Federal contract award
36C24123N0438
36C24118D0104 36C24123N0438 - PROJECT 631-18-001 EXTEND CHILL WATER THROUGH BUILDINGS 1 & 60
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Veterans Affairs |
| Office | 241-NETWORK CONTRACT OFFICE 01 (36C241) |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Z2DZ — REPAIR OR ALTERATION OF OTHER HOSPITAL BUILDINGS |
| Parent award / vehicle | 36C24118D0104 |
| Set-aside | SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $3.4M |
| Current contract value | $3.4M |
| Potential contract value / ceiling | $3.4M |
| Start date | Mar 15, 2023 |
| Current end date | Mar 24, 2026 |
| Potential end date | Mar 24, 2026 |
| Latest award activity | Apr 23, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Apr 23, 2026 | P00006 | $105.2K | PROJECT 631-18-001 EXTEND CHILL WATER. PCO-012: MODIFY CONDENSER WATER DISTRIBUTION SYSTEM TO INSTALL NEW VALVES AND SENSORS. PCO-013: UPDATE CHILLER SEQUENCE OF OPERATIONS TO TIE IN EQUIPMENT INTO THE BMS. |
| Oct 30, 2025 | P00005 | $30.7K | 36C24118D0104 36C24123N0438 - PROJECT 631-18-001 EXTEND CHILL WATER. PCO-011 IS TO ADD CIRCUIT SETTERS AND OTHER MECHANICAL EQUIPMENT THE A/E FAILED TO ILLUSTRATE IN THE CONTRACT DOCUMENTS FOR THE PROJECT. |
| May 20, 2025 | P00004 | $0 | 36C24118D0104 36C24123N0438 - PROJECT 631-18-001 EXTEND CHILL WATER. PCO-009 MODIFY THE EXISTING PIPE FEEDING AHU AND HUMIDIFIER FOR 10 PSI. PCO-010 DISCOVERED 40 FT. OF ASBESTOS FOR ABATEMENT, FLOOR WHERE THE WORK IS TO OCCUR NEEDED TO BE REPLACED |
| Mar 25, 2025 | P00003 | $0 | 36C24118D0104 36C24123N0438 - PROJECT 631-18-001 EXTEND CHILL WATER THROUGH BUILDINGS 1 & 60. PCO-005 IS TO RE-INSTALL SPRINKLERS IN THE MECHANICAL ROOM. PCO-006 IS TO PROVIDE A FINISH TO THE CONCRETE IN THE MECHANICAL ROOM PER VA DESIGN GUIDE |
Research next steps
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.