 2026 | P00214 | $-26.1K | CREDITS FOR PCI 970142 AND PCI 970186 TOILET PARTITIONS AND AUTO BOTTOMS |
| May 15, 2026 | P00204 | $0 | PAYMENT FOR MATERIALS STORED OFFSITE EXECUTIVE MILLWORK |
| May 15, 2026 | P00205 | $12.0K | CURTAINWALL 21 HEAD CONFLICT |
| May 15, 2026 | P00206 | $88.4K | LT UNIT POD BUSINESS CENTER COUNTERTOP |
| May 15, 2026 | P00207 | $2.9K | T7 SHELVING AT HAC ROOMS |
| May 15, 2026 | P00208 | $12.4K | DOOR JAMBS AT PRECAST RFI 0792 |
| May 15, 2026 | P00209 | $29.7K | ROTATING WORK SURFACE AT EXAM ROOM FOOTWALL |
| May 15, 2026 | P00210 | $0 | PAYMENT FOR MATERIALS STORED OFFSITE HUBZONE DOORS INC |
| May 12, 2026 | P00200 | $3.8K | RESOLVE FIRE ALARM DEVICE CONFLICTS PER RFI 0846 AND RFI 0911 RESPONSES |
| May 11, 2026 | P00198 | $46.7K | CHANGE ORDER CURTAINWALL 05 EOS CONFLICT RFI 899.1 |
| May 11, 2026 | P00199 | $76.4K | EDGE OF SLAB CHANGES RFI 902 |
| May 6, 2026 | P00201 | $89.7K | FIRE SMOKE DAMPER CHANGES PCI 970202 |
| Apr 30, 2026 | P00196 | $0 | PAYMENT FOR MATERIALS STORED OFFSITE CROWN CORR |
| Apr 30, 2026 | P00197 | $0 | REMOVE RESIDUAL BALANCE FROM CONTRACTORS SYSTEM OF RECORD FOR THE TOTAL CONTRACT VALUE IN WHOLE DOLLARS |
| Apr 24, 2026 | P00194 | $2.0K | DEFINITIZE P00186 POWER FOR WINDOW SHADES |
| Apr 24, 2026 | P00195 | $0 | PAYMENT FOR MATERIALS STORED OFFSITE FLOORING |
| Apr 21, 2026 | P00190 | $38.6K | STUCCO FACADE |
| Apr 21, 2026 | P00191 | $26.1K | POD ROOF DRAINS AND FRAMING DETAIL |
| Apr 17, 2026 | P00192 | $22.8K | POD NURSE STATION DEVICE CONFLICTS |
| Apr 16, 2026 | P00193 | $5.8K | ADDITIONAL CAULKING AT CURTAIN WALL |
| Apr 9, 2026 | P00187 | $3.9K | RELOCATE DOME CAMERA |
| Apr 9, 2026 | P00189 | $89.7K | PROVIDE MISSING STORM TIE INS FOR ROOF DRAINS |
| Apr 8, 2026 | P00188 | $0 | CHANGE ORDER DESCOPE EMERGENCY CALL BOXES |
| Apr 6, 2026 | P00186 | $11.3K | CHANGE ORDRE POWER FOR WINDOW SHADES |
| Apr 2, 2026 | P00185 | $-9.6K | CYSTO ROOM CREDIT DEFINITIZES P00100 AND P00119 |
| Mar 27, 2026 | P00184 | $0 | PAYMENT FOR MATERIALS STORED OFFSITE EXECUTIVE MILLWORK |
| Mar 24, 2026 | P00182 | $3.3K | DUCT AND DOOR FRAME CONFLICT |
| Mar 24, 2026 | P00183 | $15.9K | WINDOW FILM TYPE A |
| Mar 19, 2026 | P00179 | $15.1K | ZVB LOCATIONS AND MED GAS RISER |
| Mar 19, 2026 | P00180 | $269.9K | EXTENT OF KICKERS AND EXPANSION ANCHORS |
| Mar 19, 2026 | P00181 | $45.3K | SIEMENS CONTROL PANEL POWER |
| Mar 16, 2026 | P00176 | $14.8K | FAN COIL CHANGES AND ASSOCIATED REWORK |
| Mar 16, 2026 | P00177 | $4.4K | DATA DEVICE QUANTITY IN FOOTWALLS |
| Mar 16, 2026 | P00178 | $8.6K | MEDICATION 1B032 UNDER CABINET LIGHTING |
| Mar 5, 2026 | P00174 | $26.2K | FURRING CHANGES PER MULTIPLE RFI |
| Mar 5, 2026 | P00175 | $19.8K | VOID AT PENTHOUSE PARAPET WALL ROOF DECK |
| Mar 2, 2026 | P00170 | $24.8K | CONCRETE DOWELING CHANGES |
| Mar 2, 2026 | P00171 | $49.2K | MANHOLE 9A TESTING |
| Mar 2, 2026 | P00172 | $39.1K | DEFLECTION JOINT AT METAL PANELS |
| Mar 2, 2026 | P00173 | $0 | PAYMENT FOR MATERIALS STORED OFF SITE TEXAS INDUSTRIAL GLASS |
| Feb 13, 2026 | P00168 | $-47.4K | PCI 970134 FIRE AND SMOKE CURTAINS CREDIT |
| Feb 13, 2026 | P00169 | $12.0K | PCI 970162 RFI 0760 DISCONTINUED COUNTERTOP |
| Feb 5, 2026 | P00166 | $11.6K | PCI 970154 RFI 0782 SLAB EDGE FRAMING DISCREPANCIES |
| Feb 5, 2026 | P00167 | $39.2K | PCI 970121 - RFI-0656 - STEEL DETAILS CONFIRMATION |
| Feb 4, 2026 | P00164 | $20.8K | ADDED KICKERS PER RFI 0654 RESPONSE |
| Feb 4, 2026 | P00165 | $73.1K | CIRCUIT BREAKER AMPERAGE DISCREPANCIES |
| Jan 30, 2026 | P00159 | $23.8K | STAIRS CLARIFICATION AT BLDG 74 LOADING DOCK |
| Jan 30, 2026 | P00160 | $44.2K | PATIENT LIFTS CONFLICT WITH SHOWER CURTAIN RODS |
| Jan 30, 2026 | P00161 | $23.2K | ICE MACHINE AND COFFEE WATER SUPPLY BOXES |
| Jan 30, 2026 | P00162 | $18.4K | STEEL ANGLE AT CURTAIN WALL COPING INTERFACE |
| Jan 30, 2026 | P00163 | $0 | APPROVE PAYMENT FOR MATERIALS STORED OFF SITE |
| Jan 28, 2026 | P00153 | $3.5K | ADDED EXPANSION JOINT N AREA F LEVEL I |
| Jan 28, 2026 | P00154 | $34.6K | ELECTRICAL RFIS FOR CIRCUITRY AND DEVICE LOCATIONS |
| Jan 28, 2026 | P00155 | $9.2K | Y4 FIXTURE CHANGES |
| Jan 28, 2026 | P00156 | $7.2K | PUSH PLATES AT ELECTRICAL DOORS |
| Jan 28, 2026 | P00157 | $8.6K | CAULKING SUBSTRATE AT WINDOW OPENINGS |
| Jan 28, 2026 | P00158 | $13.8K | ADDED FRAMED WALL AT LOADING DOCK CEILING |
| Jan 21, 2026 | P00148 | $-17.8K | DEFINITIZE P00120 FIRE DAMPERS FOR A CREDIT |
| Jan 21, 2026 | P00149 | $9.0K | ELEVATOR DESIGN REVISIONS |
| Jan 21, 2026 | P00150 | $55.2K | LEVEL 3 EQUIPMENT CIRCUITS FOR DAMPERS |
| Jan 21, 2026 | P00151 | $71.7K | DRAINAGE AT STUCCO |
| Jan 21, 2026 | P00152 | $13.5K | FIRE EXTINGUISHER CABINET CLARIFICATION |
| Dec 30, 2025 | P00147 | $11.7K | FLOORING CHANGES PER SHOP DRAWINGS |
| Dec 27, 2025 | P00146 | $-414.0K | DEFINITIZES P00098 AND P00115 URC 002 IT CHANGES |
| Dec 19, 2025 | P00140 | $77.0K | NOURISHMENT KITCHEN CEILING SUPPORT |
| Dec 19, 2025 | P00141 | $4.0K | GRADING PLANS AND CONCRETE CHANGES |
| Dec 19, 2025 | P00142 | $10.9K | EXTERIOR WALL LAYOUT |
| Dec 19, 2025 | P00143 | $3.2K | ADDED AIR BARRIER AT CMP BASE |
| Dec 19, 2025 | P00144 | $30.5K | ADDITIONAL ERECTION TIME FOR REDUCED PRECAST PANEL SIZING |
| Dec 19, 2025 | P00145 | $2.9K | SUNSHADE EMBEDS AT PRECAST JOINTS |
| Dec 11, 2025 | P00139 | $0 | PAYMENT FOR MATERIALS STORED OFFSITE |
| Dec 5, 2025 | P00135 | $15.1K | ADDED SOMD REINFORCING AT PODS |
| Dec 5, 2025 | P00136 | $29.7K | DISCONTINUED FLOOR AND TILE PRODUCTS |
| Dec 5, 2025 | P00137 | $24.2K | MILLWORK CHANGES |
| Dec 5, 2025 | P00138 | $67.4K | CIRCUITRY DISCREPANCIES AND CHANGES |
| Dec 4, 2025 | P00134 | $18.7K | ADDED KNEE BRACING FOR CONNECTOR BRIDGE |
| Dec 1, 2025 | P00132 | $9.7K | RFI 0617 OPENING 1F020A DOOR TYPE CHANGE |
| Dec 1, 2025 | P00133 | $177.5K | GROUNDING RISER CHANGES FOR PODS |
| Nov 21, 2025 | P00130 | $9.7K | FRAMING AND SLAB EDGE DISCREPANCIES |
| Nov 21, 2025 | P00131 | $37.5K | DEFINITIZES CHANGE ORDERS P00114 AND P00128 FOR MED GAS CHANGES |
| Nov 20, 2025 | P00129 | $58.8K | CMU SUPPORTS |
| Nov 12, 2025 | P00128 | $0 | NO COST CHANGE ORDER IN RELATION TO P00114 MED GAS CHANGES |
| Nov 6, 2025 | P00127 | $128.5K | GENERATOR DAY TANK CONFLICTS |
| Oct 28, 2025 | P00126 | $9.4K | PERIPHERAL TIES AT CHASE |
| Oct 24, 2025 | P00124 | $119.9K | SOMD REINFORCING AT PODS |
| Oct 24, 2025 | P00125 | $155.5K | MEDICAL GAS CIRCUITS AND EQUIPMENT LOCATIONS |
| Oct 21, 2025 | P00121 | $20.1K | IRRIGATION CONTROLLER DATA |
| Oct 21, 2025 | P00122 | $16.6K | GFCI RECEPTACLE CHANGES AND ADDED CIRCUITRY |
| Oct 21, 2025 | P00123 | $9.6K | MISSING EMBEDS AT ELEVATORS |
| Sep 30, 2025 | P00119 | $0 | CHANGE ORDER CYSTO ROOM CLARIFICATION IN RELATION TO P00100 |
| Sep 30, 2025 | P00120 | $0 | CHANGE ORDER FIRE DAMPERS |
| Sep 29, 2025 | P00114 | $391.0K | CHANGE ORDER MED GAS REVISIONS |
| Sep 26, 2025 | P00118 | $50.6K | SIEMENS CONTROL PANELS |
| Sep 25, 2025 | P00116 | $12.3K | PANEL 83B1DPHEA DOOR CONFLICT |
| Sep 25, 2025 | P00117 | $15.4K | ADDED STEEL FOR CLERESTORY WINDOW FRAMING |
| Sep 22, 2025 | P00115 | $0 | CHANGE ORDER FOR REVISED URC-002 IT CHANGES - IN RELATION TO P00098 |
| Sep 10, 2025 | P00113 | $0 | APPROVAL OF MATERIALS STORED OFFSITE |
| Sep 2, 2025 | P00112 | $1.2M | IN RELATION TO P00065 DIRECT AND INDIRECT COSTS AS WELL AS TIME 29 CDS CHANGE ORDER |
| Aug 4, 2025 | P00110 | $8.4K | FLASHING AND WATERPROOFING AT STONE BENCHES/CANOPY BASES AT ENTRY |
| Aug 4, 2025 | P00111 | $82.3K | SUPPORT FOR UP-SWINGING GRAB BARS |
| Jul 31, 2025 | P00109 | $0 | PAYMENT FOR OFFSITE MATERIALS STORED |
| Jul 29, 2025 | P00108 | $79.6K | PNEUMATIC TUBE POWER AND DATA |
| Jul 28, 2025 | P00103 | $15.8K | PRECAST JOINT TOLERANCE RFI 0318 RESPONSE |
| Jul 28, 2025 | P00104 | $4.5K | FRAMING CONDITIONS AT THE WEST SIDE OF AREA F AND A WHERE BUILDING 83 TIES INTO EXISTING BUILDING 74 |
| Jul 28, 2025 | P00105 | $18.4K | GROUND WATER SUMP PUMP DEWATERING |
| Jul 28, 2025 | P00106 | $4.5K | REPAIR DAMAGED CONDUIT PHASE I PARKING |
| Jul 28, 2025 | P00107 | $164.7K | ADDED STEEL FOR ROOFTOP FALL PROTECTION |
| Jul 22, 2025 | P00102 | $6.9K | ADDED FLASHING FOR CURTAIN WALL WEEPS |
| Jul 1, 2025 | P00101 | $6.0K | CONCRETE CHANGES |
| Jun 30, 2025 | P00100 | $25.7K | CYSTO ROOM CHANGES |
| Jun 27, 2025 | P00099 | $7.3K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00075 - SA FOR ELECTRICAL ROOMS ENLARGEMENT PER RESPONSES TO RFIS 0364 AND 0364.1. |
| Jun 26, 2025 | P00095 | $4.9K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00075 - SA FOR ELECTRICAL ROOMS ENLARGEMENT PER RESPONSES TO RFIS 0364 AND 0364.1. |
| Jun 26, 2025 | P00096 | $7.5K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00075 - SA FOR ELECTRICAL ROOMS ENLARGEMENT PER RESPONSES TO RFIS 0364 AND 0364.1. |
| Jun 26, 2025 | P00097 | $171.9K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00075 - SA FOR ELECTRICAL ROOMS ENLARGEMENT PER RESPONSES TO RFIS 0364 AND 0364.1. |
| Jun 26, 2025 | P00098 | $0 | CHANGE ORDER TO INCORPORATE USER REQUESTED CHANGE IT CHANGES |
| Jun 25, 2025 | P00094 | $17.0K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00075 - SA FOR ELECTRICAL ROOMS ENLARGEMENT PER RESPONSES TO RFIS 0364 AND 0364.1. |
| Jun 23, 2025 | P00092 | $12.3K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00075 - SA FOR ELECTRICAL ROOMS ENLARGEMENT PER RESPONSES TO RFIS 0364 AND 0364.1. |
| Jun 23, 2025 | P00093 | $13.2K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00075 - SA FOR ELECTRICAL ROOMS ENLARGEMENT PER RESPONSES TO RFIS 0364 AND 0364.1. |
| Jun 16, 2025 | P00091 | $17.5K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00075 - SA FOR ELECTRICAL ROOMS ENLARGEMENT PER RESPONSES TO RFIS 0364 AND 0364.1. |
| Jun 2, 2025 | P00090 | $0 | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00075 - SA FOR ELECTRICAL ROOMS ENLARGEMENT PER RESPONSES TO RFIS 0364 AND 0364.1. |
| May 13, 2025 | P00089 | $18.1K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00075 - SA FOR ELECTRICAL ROOMS ENLARGEMENT PER RESPONSES TO RFIS 0364 AND 0364.1. |
| Apr 30, 2025 | P00088 | $122.8K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00075 - SA FOR ELECTRICAL ROOMS ENLARGEMENT PER RESPONSES TO RFIS 0364 AND 0364.1. |
| Apr 29, 2025 | P00086 | $20.2K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00075 - SA FOR ELECTRICAL ROOMS ENLARGEMENT PER RESPONSES TO RFIS 0364 AND 0364.1. |
| Apr 29, 2025 | P00087 | $0 | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00075 - SA FOR ELECTRICAL ROOMS ENLARGEMENT PER RESPONSES TO RFIS 0364 AND 0364.1. |
| Apr 28, 2025 | P00084 | $7.3K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00075 - SA FOR ELECTRICAL ROOMS ENLARGEMENT PER RESPONSES TO RFIS 0364 AND 0364.1. |
| Apr 28, 2025 | P00085 | $15.9K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00075 - SA FOR ELECTRICAL ROOMS ENLARGEMENT PER RESPONSES TO RFIS 0364 AND 0364.1. |
| Apr 18, 2025 | P00083 | $53.1K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00075 - SA FOR ELECTRICAL ROOMS ENLARGEMENT PER RESPONSES TO RFIS 0364 AND 0364.1. |
| Apr 14, 2025 | P00081 | $59.5K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00075 - SA FOR ELECTRICAL ROOMS ENLARGEMENT PER RESPONSES TO RFIS 0364 AND 0364.1. |
| Apr 14, 2025 | P00082 | $11.2K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00075 - SA FOR ELECTRICAL ROOMS ENLARGEMENT PER RESPONSES TO RFIS 0364 AND 0364.1. |
| Apr 9, 2025 | P00080 | $68.1K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00075 - SA FOR ELECTRICAL ROOMS ENLARGEMENT PER RESPONSES TO RFIS 0364 AND 0364.1. |
| Apr 4, 2025 | P00079 | $293.4K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00075 - SA FOR ELECTRICAL ROOMS ENLARGEMENT PER RESPONSES TO RFIS 0364 AND 0364.1. |
| Mar 31, 2025 | P00078 | $-16.7K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00075 - SA FOR ELECTRICAL ROOMS ENLARGEMENT PER RESPONSES TO RFIS 0364 AND 0364.1. |
| Mar 21, 2025 | P00077 | $643.9K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00075 - SA FOR ELECTRICAL ROOMS ENLARGEMENT PER RESPONSES TO RFIS 0364 AND 0364.1. |
| Mar 18, 2025 | P00076 | $374.5K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00075 - SA FOR ELECTRICAL ROOMS ENLARGEMENT PER RESPONSES TO RFIS 0364 AND 0364.1. |
| Mar 12, 2025 | P00074 | $-22.1K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00074 - SA FOR CREDIT FOR LEAD LINING THICKNESS FOR CYSTOSCOPY ROOM PER RESPONSE TO RFI 0252. |
| Mar 12, 2025 | P00075 | $97.2K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00075 - SA FOR ELECTRICAL ROOMS ENLARGEMENT PER RESPONSES TO RFIS 0364 AND 0364.1. |
| Mar 11, 2025 | P00073 | $-869.0K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00073 - SA TO REMOVE TT-60 AND ASSOCIATED UTILITIES FROM PROJECT SCOPE. |
| Feb 27, 2025 | P00072 | $4.6M | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00072 - DEFINITIZE CO-02 CO-03 CO-04 CO-06 CO-07 CO-08 CO-16 FOR UNFORESEEN SITE CONDITIONS AND CHANGES IMPACT. |
| Feb 26, 2025 | P00069 | $12.8K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00069 - SA FOR ALL WORK REQUIRED FOR THE ADDITIONAL CIRCUITRY AND PATHWAYS PER RESPONSES TO RFIS 0273.1, 0362 AND 0425. |
| Feb 26, 2025 | P00070 | $12.4K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00070 - SA FOR ALL WORK REQUIRED FOR THE SLIDING DOOR FRAMES FINISH CHANGE PER RESPONSES TO RFIS 0393 AND 0393.1. |
| Feb 26, 2025 | P00071 | $18.7K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00071 - SA FOR ALL WORK REQUIRED FOR THE RELOCATION OF MAC/MVP IN PENTHOUSE AREA B PER RESPONSE TO RFI 0244. |
| Feb 25, 2025 | P00066 | $70.3K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00066 - SA FOR ALL WORK REQUIRED FOR THE INTERIOR WINDOW ELEVATION CLARIFICATION PER RESPONSE TO RFI 0390. |
| Feb 25, 2025 | P00067 | $46.4K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00067 - SA FOR ALL WORK REQUIRED FOR THE LIGHTING CONTROL SYSTEM CHANGES PER RESPONSE TO RFI 0199. |
| Feb 25, 2025 | P00068 | $21.0K | CONSTRUCTION LONG TERM SPINAL CORD INJURY VAMC NORTH DALLAS, TX - MOD P00068 - SA FOR ALL WORK REQUIRED FOR THE CONCRETE GRADE BEAM CHANGES AT GRID LINE 1 PER RESPONSES TO RFIS 0185, 0343.1 AND 0353. |
Estimated positioning window
Oct 25, 2026 – Jan 23, 2027
80/100
Why this recompete signal
Contract timing and recorded acquisition signals at the time of calculation.
Stored score: 80/100. Available recorded signals: 75 points.
- Contract end 2027-03-25 (151 days from calculation)
- +35 points
- 8 historical awards in this buyer and category group
- +15 points
- 265 recorded award transactions
- +10 points
- Latest award action: 2026-09-04
- +5 points
- Parent award identifier recorded
- +0 points
- Solicitation identifier recorded
- +10 points
- Linked official forecast
- +0 points
- Calculated on
- 2026-10-25 10:18:04.631876+00:00
The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.
Rule-based research score; it does not measure your chance of winning.
This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.
Recompete score calculated Oct 25, 2026.
Buyer contacts from matching notices
Matched on exact award/solicitation identifier and awarding agency. Source dates describe the notice, not current contact verification.
| Contact | Role | Published contact methods | Evidence | Source date |
|---|---|---|---|---|
| Deontrinese Dalton | Contract Specialist | deontrinese.dalton@va.gov | Source | Jun 2, 2023 |
| Deontrinese Dalton | Contract Specialist | deontrinese.dalton@va.gov | Source | May 30, 2023 |
| Deontrinese Dalton | Contract Specialist | deontrinese.dalton@va.gov | Source | May 30, 2023 |
| Deontrinese Dalton | Contract Specialist | deontrinese.dalton@va.gov | Source | May 30, 2023 |
| Deontrinese Dalton | Contract Specialist | deontrinese.dalton@va.gov | Source | May 22, 2023 |
| Deontrinese Dalton | Contract Specialist | deontrinese.dalton@va.gov | Source | May 18, 2023 |
| Deontrinese Dalton | Contract Specialist | deontrinese.dalton@va.gov | Source | May 17, 2023 |
| Deontrinese Dalton | Contract Specialist | deontrinese.dalton@va.gov | Source | May 15, 2023 |
| Deontrinese Dalton | Contract Specialist | deontrinese.dalton@va.gov | Source | May 12, 2023 |
| Deontrinese Dalton | Contract Specialist | deontrinese.dalton@va.gov | Source | May 12, 2023 |
| Deontrinese Dalton | Contract Specialist | deontrinese.dalton@va.gov | Source | May 2, 2023 |
| Deontrinese Dalton | Contract Specialist | deontrinese.dalton@va.gov | Source | May 1, 2023 |
| Deontrinese Dalton | Contract Specialist | deontrinese.dalton@va.gov | Source | Apr 28, 2023 |
| Deontrinese Dalton | Contract Specialist | deontrinese.dalton@va.gov | Source | Apr 26, 2023 |
| Deontrinese Dalton | Contract Specialist | deontrinese.dalton@va.gov | Source | Apr 26, 2023 |
| Deontrinese Dalton | Contracting Officer | deontrinese.dalton@va.gov 504-412-3700 x18705 | Source | Mar 6, 2023 |
Research next steps
- Check the linked forecast or SAM for a confirmed solicitation and current timing.
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.