Federal contract award
47PB0025F0372
TASK ORDER 47PB0025F0372 IS AWARDED TO OAK POINT ASSOCIATES IN THE AMOUNT OF $49,864.60. THE PROJECT IS FOR THE DESIGN OF THE MOAKLEY DATA CENTER COOLING SYSTEM, AT THE MOAKLEY COURTHOUSE IN BOSTON, MA.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | General Services Administration |
| Office | PBS R1 ACQ MANAGEMENT DIVISION |
| NAICS | 541330 — Engineering Services |
| PSC | C1AZ — ARCHITECT AND ENGINEERING- CONSTRUCTION: OTHER ADMINISTRATIVE FACILITIES/SERVICE BUILDINGS |
| Parent award / vehicle | 47PB0025D0014 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $49.9K |
| Current contract value | $49.9K |
| Potential contract value / ceiling | $49.9K |
| Start date | Aug 11, 2025 |
| Current end date | Apr 13, 2026 |
| Potential end date | Apr 13, 2026 |
| Latest award activity | Mar 10, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Mar 10, 2026 | PS0003 | $0 | PROJECT IS EXTENDED TO 04/13/2027 AT NO COST. PROJECT IS FOR THE DESIGN OF THE MOAKLEY DATA CENTER AT THE MOAKLEY FEDERAL COURTHOUSE IN BOSTON, MA. ALL OTHER TERMS REMAIN UNCHANGED. |
| Jan 8, 2026 | PS0002 | $0 | MODIFICATION IS EXTENDED AT NO-COST TO 03/13/2026. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. |
| Oct 31, 2025 | PS0001 | $0 | PS0001 EXTENDS THE CONTRACT AT NO-COST TO 01/02/2026. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. |
| Aug 19, 2025 | 0 | $49.9K | TASK ORDER 47PB0025F0372 IS AWARDED TO OAK POINT ASSOCIATES IN THE AMOUNT OF $49,864.60. THE PROJECT IS FOR THE DESIGN OF THE MOAKLEY DATA CENTER COOLING SYSTEM, AT THE MOAKLEY COURTHOUSE IN BOSTON, MA. |