36C25222C0013

CONSTRUCT CAMPUS WATER SOFTENING PLANT PROJECT 550-20-103

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Veterans Affairs
Office252-NETWORK CONTRACT OFFICE 12 (36C252)
NAICS237110 — Water and Sewer Line and Related Structures Construction
PSCZ1DA — MAINTENANCE OF HOSPITALS AND INFIRMARIES
Parent award / vehicleNot reported
Set-asideSERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Pricing typeFIRM FIXED PRICE
Obligations$2.2M
Current contract value$2.2M
Potential contract value / ceiling$2.2M
Start dateDec 9, 2021
Current end dateJun 30, 2026
Potential end dateJun 30, 2026
Latest award activityApr 20, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 3 of 3 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Apr 20, 2026P00010$0P00010 NO COST TIME EXTENSION 550-20-103 CAMPUS WATER SOFTENING PLANT CON
Jun 9, 2025P00009$44.2KP00009 PUMP -WATER HEATER MODIFICATION PROJECT 550-20-103 CONSTRUCT CAMPUS WATER SOFTENING PLANT (CON)
Mar 20, 2025P00008$8.2KP00008: MODIFICATION PROJECT 550-20-103 CONSTRUCT CAMPUS WATER SOFTENING PLANT (CON)

Buyer contacts from matching notices

Matched on exact award/solicitation identifier and awarding agency. Source dates describe the notice, not current contact verification.

ContactRolePublished contact methodsEvidenceSource date
Juan C GaytanContract SpecialistJuan.Gaytan@va.govSourceAug 31, 2021
Juan C GaytanContract SpecialistJuan.Gaytan@va.govSourceAug 17, 2021
Juan C. GaytanContract Specialistjuan.gaytan@va.gov
224-610-3644
SourceAug 10, 2021
Steven T HelmContract SpecialistSteven.Helm@va.govSourceAug 10, 2021
Juan C. GaytanContract Specialistjuan.gaytan@va.gov
224-610-3644
SourceJul 14, 2021

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.