Federal contract award

36C25225C0026

PROJECT 585-21-115: REPLACE BOILER PLANT: REPLACE EXISTING, 40-YEAR OLD BOILERS AND UPGRADE AND ADD EXTENSION TO THE EXISTING BUILDING.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Veterans Affairs
Office252-NETWORK CONTRACT OFFICE 12 (36C252)
NAICS236220 — Commercial and Institutional Building Construction
PSCY1NB — CONSTRUCTION OF HEATING AND COOLING PLANTS
Parent award / vehicleNot reported
Set-asideSERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Pricing typeFIRM FIXED PRICE
Obligations$29.1M
Current contract value$29.1M
Potential contract value / ceiling$29.1M
Start dateMar 18, 2025
Current end dateMay 21, 2027
Potential end dateMay 21, 2027
Latest award activityJul 7, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 7 of 7 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jul 7, 2026P00006$0585-21-115: REPLACE BOILER PLANT-REPLACE 40-YEAR OLD BOILERS & UPGRADE/ADD EXTENSION TO EXISTING BLDG. PER MOD-6 IMPLEMENT EXECUTIVE ORDER EO 14398 (FAR 52.222-90) INTO CONTRACT REQUIREMENTS.
Jun 18, 2026P00005$500.0K585-21-115: REPLACE BOILER PLANT-REPLACE 40-YEAR OLD BOILERS & UPGRADE/ADD EXTENSION TO EXISTING BLDG. PER MOD-5 REMOVE/REPLACE STORM MANHOLE, REVISE SHORING AND PIPE LAYOUT.
Jun 4, 2026P00004$24.8K585-21-115: REPLACE BOILER PLANT-REPLACE 40-YEAR OLD BOILERS & ADD BUILDING EXTENSION. PER MOD-4 PROVIDE TEMP BLOW-DOWN SEPARATOR, CHANGE WALL FROM 3-5/8" TO 6" AND INSTALL TWO 1.5" RPZS.
Jan 7, 2026P00003$64.6K585-21-115: REPLACE BOILER PLANT-REPLACE 40-YEAR OLD BOILERS & UPGRADE/ADD EXTENSION TO EXISTING BLDG. PER MOD-3 INSTALL 4/0 AWG, 15 KV WITH #6 AWG GROUND FROM BLDG 11, SPARE CONDUITS IN MANHOLES & INTO BLDG 2 SWITCHGEAR ROOM FOR TEMP FEEDER F.
Nov 26, 2025P00002$4.1KPROJECT 585-21-115: REPLACE BOILER PLANT - REPLACE EXISTING, 40-YEAR OLD BOILERS AND UPGRADE AND ADD EXTENSION TO THE EXISTING BUILDING. PER MOD-2,TO FURNISH AND INSTALL STRUCTURAL SUPPORT FOR THE BLOCKING OF THE WINDOWSILLS.
Sep 8, 2025P00001$62.8KPROJECT 585-21-115: REPLACE BOILER PLANT: REPLACE EXISTING, 40-YEAR OLD BOILERS AND UPGRADE AND ADD EXTENSION TO THE EXISTING BUILDING. PER MOD-1, REVISE PIPE FROM 30" SDR35PVC TO 30" CLASS IV RCP.
Mar 18, 20250$28.4MPROJECT 585-21-115: REPLACE BOILER PLANT: REPLACE EXISTING, 40-YEAR OLD BOILERS AND UPGRADE AND ADD EXTENSION TO THE EXISTING BUILDING.

Estimated positioning window

Nov 1, 2026 – Jan 30, 2027

Recompete signal:
65/100

Why this recompete signal

Contract timing and recorded acquisition signals at the time of calculation.

Stored score: 65/100. Available recorded signals: 60 points.

Contract end 2027-05-21 (201 days from calculation)
+35 points
1 historical awards in this buyer and category group
+0 points
7 recorded award transactions
+10 points
Latest award action: 2026-07-07
+5 points
Parent award identifier recorded
+0 points
Solicitation identifier recorded
+10 points
Linked official forecast
+0 points
Calculated on
2026-11-01 10:17:53.997580+00:00

The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.

Rule-based research score; it does not measure your chance of winning.

This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.

USAspending award record

. Rule-based research score; positioning dates are estimates.

Recompete score calculated Nov 1, 2026.

Buyer contacts from matching notices

Matched on exact award/solicitation identifier and awarding agency. Source dates describe the notice, not current contact verification.

ContactRolePublished contact methodsEvidenceSource date
Kristi L KluckContract OfficerKristi.Kluck3@va.govSourceFeb 4, 2025
Kristi L KluckContract OfficerKristi.Kluck3@va.govSourceFeb 4, 2025
Kristi L KluckContract OfficerKristi.Kluck3@va.govSourceJan 31, 2025
Kristi L KluckContract OfficerKristi.Kluck3@va.govSourceJan 27, 2025
Kristi L KluckContract OfficerKristi.Kluck3@va.govSourceJan 22, 2025
Kristi L KluckContract OfficerKristi.Kluck3@va.govSourceJan 16, 2025
Kristi L KluckContract OfficerKristi.Kluck3@va.govSourceJan 15, 2025
Kristi L KluckContract OfficerKristi.Kluck3@va.govSourceJan 15, 2025
Kristi L KluckContract OfficerKristi.Kluck3@va.govSourceJan 3, 2025
Kristi L KluckContract OfficerKristi.Kluck3@va.govSourceDec 20, 2024
Kristi L KluckContract OfficerKristi.Kluck3@va.govSourceDec 17, 2024
Kristi L KluckContract OfficerKristi.Kluck3@va.govSourceDec 16, 2024
Kristi L KluckContract OfficerKristi.Kluck3@va.govSourceDec 16, 2024
Kristi L KluckContract OfficerKristi.Kluck3@va.govSourceDec 16, 2024
Kristi KluckContracting OfficerKristi.Kluck3@va.gov
414-844-4879
SourceNov 18, 2024
Kristi KluckContracting OfficerKristi.Kluck3@va.gov
414-844-4879
SourceSep 10, 2024
Kristi KluckContracting OfficerKristi.Kluck3@va.gov
414-844-4879
SourceSep 10, 2024

Research next steps

  1. Check the linked forecast or SAM for a confirmed solicitation and current timing.
  2. Check the stated set-aside against the solicitation and current certifications.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.