| Field | Reported value |
|---|---|
| Agency | General Services Administration |
| Office | PBS R00 SPECIAL PROGRAMS DIVISION |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Z2AA — REPAIR OR ALTERATION OF OFFICE BUILDINGS |
| Parent award / vehicle | 47PC0220D0005 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $7.7M |
| Current contract value | $7.7M |
| Potential contract value / ceiling | $7.7M |
| Start date | Nov 14, 2022 |
| Current end date | Aug 15, 2026 |
| Potential end date | Oct 14, 2026 |
| Latest award activity | Mar 26, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 6 of 6 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Mar 26, 2026 | PS0008 | $7.3K | MODIFICATION PS0008 IS HEREBY ISSUED TO ADD ENDOTHERMIC MAT AND GENERATOR REDUCING PINS AND CHANGE THE SUBSTANTIAL COMPLETION DATE TO 8/15/2026 AND FINAL COMPLETION DATE TO 10/14/2026 |
| Jan 14, 2026 | PS0007 | $119.6K | MODIFICATION PS0007 IS HEREBY ISSUED TO ADD ATS FUNCTIONALITY TESTING AND EXTERIOR LIGHTING IN ACCORDANCE WITH THE REVISED CONSTRUCTION SCOPE OF WORK DATED JANUARY 2, 2026, AND THE ROOF LIGHTING LAYOUT DRAWING NO. A-112 AT A COST OF $119,623.84. |
| Dec 15, 2025 | PS0006 | $0 | NO COST EXTENSION TO ALLOW A FUNCTIONALITY TEST OF THEIR CURRENT AUTOMATIC TRANSFER SWITCHES PRIOR TO THE FINAL GENERATOR SWITCHOVER. |
| Sep 25, 2025 | PS0005 | $0 | PERIOD OF PERFORMANCE EXTENSION DUE TO DELAY FROM CITY PERMITS |
| May 14, 2025 | PS0004 | $29.0K | MODIFICAITON TO ADD A NEW SITCHGEAR DRIPPAN AND FUEL LINE PAINT AND ALSO EXTEND THE PERIOD OF PERFORMANCE END DATE TO A NEW SUBSTANTIAL COMPLETION DATE OF 9/23/2025 AND FINAL COMPLETION DATE OF 10/22/2025 |
| Feb 10, 2025 | PS0003 | $55.6K | MODIFICATION FOR ADDITIONAL STRUCTURAL STEEL FOR THE FUEL LINE RETURN SHAFT |
Research next steps
- Verify whether remaining options may extend performance beyond the current end date.