Federal contract award

47PB0123F0030

NEPA MANAGEMENT AT LOCATIONS IN VERMONT

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyGeneral Services Administration
OfficePBS R1 NATIONAL CONTRACTS TEAM
NAICS541620 — Environmental Consulting Services
PSCB510 — Environmental Studies and Assessments
Parent award / vehicle47QRAA18D002R
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$1.5M
Current contract value$1.5M
Potential contract value / ceiling$1.5M
Start dateMar 27, 2023
Current end dateJun 22, 2026
Potential end dateJun 22, 2026
Latest award activityApr 15, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 9 of 9 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Apr 15, 2026PS0012$54.3KTHIS MODIFICATION PS0012 INCLUDESRFP#7 BAT SURVEY AND RFP#8 PHASE 1B SECOND MOBILIZATION FOR ARCHAEOLOGICAL SURVEY, A TOTAL INCREASE TO THE CONTRACT OF $54,335.91.
Mar 6, 2026PS0011$39.5KTHIS MOD PS0011 IS FOR ADDITIONAL PERMITS, VT DEC STREAM AND ADDRESS CHANGE
Jan 29, 2026PS0010$14.7KTHIS MOD ADDS A STREAM PERMIT REQUIRED BY THE VERMONT DEPARTMENT OF ENVIRONMENTAL CONSERVATION AND US ARMY CORPS OF ENGINEERS.
Oct 16, 2025PS0009$56.0KMOD PS0009 IS FOR REQUEST FOR EQUITABLE ADJUSTMENT FOR ADDITIONAL TECHNICAL HOURS FOR THE NEPA WORK RELATED TO THE VERMONT'S LPOE.
Sep 11, 2025PS0008$34.1KTHIS MOD PS0008 IS FOR WETLAND PERMITTING AT RICHFORD LPOE, VERMONT
May 28, 2025PS0007$25.2KTHIS MODIFICATION IS ADDITIONAL WORK FOR THE NEPA PROCESS FOR NORTON AND RICHFORD LPOE, VERMONT .
May 20, 2025PS0006$192.5KTHIS MODIFICATION ADDES ADDTIONAL WORK AND MEETINGS TO SUPPORT THE NEPA PROCESS FOR THE 5 VT LPOE SITES.
Mar 31, 2025PS0005$0THIS MODIFICATION HAS THE CONTRACTOR RESUME WORK FOR THE LPOE'S, VT
Mar 4, 2025PS0004$0THIS MODIFICATION PS0004 IS TO STOP WORK ON ALL VERMONT LPOE'S REGARDING NEPA.

Research next steps

  1. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.