CONSTRUCTION MANAGER AS CONSTRUCTOR(CMC) HVAC AND FIRE ALARM REPLACEMENT, GIGNOUX COURT HOUSE, PORTLAND, ME
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | General Services Administration |
| Office | PBS R1 ACQ MANAGEMENT DIVISION |
| NAICS | 238220 — Plumbing, Heating, and Air-Conditioning Contractors |
| PSC | Z2AA — REPAIR OR ALTERATION OF OFFICE BUILDINGS |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIXED PRICE INCENTIVE |
| Obligations | $40.9M |
| Current contract value | $40.9M |
| Potential contract value / ceiling | $40.9M |
| Start date | Mar 20, 2023 |
| Current end date | Mar 9, 2027 |
| Potential end date | May 11, 2027 |
| Latest award activity | Aug 24, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 38 of 38 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Sep 8, 2026 | PA0037 | $0 | EXECUTES NET-ZERO ADJUSTMENT TO CORRECT THE ACCOUNTING OF ALLOWANCE DRAWDOWNS PREVIOUSLY BUNDLED INCORRECTLY UNDER CR187 ADJUSTMENT IS PERFORMED BY ISSUING A $13,910 CREDIT TO SLIN 002AC AND ADJUSTING CR187 TO APPLY A $13,910 INCREASE TO SLIN 0032AA, |
| Aug 24, 2026 | PS0036 | $66.4K | INCORPORATE MULTIPLE CONTINGENCY TRANSFERS, ALLOWANCE TRANSFERS, AND CHANGE REQUESTS FOR A TOTAL VALUE OF $66,429.00. SCF AND FCD REMAIN THE SAME |
| Jul 10, 2026 | PS0035 | $-14.4K | INCORPORATE CONTINGENCY TRANSFERS, ALLOWANCE TRANSFERS, AND CHANGE REQUESTS FOR A TOTAL VALUE OF - $14,358 |
| Jul 8, 2026 | PS0034 | $0 | INCORPORATING DEI CLAUSE UNDER EO 14398 |
| Jun 9, 2026 | PS0033 | $38.0K | INCORPORATE THE CHANGE REQUESTS FOR THE COMBINED VALUE OF $37,999. |
| May 7, 2026 | PS0032 | $0 | RESEQUENCING PHASES OF THE PROJECT, WHICH UPDATED THE CONTRACT COMPLETION DATE FROM 5/24/27 TO 5/11/27 |
| Apr 30, 2026 | PS0031 | $71.0K | MDP INVESTIGATION & REPAIRS. THIS CHANGE REQUEST INCLUDES ALL LABOR, MATERIALS, AND EQUIPMENT REQUIRED TO COMPLETE THE MAIN SWITCHGEAR SHUTDOWN, INVESTIGATION, RE-ENERGIZE AND REPORTING |
| Apr 7, 2026 | PS0030 | $326.9K | THIS MODIFICATION TO APPROVE MULTIPLE CONTINGENCY TRANSFERS, ALLOWANCE TRANSFERS, AND CHANGE REQUESTS FOR A TOTAL VALUE OF $326,933. |
| Mar 3, 2026 | PS0029 | $122.1K | THIS MODIFICATION TO APPROVE MULTIPLE CONTINGENCY TRANSFERS, ALLOWANCE TRANSFERS, AND CHANGE REQUESTS FOR A TOTAL VALUE OF $122,078. |
| Feb 12, 2026 | PS0028 | $-347.0K | THIS MODIFICATION IS FOR ALLOWANCE TRANSFERS, CONTINGENCY TRANSFERS, AND CHANGE REQUESTS WHICH TOTAL -$347,027 IN CREDITS BACK TO THE GSA. |
| Jan 13, 2026 | PS0027 | $127.8K | THIS MODIFICATION IS FOR MULTIPLE CHANGE REQUESTS AND CONTINGENCY TRANSFERS TOTALING $127,845 |
| Dec 2, 2025 | PS0026 | $163.5K | THIS MODIFICATION INCORPORATES MULTIPLE CRS, ATS, AND CTS. |
| Oct 31, 2025 | PS0025 | $117.5K | THIS MODIFICATION ENCOMPASSES THREE CHANGE REQUESTS TOTALING $117,472 |
| Oct 15, 2025 | PS0024 | $0 | THIS MODIFICATION IS FOR ALLOWANCE AND CONTINGENCY TRANSFERS THAT HAVE ALREADY BEEN AWARDED ON CONTRACT AND THEREFORE THIS IS A $0 MOD. THE CONSTRUCTION CONTINGENCY IS LOWERED FROM $855,185 TO $788,901. |
| Sep 23, 2025 | PS0023 | $12.4K | THIS MODIFICATION IS FOR CR157, PHASE 1 HOT WATER PUMP EVENT IN THE AMOUNT OF $12,445 |
| Aug 21, 2025 | PS0022 | $395.3K | THIS MODIFICATION IS FOR MULTIPLE CRS, CTS, AND ATS FOR THE COMBINED VALUE OF $395,312.00 |
| Jul 30, 2025 | PS0021 | $-169.9K | THIS A CONTINGENCY TRANSFER AND CREDIT MODIFICATION IN THE AMOUNT OF $-169,930 |
| Jul 8, 2025 | PS0020 | $501.4K | THIS MOD IS FOR MULTIPLE CRS WHICH TOTALS $501,393 |
| May 27, 2025 | PS0019 | $456.4K | MULTIPLE CR'S |
| Apr 23, 2025 | PS0018 | $69.9K | MULTIPLE CR'S |
| Mar 28, 2025 | PS0017 | $0 | IMPLEMENTATION OF CDS AND DRONES CLAUSE. |
| Mar 20, 2025 | PS0016 | $302.5K | MULTIPLE CHANGE REQUESTS INCLUDING THE TEMP CHILLER WHICH WILL HELP KEEP THE CONSTRUCTION SCHEDULE MOVING |
| Mar 10, 2025 | PS0015 | $606.6K | MULTIPLE CHANGE REQUESTS THAT ARE REQUIRED TO KEEP PROJECT SCHEDULE MOVING FORWARD. |
| Feb 11, 2025 | PS0014 | $-5.7K | MULTIPLE $0.00 ALLOWANCE AND CONTINGENCY TRANSFERS THAT CONSIGLI HAS MADE USING THEIR CURRENT ALLOWANCE AND CONTINGENCY FUNDS. THE MODIFICATION ALSO PROCESSES TWO CREDITS FOR FCU SPRING HANGERS AND UNDERSLAB PIPE CLEANING. |
| Jan 30, 2025 | PS0013 | $714.4K | PDL MOD TO CORRECT FIRESTOPPING DEFICIENCIES IN SHAFT AND MASONRY. |
| Dec 20, 2024 | PS0012 | $612.8K | MULTIPLE CHANGE REQUESTS INCORPORATED INTO THIS MODIFICATION. CR077 WILL BE A PDL NTE $140,818. THE REMAINING CRS TOTAL TO $471,995. CONTRACT COMPLETION REMAINS UNCHANGED. TOTAL AMOUNT IS $612,813 |
| Nov 14, 2024 | PS0011 | $40.3K | THIS MODIFICATION IS TO INCORPORATE UNFORSEEN WORK ASSOCIATED WITH CHANGE REQUESTS 35, 37, 39, 40, 44, 48, 49, AND 50. THE COST OF THIS MODIFICATION IS $40,279.00. ALL OTHER TERMS AND CONDITIONS OF THIS CONTRACT REMAIN THE SAME. |
| Oct 11, 2024 | PS0009 | $392.8K | THIS MODIFICATION IS TO ADD WORK FOR UNFORESEEN CIRCUMSTANCES TO THE GIGNOUX FEDERAL COURTHOUSE HVAC AND FIRE ALARM PROJECT IN PORTLAND, ME. THE COST OF THIS WORK WILL BE $392,796.00. |
| Oct 11, 2024 | PS0010 | $146.8K | CONTRACT 47PB0023C0008, GIGNOUX HVAC & FIRE ALARM CMC PROJECT IN PORTLAND, ME IS MODIFIED TO INCORPORATE RETURN AIR DUCT INSULATION, DUCTWORK AND ELECTRICAL CHANGES, EXISTING EXHAUST HOOD DEMO, FABRIC CEILING PANELS AND ALTERNATE HUMIDIFIER EQUIPMENT |
| Sep 27, 2024 | PS0008 | $2.9K | MODIFICATION TO INCORPORATE VRF EMERGENCY FIX, ROOF PENETRATIONS TO SCOPE OF WORK FOR THE GIGNOUX HVAC AND FIRE ALARM PROJECT IN PORTLAND, ME. |
| Aug 16, 2024 | PS0007 | $364.1K | NOT TO EXCEED AMOUNT FOR CHANGE REQUEST #006 ADDED TO THE GIGNOUX HVAC AND FIRE ALARM CMC PROJECT AT THE GIGNOUX COURTHOUSE IS PORTLAND, ME. |
| May 23, 2024 | PS0006 | $9.3M | OPTION EXERCISE FOR PHASES 4 AND 5 OF THE GIGNOUX COURTHOUSE HVAC AND FIRE ALARM PROJECT IN PORTLAND, ME |
| Apr 10, 2024 | PS0005 | $-18.3K | MODIFICATION TO CREDIT BACK $18,266 OFF THE CONTRACT FOR LABOR AND MATERIALS UNUSED IN THE PERFORMANCE OF PS0001 FOR THE HVAC AND FIRE ALARM PROJECT AT THE GIGNOUX COURTHOUSE IN PORTLAND, ME. |
| Mar 29, 2024 | PS0004 | $23.3M | MODIFICATION TO EXERCISE OPTIONAL CLIN 0002 FOR PHASES 1, 2 AND 3 OF THE GMP FOR THE GIGNOUX HVAC AND FIRE ALARM PROJECT AT THE GIGNOUX COURTHOUSE IN PORTLAND, ME. |
| Mar 13, 2024 | PS0003 | $0 | MODIFICATION TO INCREASE THE GMP DUE TO SCOPE INCREASES FROM $24,895,442.26 TO $32,620,415.49 ON THE GIGNOUX HVAC AND FIRE ALARM PROJECT CMC CONTRACT AT THE GIGNOUX COURTHOUSE IN PORTLAND, ME. |
| Jan 31, 2024 | PS0002 | $2.5M | MODIFICATION TO INCORPORATE THE EARLY RELEASE PACKAGE WORK FOR THE GIGNOUX HVAC AND FIRE ALARM PROJECT AT THE GIGNOUX COURTHOUSE IN PORTLAND, ME. |
| Nov 14, 2023 | PS0001 | $111.3K | MODIFICATION TO ADD INVESTIGATION SERVICES TO THE GIGNOUX HVAC AND FIRE ALARM PROJECT AT THE GIGNOUX COURTHOUSE IN PORTLAND, ME. |
| Mar 20, 2023 | 0 | $540.8K | CONSTRUCTION MANAGER AS CONSTRUCTOR(CMC) HVAC AND FIRE ALARM REPLACEMENT, GIGNOUX COURT HOUSE, PORTLAND, ME |
Estimated positioning window
Oct 25, 2026 – Jan 23, 2027
75/100
Why this recompete signal
Contract timing and recorded acquisition signals at the time of calculation.
Stored score: 75/100. Available recorded signals: 70 points.
- Contract end 2027-05-11 (198 days from calculation)
- +35 points
- 2 historical awards in this buyer and category group
- +10 points
- 38 recorded award transactions
- +10 points
- Latest award action: 2026-08-24
- +5 points
- Parent award identifier recorded
- +0 points
- Solicitation identifier recorded
- +10 points
- Linked official forecast
- +0 points
- Calculated on
- 2026-10-25 10:18:04.631876+00:00
The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.
Rule-based research score; it does not measure your chance of winning.
This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.
Recompete score calculated Oct 25, 2026.
Buyer contacts from matching notices
Matched on exact award/solicitation identifier and awarding agency. Source dates describe the notice, not current contact verification.
| Contact | Role | Published contact methods | Evidence | Source date |
|---|---|---|---|---|
| Sebastian Asaro | Contact | sebastian.asaro@gsa.gov 6463980455 | Source | Dec 16, 2022 |
| Paul Murphy | Contact | Paul.murphy@gsa.gov | Source | Dec 16, 2022 |
| Sebastian Asaro | Contact | sebastian.asaro@gsa.gov 6463980455 | Source | Dec 14, 2022 |
| Paul Murphy | Contact | Paul.murphy@gsa.gov | Source | Dec 14, 2022 |
| Sebastian Asaro | Contact | sebastian.asaro@gsa.gov 6463980455 | Source | Nov 23, 2022 |
| Paul Murphy | Contact | Paul.murphy@gsa.gov | Source | Nov 23, 2022 |
| Michele Valenza | Contact | michele.valenza@gsa.gov 6175658508 | Source | Nov 8, 2022 |
| Paul Murphy | Contact | Paul.murphy@gsa.gov | Source | Nov 8, 2022 |
| Michele Valenza | Contact | michele.valenza@gsa.gov 6175658508 | Source | Nov 4, 2022 |
| Paul Murphy | Contact | Paul.murphy@gsa.gov | Source | Nov 4, 2022 |
| Michele Valenza | Contact | michele.valenza@gsa.gov 6175658508 | Source | Sep 28, 2022 |
Research next steps
- Check the linked forecast or SAM for a confirmed solicitation and current timing.
- Verify whether remaining options may extend performance beyond the current end date.