Federal contract award

47PA0323F0001

REPLACEMENT OF THE EMERGENCY GENERATOR AT JOSEPH P. ADDABBO FEDERAL OFFICE BUILDING

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyGeneral Services Administration
OfficePBS R00 SPECIAL PROGRAMS DIVISION
NAICS236220 — Commercial and Institutional Building Construction
PSCZ2AA — REPAIR OR ALTERATION OF OFFICE BUILDINGS
Parent award / vehicle47PC0220D0005
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$7.7M
Current contract value$7.7M
Potential contract value / ceiling$7.7M
Start dateNov 14, 2022
Current end dateAug 15, 2026
Potential end dateOct 14, 2026
Latest award activityMar 26, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 6 of 6 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Mar 26, 2026PS0008$7.3KMODIFICATION PS0008 IS HEREBY ISSUED TO ADD ENDOTHERMIC MAT AND GENERATOR REDUCING PINS AND CHANGE THE SUBSTANTIAL COMPLETION DATE TO 8/15/2026 AND FINAL COMPLETION DATE TO 10/14/2026
Jan 14, 2026PS0007$119.6KMODIFICATION PS0007 IS HEREBY ISSUED TO ADD ATS FUNCTIONALITY TESTING AND EXTERIOR LIGHTING IN ACCORDANCE WITH THE REVISED CONSTRUCTION SCOPE OF WORK DATED JANUARY 2, 2026, AND THE ROOF LIGHTING LAYOUT DRAWING NO. A-112 AT A COST OF $119,623.84.
Dec 15, 2025PS0006$0NO COST EXTENSION TO ALLOW A FUNCTIONALITY TEST OF THEIR CURRENT AUTOMATIC TRANSFER SWITCHES PRIOR TO THE FINAL GENERATOR SWITCHOVER.
Sep 25, 2025PS0005$0PERIOD OF PERFORMANCE EXTENSION DUE TO DELAY FROM CITY PERMITS
May 14, 2025PS0004$29.0KMODIFICAITON TO ADD A NEW SITCHGEAR DRIPPAN AND FUEL LINE PAINT AND ALSO EXTEND THE PERIOD OF PERFORMANCE END DATE TO A NEW SUBSTANTIAL COMPLETION DATE OF 9/23/2025 AND FINAL COMPLETION DATE OF 10/22/2025
Feb 10, 2025PS0003$55.6KMODIFICATION FOR ADDITIONAL STRUCTURAL STEEL FOR THE FUEL LINE RETURN SHAFT

Research next steps

  1. Verify whether remaining options may extend performance beyond the current end date.
  2. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.