Federal contract award

36C24723N0600

679-19-103 CORRECT CRITICAL INFRASTRUCTURE BLDG. 4

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Veterans Affairs
Office247-NETWORK CONTRACT OFFICE 7 (36C247)
NAICS236220 — Commercial and Institutional Building Construction
PSCY1DA — CONSTRUCTION OF HOSPITALS AND INFIRMARIES
Parent award / vehicle36C24719D0024
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$2.1M
Current contract value$2.1M
Potential contract value / ceiling$2.1M
Start dateOct 9, 2023
Current end dateJan 31, 2026
Potential end dateJan 31, 2026
Latest award activityDec 30, 2025
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 13 of 13 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Dec 30, 2025P00014$0ADMIN MODIFICATION TO EXTEND CONTRACT END DATE | 679-19-103 CORRECT CRITICAL INFRASTRUCTURE BLDG. 4
Nov 25, 2025P00013$0ADMIN MODIFICATION TO EXTEND CONTRACT END DATE | 679-19-103 CORRECT CRITICAL INFRASTRUCTURE BLDG. 4
Oct 29, 2025P00012$0ADMIN MODIFICATION TO EXTEND CONTRACT END DATE | 679-19-103 CORRECT CRITICAL INFRASTRUCTURE BLDG. 4
Sep 29, 2025P00011$0ADMIN MODIFICATION TO EXTEND CONTRACT END DATE | 679-19-103 CORRECT CRITICAL INFRASTRUCTURE BLDG. 4
Aug 22, 2025P00010$0ADMIN MODIFICATION TO EXTEND CONTRACT END DATE | 679-19-103 CORRECT CRITICAL INFRASTRUCTURE BLDG. 4
Jul 23, 2025P00009$0ADMIN MODIFICATION TO EXTEND CONTRACT END DATE | 679-19-103 CORRECT CRITICAL INFRASTRUCTURE BLDG. 4
Jul 1, 2025P00008$14.8KBILATERAL MODIFICATION TO COMPLETE ADDITIONAL WORK WITHIN SCOPE | 679-19-103 CORRECT CRITICAL INFRASTRUCTURE BLDG. 4
Jun 26, 2025P00007$0ADMIN MODIFICATION TO EXTEND CONTRACT END DATE | 679-19-103 CORRECT CRITICAL INFRASTRUCTURE BLDG. 4
May 29, 2025P00006$0NO COST EXTENSION MODIFICATION AND UPDATE CLAUSES TO CONFORM TO EXECUTIVE ORDERS | 679-19-103 CORRECT CRITICAL INFRASTRUCTURE BLDG. 4
Apr 24, 2025P00005$0NO COST EXTENSION MODIFICATION | 679-19-103 CORRECT CRITICAL INFRASTRUCTURE BLDG. 4
Apr 10, 2025P00004$0NO COST MOD TO UPDATE CLAUSES IN ACCORDANCE WITH EXECUTIVE ORDERS | 679-19-103 CORRECT CRITICAL INFRASTRUCTURE BLDG. 4
Mar 7, 2025P00003$0NO COST PERIOD OF PERFORMANCE EXTENSION MODIFICATION | 679-19-103 CORRECT CRITICAL INFRASTRUCTURE BLDG. 4
Oct 29, 2024P00002$0PERIOD OF PERFORMANCE EXTENSION #2 DUE TO CONTINUED BACKORDERED ITEMS | 679-19-103 CORRECT CRITICAL INFRASTRUCTURE BLDG. 4